Barasch v. Pennsylvania Public Utility Commission

521 A.2d 482, 104 Pa. Commw. 52, 1987 Pa. Commw. LEXIS 1940
CourtCommonwealth Court of Pennsylvania
DecidedFebruary 18, 1987
Docket22 C.D. 1986 and 58 C.D. 1986
StatusPublished
Cited by5 cases

This text of 521 A.2d 482 (Barasch v. Pennsylvania Public Utility Commission) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Barasch v. Pennsylvania Public Utility Commission, 521 A.2d 482, 104 Pa. Commw. 52, 1987 Pa. Commw. LEXIS 1940 (Pa. Ct. App. 1987).

Opinion

Opinion by

Judge Barry,

This appeal results from an order of the Pennsylvania Public Utility Commission (PUC or Commission) which granted certain exceptions of Philadelphia Electric Company (PECO) filed with respect to the recommended opinion of Administrative Law Judge Allison Turner (the ALJ). The granting of the exceptions had the practical effect of permitting PECO to complete construction of Limerick Unit No. 2, a nuclear-powered electric generating station.

The PUC order involved declared specifically that “unconditioned completion of construction of Limerick Unit No. 2 is not in the public interest,” but adjured further that PECO notify the Commission within thirty *55 days regarding “whether it accepts and agrees to be bound by the terms and conditions of [certain] cost containment plans . . . .” Those plans, compliance with which has since been agreed to by PECO, were formulated by the PUC in its opinion accompanying the order, and were articulated as prerequisites to Limerick 2 being in the public interest, and hence to the PUC’s approval of continued construction of Limerick 2.

Petitioners, the Office of the Consumer Advocate (OCA); the Governors Energy Council (GEC); and the Consumers Education and Protective Association (CEPA), have petitioned for review from the PUC order.

1. Prior Related Proceedings and Origin of the Present Litigation

The construction of the nuclear reactors at Limerick has been the subject of continuing litigation since 1979. Most notably, after concerns had been raised with respect to the wisdom of simultaneous construction of Limerick Units 1 and 2, the PUC in 1982 ordered PECO to either suspend or cancel construction of the second unit. After a challenge by PECO to the authority of the PUC to issue such an order, the Supreme Court confirmed that the PUC indeed possessed constructive power to render such an order by refusing to approve securities issues for the funding of the project. 1 PECO then did, in fact, suspend construction.

As completion of Unit 1 approached, concerns with respect to Unit 2 continued, and public hearings were held by the House Select Committee to Investigate Limerick 2 to assess the wisdom of completing the unit. In apparent response to this legislative concern, the *56 PUC on August 7, 1984, ordered PECO to show cause why the completion of Limerick 2 would be in the public interest. The order set forth four issues raised by the spectre of completion of the unit: (1) “[the] serious question [] . . . regarding the need for the additional generating capacity represented by Unit 2”; (2) “the cost effectiveness of Unit 2 as compared to other alternatives”; (3) “the effect upon PECOs financial health and its ability to provide safe and adequate service at reasonable rates”; and (4) “the potential effect of the cost burden of Unit 2 upon PECOs existing customer base.” Show Cause Order at 2, reproduced in PUC Decision, No. 1-840381, December 5, 1985, at 6. The Order then directed the institution of an investigation and the examination of the following specific issues:

1. Is construction of Unit 2 necessary for PECO to maintain adequate reserve margins?
2. Are there less costly alternatives—such as cogeneration, additional conservation measures, or purchasing power from neighboring utilities or the [Pennsylvania-New Jersey-Maryland] interchange—for PECO to obtain power or decrease consumption?
3. How will the capital requirements necessary to complete Unit 2 affect PECOs financial health and its ability to provide adequate service?
4. Should the Commission reject any securities filing; or impose any other appropriate remedy, to guarantee the cancellation of Unit 2?
5. If Unit 2 is cancelled, what, if any, percentage of the sunk costs should PECO be permitted to recover from its rate payers?
6. If construction of Unit 2 is found to be in the public interest, should the Commission *57 adopt an “Incentive/Penalty Plan” as an inducement to cost efficient and timely construction?

Show Cause Order at 2-3, reproduced in id. at 6-7.

Hearings were thereupon convened before an ALJ, and twenty-three days of such hearings were held from January to April, 1985. At those hearings the foregoing issues were addressed by way of documentary and oral testimony adduced by PECO and adversary groups, some of which groups are pursuing the present appeal. After making extensive findings of fact, the ALJ concluded that “completion of Limerick 2 is not in the public interest,” explaining that conclusion as follows:

[This ALJ has been] persuaded that Limerick 2s capital and operating costs will most probably be higher than projected by PECO, and that in any event, the alternatives [to completion] presented . . . would be more economically beneficial than completion of Limerick 2. The impact of Limerick 2 s capital costs alone would have a strong adverse impact on PECO’s rate payers, its customer base, and its sales and revenue flows.

ALJ Decision at 407. The ALJ thus recommended against the approval of “any securities certificates the proceeds of which are to be used in whole or in part for Limerick 2.” Id. at 420.

PECO thereafter filed exceptions to the decision, arguing, among other things, that completion of the unit was in feet in the public interest and that “any uncertainties concerning the costs/benefits of Unit No. 2 [could] be eliminated by a reasonable cost containment plan.” See PECO Exceptions at 3. Such a plan had been advocated by several parties during the proceedings and had been characterized by the ALJ as a necessary ingredient of a Limerick 2 completion scenario.

After PECO had filed its exceptions and the parties had briefed the case before the PUC, the legislature en *58 acted legislation which supplied the Commission with the express authority to cancel a plant. That legislation mandated that the Commission was to order cancellation when such unit was found not to be in the public interest.

2. PUC Decision

In a decision dated December 5, 1985, the PUC granted in part and denied in part PECOs exceptions. First re-assessing the evidence, the PUC found that “PECO may need additional base load capacity as early as 1992,” but pointedly refrained from making any “finding as to how that need should be met.” The PUC then went on to consider the alternatives to completion. 2 In this respect, the PUC concluded that “there is *59 no clear best choice among the alternatives analyzed.” PUC Decision at 49 (emphasis in original). Against this backdrop, the PUC (1) found that “there may be present value benefits to customers

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cresco, Inc. v. Pennsylvania Public Utility Commission
622 A.2d 997 (Commonwealth Court of Pennsylvania, 1993)
Beers v. UN. COMP. BD. of REV.
546 A.2d 1260 (Commonwealth Court of Pennsylvania, 1988)
SME Bessemer Cement, Inc. v. Pennsylvania Public Utility Commission
540 A.2d 1006 (Commonwealth Court of Pennsylvania, 1988)
East Rockhill Township v. Pennsylvania Public Utility Commission
540 A.2d 600 (Commonwealth Court of Pennsylvania, 1988)
E. Rockhill T. v. Pa. Puc
540 A.2d 600 (Commonwealth Court of Pennsylvania, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
521 A.2d 482, 104 Pa. Commw. 52, 1987 Pa. Commw. LEXIS 1940, Counsel Stack Legal Research, https://law.counselstack.com/opinion/barasch-v-pennsylvania-public-utility-commission-pacommwct-1987.