Barasch v. Pennsylvania Public Utility Commission

515 A.2d 651, 101 Pa. Commw. 76, 1986 Pa. Commw. LEXIS 2564
CourtCommonwealth Court of Pennsylvania
DecidedSeptember 29, 1986
DocketAppeals, 493 C.D. 1985, 533 C.D. 1985 and 655 C.D. 1985
StatusPublished
Cited by12 cases

This text of 515 A.2d 651 (Barasch v. Pennsylvania Public Utility Commission) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Barasch v. Pennsylvania Public Utility Commission, 515 A.2d 651, 101 Pa. Commw. 76, 1986 Pa. Commw. LEXIS 2564 (Pa. Ct. App. 1986).

Opinion

Opinion by

President Judge Crumlish, Jr,

The Office of Consumer Advocate (OCA), the City of Philadelphia (City) and eight suburban Philadelphia municipalities (municipalities) 1 separately appeal a Pennsylvania Public Utility Commission (Commission) order granting Philadelphia Electric Company (PECO) a base rate increase of $149,636,000. These appeals were consolidated for argument and disposition. We affirm the Commission order as to all three appeals.

On April 27, 1984, PECO filed Supplement No. 23 to Tariff Electric—Pa. P.U.C. No. 26, to become efiec *79 tive January 27, 1985. This supplement contained a base rate increase of approximately $252,000,000 predicated upon historic and future test years ending December 31, 1983, and December 31, 1984, respectively. After complaints were filed against PECOs proposed rate increase by the OCA, the City, the municipalities, and other parties, the Commission suspended Supplement No. 23 for seven months and instituted an investigation into its lawfulness and reasonableness. Following public hearings, an administrative law judge (ALJ) issued a November 27, 1984 recommended decision. Ruling upon exceptions to the ALJs recommended decision, the Commission on January 25, 1985, issued the order granting the $149,636,000 rate increase 2 from which the appeals now before us were taken.

Our scope of review of a Commission order in a rate case is limited to determining whether the Commission violated constitutional rights, committed an error of law, or made findings of fact that are not supported by substantial evidence. Green v. Pennsylvania Public Utility Commission, 81 Pa. Commonwealth Ct. 55, 473 A.2d 209 (1984), aff'd sub nom., Barasch v. Pennsylvania Public Utility Commission, 507 Pa. 430, 490 A.2d 806 (1985).

OCA Appeal

Surplus on Cancellation of Construction Contracts

In its appeal, the OCA challenges the Commissions decision not to deduct from PECOs rate base a surplus of $7,448,362 in payments received from General Atomic Corporation (GAC) in settlement of GACs can *80 cellation of contracts for construction of two nuclear generating stations, Fulton and Summit, in which PECO had invested funds. 3

The OCA contends that the Commission erred in not deducting the $7,448,362 surplus from rate base because these monies were not supplied by investors. We disagree.

The ALJ and the Commission both declined to reduce PECOs rate base to reflect the surplus of the GAC payments because the cancelled construction projects were funded entirely by PECOs shareholders, not by its ratepayers. 4 They cited our decision in Philadelphia Suburban Water Co. v. Pennsylvania Public Utility Commission, 58 Pa. Commonwealth Ct. 272, 427 A.2d 1244 (1981), where we held that the Commission erred by crediting to a utility’s revenues surplus proceeds on the sale of land acquired through shareholder capital.

The OCA urges that Philadelphia Suburban Water does not control because this case involves cancelled depreciable assets, the construction costs of which could be recovered from ratepayers. Cohen v. Pennsylvania Public Utility Commission, 90 Pa. Commonwealth Ct. 98, 494 A.2d 58 (1985). Conversely, Philadelphia Suburban Water dealt with a sale of land, a loss on which we therein stated would not be the responsibility of ratepayers. The OCA asserts that, as PECOs *81 ratepayers would have borne any unrecovered costs for the cancelled projects, they should also benefit from a gain on cancellation. We do not agree.

Although utilities have been allowed to recover the prudently incurred construction costs of cancelled nuclear power projects from ratepayers as an amortized expense, Cohen, this is a narrow exception to the general rule that ratepayers do not compensate a utility for a loss on an investment. The purpose of this exception is to avoid the severely debilitating effects upon a utility’s fiscal condition and, concomitantly, its ability to serve the public, which would result if the multi-million dollar funding of a cancelled nuclear power project’s construction was not recouped. These monies are recovered from ratepayers on the theory that they are a necessary aspect of a utility’s obligation to provide public service. A gain on an investment, however, should benefit those who have provided the funding. This is the principle upon which our economic system was built. It is also the principle we relied upon in Philadelphia Suburban Water and which controls in this case.

The OCA further argues that the Commission’s refusal to deduct the surplus of the GAC payments was arbitrary and capricious in light of the treatment accorded two other items in the Commission’s order. This argument likewise fails.

The Commission permitted PECO to recover $2,296,000 in losses incurred when its contractor can-celled construction of a uranium mining project. The OCA claims that this is inconsistent with the denial to ratepayers of the benefit of the gain on GAC’s contract cancellation. As we noted above, however, the recovery of cancelled construction project costs is necessary to *82 ensure that a utility remains fiscally sound and able to adequately serve the public. 5

The OCA also points to the Commissions deduction from PECOs rate base of $6.9 million received from a third party, Hercules Corporation (Hercules), in connection with the sale of tax benefits associated with the Salem Unit No. 2 nuclear generating station. It claims that the treatment of these monies is irreconcilable with the Commissions treatment of the GAC surplus. We disagree. The payments by Hercules were in compensation for the lost time value of monies related to the receipt of the Salem Unit No. 2 tax benefits. In contrast, the payments by GAC were in satisfaction of the investment by PECOs shareholders in the Fulton and Summit projects. Moreover, while the Fulton and Summit projects were never supported by ratepayers, Salem Unit No. 2 was included in PECOs rate base and thus paid for by ratepayers. A reasonable basis clearly exists for the Commissions different treatment of these payments.

We hold that the Commission did not err by refusing to deduct the surplus of GACs payments from PECOs rate base.

Land Held for Future Use

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Metropolitan Edison Co. v. Pennsylvania Public Utility Commission
22 A.3d 353 (Commonwealth Court of Pennsylvania, 2011)
Lloyd v. Pennsylvania Public Utility Commission
904 A.2d 1010 (Commonwealth Court of Pennsylvania, 2006)
Bell Atlantic-Pennsylvania, Inc. v. Pennsylvania Public Utility Commission
763 A.2d 440 (Commonwealth Court of Pennsylvania, 2000)
Popowsky v. Pennsylvania Public Utility
706 A.2d 1197 (Supreme Court of Pennsylvania, 1997)
Pennsylvania Game Commission v. Pennsylvania Public Utility Commission
651 A.2d 596 (Commonwealth Court of Pennsylvania, 1994)
Allegheny Center Associates v. Pennsylvania Public Utility Commission
570 A.2d 149 (Commonwealth Court of Pennsylvania, 1990)
Commonwealth v. Jerrytone
545 A.2d 395 (Commonwealth Court of Pennsylvania, 1988)
City of Pittsburgh v. Pennsylvania Public Utility Commission
526 A.2d 1243 (Commonwealth Court of Pennsylvania, 1987)
City of Pgh. v. Pa. Puc
526 A.2d 1243 (Commonwealth Court of Pennsylvania, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
515 A.2d 651, 101 Pa. Commw. 76, 1986 Pa. Commw. LEXIS 2564, Counsel Stack Legal Research, https://law.counselstack.com/opinion/barasch-v-pennsylvania-public-utility-commission-pacommwct-1986.