Bar-Til, Inc. v. Superior Asphalt, Inc.

164 So. 3d 1028, 2014 Miss. App. LEXIS 452, 2014 WL 4197351
CourtCourt of Appeals of Mississippi
DecidedAugust 26, 2014
DocketNo. 2013-CA-00304-COA
StatusPublished
Cited by4 cases

This text of 164 So. 3d 1028 (Bar-Til, Inc. v. Superior Asphalt, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Mississippi primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bar-Til, Inc. v. Superior Asphalt, Inc., 164 So. 3d 1028, 2014 Miss. App. LEXIS 452, 2014 WL 4197351 (Mich. Ct. App. 2014).

Opinion

CARLTON, J.,

for the Court:

¶ 1. Bar-Til Inc. appeals the Hinds County Chancery Court’s judgment denying its claim for punitive damages. Bar-Til argues that the chancellor erred by failing to consider the bifurcated issues of bad faith and punitive damages.1 Finding no error, we affirm the chancellor’s ruling.

FACTS

¶ 2. In January 2007, Pull-A-Part of Jackson LLC and Superior Asphalt Inc. (collectively Defendants) entered into a contract for Superior to perform work on Pull-A-Part’s property. Superior entered into a subcontract with Bar-Til and engaged Bar-Til to perform site and dirt work for the project. According to Bar-Til’s contract with Superior, Bar-Til would clear approximately 26 acres of land and strip almost 20,000 cubic yards of topsoil for $62,680. Superior later expanded the scope of Bar-Til’s work on the project for a total of $111,410. Superior sent Bar-Til a “Letter of Intent to Award,” which reflected these contract changes. Robert Cox, the project manager, signed the letter on behalf of Superior. In his findings of fact in the court below, the chancellor also noted that Superior issued Bar-Til additional work in the amount of $34,340.

¶ 3. After starting the Pull-A-Part project,. Superior discovered that certain items in the original project plan failed to consider new FEMA requirements for flood-zone elevation and that “the grades for proper drainage over the entire site were incorrect.” The original project plan required 20,000 cubic yards of dirt to be used as fill to provide proper drainage. However, Superior had since learned that a minimum of 53,000 cubic yards of dirt was needed to correct the problems. As a result, Superior authorized Bar-Til to excavate the additional 33,000 cubic yards of dirt for $74,250.

¶ 4. In July 2007, Mike Carroll replaced Cox as Superior’s project manager. On August 21, 2007, Carroll ordered Bar-Til to cease work to allow Superior to conduct a topographical survey. Bar-Til later resumed work in September 2007. In his findings of fact, the chancellor noted that, “[a]s problems developed on the project, Carroll continued to give Bar-Til oral change orders[,] and Bar-Til continued to work and submit invoices as the parties had done for the previous several months. However, Superior stopped paying invoices totaling $156,972.50.... ” The chancellor further noted that Bar-Til completed the project in December 2007, but Superior failed to pay Bar-Til for completion of the project.

¶ 5. Bar-Til filed a complaint in Hinds County Chancery Court on May 13, 2009, against the Defendants. Bar-Til asserted that Pull-A-Part was unjustly enriched as a result of Bar-Til’s unpaid work and that Superior breached the parties’ contract, breached the implied covenant of good faith and fair dealing, and breached its fiduciary duty to Bar-Til. The trial took place over the course of five different dates: June 20, 2011; June 21, 2011; November 10, 2011; February 13, 2012; and February 14, 2012.

¶ 6. On November 10, 2011, the third day of trial, Bar-Til asked to amend its complaint. Bar-Til asserted that Superi- or’s conduct constituted bad faith, and Bar-Til therefore sought to recover puni[1030]*1030tive damages. As reflected in the record, Bar-Til sought to recover punitive damages from Superior only. The chancellor ordered the parties to brief the issue and stated that he would rule on Bar-Til’s motion to amend its complaint on February 13, 2012.

¶ 7. When trial resumed on February 13, 2012, the chancellor granted Bar-Til’s motion to amend its complaint. Immediately after granting the motion, though, the chancellor cautioned;

However, this [c]ourt is not making any determination whether or not compensatory or even punitive damages will be awarded at this point. And if the [c]ourt finds that the compensatory damages are awarded, then there will have to be a second hearing on the issue of punitive damages if the [c]ourt finds that they are meritorious.

In response to a question by one of Superi- or’s attorneys, the chancellor clarified that his ruling did not mean Bar-Til was allowed to recover punitive damages against Superior. Instead, the chancellor emphasized that Bar-Til now had “the opportunity to offer the proof of punitive damages when we decide if that’s going to be an issue.”

¶ 8. After hearing the evidence presented by the parties, the chancellor found that a valid contract existed between Superior and Bar-Til, which the parties had verbally modified on several occasions. The chancellor found that Superior breached the parties’ contract by refusing to complete payment to Bar-Til. Even without the existence of a valid contract, the chancellor found that Bar-Til would be entitled to recover the reasonable cost of the services it performed under a theory of quantum meruit.

¶ 9. As to Bar-Til’s remaining claims, the chancellor found that Bar-Til failed to prove Superior acted in bad faith or breached its fiduciary duty to Bar-Til. As a result, the chancellor denied Bar-Til’s claim for punitive damages. Upon finding that Bar-Til failed to make a sufficient showing to warrant punitive damages, the chancellor also denied Bar-Til’s claim for attorneys’ fees. In addition, the chancellor found that Bar-Til failed to prove any of its claims against Pull-A-Part, and he dismissed with prejudice all claims against Pull-A-Part.

¶ 10. The chancellor entered his final judgment on September 19, 2012. On October 5, 2012, Bar-Til filed a post-trial motion to alter or amend the judgment pursuant to Rule 59(e) of the Mississippi Rules of Civil Procedure. In the alternative, Bar-Til’s motion sought partial relief from the final judgment pursuant to Rule 60(b) of the Mississippi Rules of Civil Procedure. The chancellor fouftd that Bar-Til failed to file its motion within the ten-day time limit provided by Rule 59(e), and he therefore denied as untimely Bar-Til’s motion to alter or amend.

¶ 11. However, the chancellor also found that Bar-Til’s motion for partial relief under Rule 60(b) possessed merit. The chancellor found that, due to a mathematical error, the monetary judgment entered in favor of Bar-Til had been incorrectly stated in both his previous order and the final judgment. The chancellor therefore amended his previous order and the final judgment to reflect the total corrected sum of $171,033.20. Aggrieved by the chancellor’s ruling on the issue of punitive damages, Bar-Til now appeals to this Court.

STANDARD OF REVIEW

¶ 12. This Court “will not disturb the factual findings of a chancellor when supported by substantial evidence unless we can say with reasonable certain[1031]*1031ty that the chancellor abused his discretion, was manifestly wrong [or] clearly erroneous[,] or applied an erroneous legal standard.” Biglane v. Under the Hill Corp., 949 So.2d 9, 13-14 (¶17) (Miss. 2007). We examine the entire record and accept as true all “evidence which supports or reasonably tends to support the findings of fact made below, together with all reasonable inferences which may be drawn therefrom and which favor the lower court’s findings of fact. That there may be other evidence to the contrary is irrelevant.” Par Indus. Inc. v. Target Container Co., 708 So.2d 44, 47 (¶4) (Miss.1998) (citation and internal quotation marks omitted). As to questions of law, however, we apply a de novo standard of review. Id. at (¶ 5).

¶ 13. In Faul v. Perlman,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Young v. Harris
N.D. Mississippi, 2024
Knights Marine & Industrial Services, Inc. v. Gulfstream Enterprises, Inc.
216 So. 3d 1164 (Court of Appeals of Mississippi, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
164 So. 3d 1028, 2014 Miss. App. LEXIS 452, 2014 WL 4197351, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bar-til-inc-v-superior-asphalt-inc-missctapp-2014.