Barbera v. Sokol

101 Cal. App. 3d 725, 161 Cal. Rptr. 843, 1980 Cal. App. LEXIS 1435
CourtCalifornia Court of Appeal
DecidedFebruary 1, 1980
DocketCiv. 55623
StatusPublished
Cited by5 cases

This text of 101 Cal. App. 3d 725 (Barbera v. Sokol) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Barbera v. Sokol, 101 Cal. App. 3d 725, 161 Cal. Rptr. 843, 1980 Cal. App. LEXIS 1435 (Cal. Ct. App. 1980).

Opinion

Opinion

JEFFERSON (Bernard), J.

This is an action by a masonry subcontractor against an owner-builder and general contractor for damages and attorney fees flowing from a breach of a written construction contract. By second amended complaint, plaintiff masonry subcontractor Joseph Barbera, doing business as A. M. Barbera & Son, also alleged causes of action on theories of an open book account and quantum meruit. Plaintiff also sought, as additional relief, foreclosure of a mechanic’s lien and recovery on a bond. Named as defendants were Erwin H. Sokol, individually and doing business as E. H. Sokol Construction Company, Arthur and Frances Sokol, Continental Auxiliary Company, a California corporation, and Bank of America National Trust & Savings Association. As a fifth cause of action, plaintiff sought recovery on performance bonds executed by defendant Houston General Insurance Company. 1

The defendants answered the second amended complaint, denying liability. Defendants Erwin H. Sokol, individually and doing business as E. H. Sokol Construction Company, and Arthur and Frances Sokol filed a cross-complaint against plaintiff for damages for breach of the *728 same construction contract by plaintiff and for damages on a performance bond against cross-defendant Financial Indemnity Company, a California corporation. It was further alleged in the cross-complaint that the construction contract contained a liquidated damages clause obligating plaintiff to pay $400 per day for delays in contractual performance, and that plaintiff cross-defendant was liable for breach of this clause of the contract.

Trial was by the court, sitting without a jury. Judgment was awarded to plaintiff on the second amended complaint and also to plaintiff and Financial Indemnity Company as cross-defendants with respect to the cross-complaint. Plaintiff was awarded damages in the sum of $21,270.86, together with interest and costs, and attorney fees of $5,000, recoverable from defendants Erwin H. Sokol, individually, and doing business as E. H. Sokol Construction Company, and Arthur and Frances Sokol. Plaintiff’s relief also included a mechanic’s lien against the subject real property, located at 1697 Pacific Avenue in Venice.

Defendants have appealed from the judgment. Plaintiff filed a cross-appeal from that portion of the judgment awarding attorney fees of $5,000. 2

In essence, defendants make one claim on this appeal—that the trial court, after hearing the evidence, should have ruled that the liquidated damages clause contained in the construction contract was valid as a matter of law, and that its failure to do so requires a remand of the case for the trial court to compute the amount of liquidated damages defendants are entitled to recover from plaintiff on the cross-complaint.

I

The Procedural History and Factual Summary

We summarize the evidence adduced below, bearing in mind that “[i]n resolving the issue of the sufficiency of the evidence, we are bound by the established rules of appellate review that all factual matters will be viewed most favorably to the prevailing party [citations] and in support of the judgment [citation]. All issues of credibility are likewise *729 within the province of the trier of fact.” (Nestle v. City of Santa Monica (1972) 6 Cal.3d 920, 925 [101 Cal.Rptr. 568, 496 P.2d 480].)

In September 1972, defendant Erwin H. Sokol was an experienced general contractor who was planning to build a 92-unit apartment house, hotel and related facilities in Venice, California, to be owned by Sokol and members of his family. The building was to be 300 feet long, about 65 feet wide, and 3 stories high, and was to be located over a semisubterranean garage.

Plaintiff Joseph Barbera, an experienced masonry subcontractor, made a bid of $85,000 for the masonry work. Sokol rejected the bid, stating it was too high. The parties discussed the project again in early 1973, and Barbera told Sokol that the easiest way to perform the masonry and carpentry work on the building was for the two trades to work together in rotation, each completing a half floor at a time. In March 1973, Sokol asked Barbera to submit another bid for the masonry work. Barbera did so and the parties reached a tentative agreement. Sokol and Barbera met on April 1. According to Barbera, there was no discussion at that time of how many working days Barbera would require to complete his part of the work. Barbera testified that he went to the job site on May 29, 1973, but noted that the site was not yet ready for his masonry crew because of some improper work done by the concrete subcontractor, the previous subcontractor on the job. Barbera had been told by Sokol of the difficulties the latter as owner builder had been having as the result of delays and damage caused by previous subcontractors.

On June 5, 1973, Barbera met with Sokol to discuss the contract, which was executed by both parties on that date and provided for a contract price of $83,600 for the masonry work. The contract, prepared by Sokol, was in part a standardized and printed building contract. Included therein, in typewriting, was a section 6, entitled “Special Provisions” and which provided, in pertinent part, that “Subcontractor hereby agrees to commence construction of the project at once upon notice from the Owner, and at all times, have a crew of men large enough to keep up with the other trades, and not in any way cause to slow down, slow down the completion of the project. If for any reason there is a delay in the completion of the project caused by the masonry subcontractor, then in that event, the foregoing $400.00 per day sum represents the amount of liquidated damages which the parties hereto *730 have agreed upon as compensation to the contractor, owners, for any delay in the completion of construction pursuant to this subcontract in excess of said 14 day period, and the parties acknowledge that said sum represents a fair and equitable amount of compensation of such delay in view of the impossibility of ascertaining actual damages.”

It is significant that the figure “14” contained in section 6, was not typed but was written into a blank space by hand. The parties read and discussed the contract on this occasion; there was agreement concerning certain deletions and an addendum was written out at the end of the contract in Sokol’s handwriting that “Masonry contractor agrees to order all materials within two days after the execution of this Contract.” The parties discussed the “time is of the essence” provision, and the amount of time Barbera would need to complete his work. Here there was a conflict in the evidence. Barbera testified that he told Sokol he would need 14 days (or 2 weeks) approximately to do each floor of the building; Sokol testified that Barbera had told him it would take 14 days to do the 3 floors. Barbera testified that, at the time he executed the contract, the number 14 had not been inserted, and that the first time he learned of the “14 day” provision was late in August 1973.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Utility Consumers' Action Network, Inc. v. AT&T Broadband of Southern Cal., Inc.
37 Cal. Rptr. 3d 827 (California Court of Appeal, 2006)
Hein v. Bobbitt (In Re Hein)
60 B.R. 769 (S.D. California, 1986)
Hong v. Somerset Associates
161 Cal. App. 3d 111 (California Court of Appeal, 1984)
Westinghouse Electric Corp. v. County of Los Angeles
129 Cal. App. 3d 771 (California Court of Appeal, 1982)
Eddy v. Lee
312 N.W.2d 326 (North Dakota Supreme Court, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
101 Cal. App. 3d 725, 161 Cal. Rptr. 843, 1980 Cal. App. LEXIS 1435, Counsel Stack Legal Research, https://law.counselstack.com/opinion/barbera-v-sokol-calctapp-1980.