Bank of New York Mellon Ex Rel. Bank of New York Global Capital Access One, Inc. v. GC Merchandise Mart, L.L.C. (In Re Denver Merchandise Mart, Inc.)

740 F.3d 1052, 2014 WL 291920, 2014 U.S. App. LEXIS 1656, 58 Bankr. Ct. Dec. (CRR) 274
CourtCourt of Appeals for the Fifth Circuit
DecidedJanuary 27, 2014
Docket13-10461
StatusPublished

This text of 740 F.3d 1052 (Bank of New York Mellon Ex Rel. Bank of New York Global Capital Access One, Inc. v. GC Merchandise Mart, L.L.C. (In Re Denver Merchandise Mart, Inc.)) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bank of New York Mellon Ex Rel. Bank of New York Global Capital Access One, Inc. v. GC Merchandise Mart, L.L.C. (In Re Denver Merchandise Mart, Inc.), 740 F.3d 1052, 2014 WL 291920, 2014 U.S. App. LEXIS 1656, 58 Bankr. Ct. Dec. (CRR) 274 (5th Cir. 2014).

Opinion

W. EUGENE DAVIS, Circuit Judge:

Lender-appellant Bank of New York Mellon (“Lender”) appeals the district court’s judgment which, in relevant part, disallowed the Lender’s claim for a con *1054 tractual prepayment consideration. We affirm.

I.

This dispute arose in a complicated bankruptcy proceeding, but the fundamental dispute is a relatively straightforward question of contract interpretation under Colorado law. Debtor-appellee GC Merchandise Mart, LLC (“GCMM”) owns the Denver Merchandise Mart, a large exposition center in Denver, Colorado. GCMM’s parent company is appellee Hawthorn Lakes Associates, Ltd., and appellee Denver Merchandise Mart, Inc. (“DMM”) is an affiliate of GCMM. All three companies filed petitions for voluntary Chapter 11 bankruptcy protection in March 2011. The cases are being jointly administered, with DMM’s case designated as the lead case.

GCMM executed a promissory note (the “Note”) dated September 30, 1997 in favor of Dynex Commercial, Inc., a predecessor in interest to lender-appellant Bank of New York Mellon (“Lender”) in exchange for a $30 million loan. The Note bore interest at a non-default rate of 8.3% and contained several clauses, only two of which are at issue in this appeal: Article 4 (“Default and Acceleration”) and Article 6 (“Prepayment”).

Article 4 provides that “if any payment required in this Note is not paid prior to the tenth (10th) day after the date when due or on the Maturity Date or on the happening of any other default,” certain sums become immediately due and payable, including the principal balance, interest, default interest, “other sums, as provided in this Note,” and “all other moneys agreed or provided to be paid by Borrower in this Note, the Security Instrument or the Other Security Documents,” among other things. Article 6 provides that the Borrower may prepay the Note under certain circumstances but must also pay a Prepayment Consideration, which is essentially a penalty for prepayment.

GCMM stopped making payments on the Note in October 2010 and thus defaulted under its terms. The Lender issued a notice of default, which GCMM failed to cure. Though GCMM made two more partial payments, it made no payment whatsoever after December 2010. As permitted by its security instruments, the Lender obtained an ex parte order appointing a receiver of the Merchandise Mart, at which point GCMM and the other debtors filed for bankruptcy. At that time, GCMM owed the Lender approximately $24 million.

The Lender argued that payment of the Prepayment Consideration under Article 6, valued at $1.8 million, is required by Article 4’s acceleration clause, notwithstanding the fact that GCMM stopped making payments under the Note after December 2010 and never paid the Note prior to the maturity date. The bankruptcy court disagreed on four grounds. First, it found that some payment, whether voluntary or involuntary, must actually be made to trigger the obligation to pay the Prepayment Consideration. Second, it found that the rationale for requiring a Prepayment Consideration did not apply here. Third, it found that the cases cited by the Lender were inapposite because in each of those cases, 1 the acceleration clause specifically provided that acceleration of the note would trigger the obligation to pay the prepayment consideration. Fourth and finally, the bankruptcy court noted that it *1055 would have been easy to expressly provide for payment of the Prepayment Consideration in the event of acceleration.

Thus, although the bankruptcy court allowed the Lender to recover a $25 million secured claim under the Note in conjunction with confirming the reorganization plan, 2 it disallowed the $1.8 million claim for the Prepayment Consideration under Article 6 of the Note. 3

The Lender appealed the bankruptcy court’s order to the district court. The district court affirmed the bankruptcy court in full. The Lender timely appealed to this court. The only issue the Lender presents on appeal is whether or not GCMM became liable for the $1.8 Prepayment Consideration upon the pre-bank-ruptcy acceleration of the Note.

II.

In this dispute over the disallowance of a claim in a bankruptcy proceeding, the bankruptcy court had jurisdiction under 28 U.S.C. §§ 157(b)(2)(B) and 1384(b), and the district court had jurisdiction over the appeal from the bankruptcy court under 28 U.S.C. § 158(a)(1). We therefore have jurisdiction over this appeal from the district court’s judgment pursuant to 28 U.S.C. §§ 158(d)(1) and 1291.

“We review the bankruptcy court’s findings of fact for clear error and its conclusions of law de novo, using the same standards that the bankruptcy court and district court applied.” 4 We look to applicable state law to determine the appropriate standard of review for interpretation of a contract. 5 Under Colorado law, the interpretation of a contract is a matter of law that is reviewed de novo. 6

III.

A. Colorado Contract Interpretation Principles

It is undisputed that Colorado law applies with respect to the interpretation of this contract. The Supreme Court of Colorado, sitting en banc, summarized Colorado’s general principles for contract interpretation as follows:

We must construe the terms of the agreement in a manner that allows each party to receive the benefit of the bargain, and the scope of the agreement must faithfully reflect the reasonable expectations of the parties. In other words, we must interpret the agreement in a manner that best effectuates the intent of the parties. We ascertain the parties’ intent by looking to the plain language of the agreement. We will enforce the agreement as written unless there is an ambiguity in the language; courts should neither rewrite the agreement nor limit its effect by a strained construction. Thus, like any contract, *1056 an arbitration agreement must be given effect according to the plain and ordinary meaning of its terms.
In determining whether an ambiguity exists, we must ask whether the disputed provision is reasonably susceptible on its face to more than one interpretation.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Trahant v. Mintz
Fifth Circuit, 2026

Cite This Page — Counsel Stack

Bluebook (online)
740 F.3d 1052, 2014 WL 291920, 2014 U.S. App. LEXIS 1656, 58 Bankr. Ct. Dec. (CRR) 274, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bank-of-new-york-mellon-ex-rel-bank-of-new-york-global-capital-access-one-ca5-2014.