Bank of Luverne v. Alabama Bank & Trust Co.

117 So. 219, 217 Ala. 635, 1928 Ala. LEXIS 95
CourtSupreme Court of Alabama
DecidedMarch 22, 1928
Docket3 Div. 811.
StatusPublished
Cited by4 cases

This text of 117 So. 219 (Bank of Luverne v. Alabama Bank & Trust Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Alabama primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bank of Luverne v. Alabama Bank & Trust Co., 117 So. 219, 217 Ala. 635, 1928 Ala. LEXIS 95 (Ala. 1928).

Opinions

SAYRE, J.

In June, 1922, the Alabama Construction Company, a partnership composed of Rawlinson and another, entered into a contract with the Alabama highway department for the construction of 8.23 miles of road in Monroe county for which it was to be paid the sum of $34,399.40. The road was known as “Federal Aid Project 93-B.” The statute (Code, § 1329) requires in such eases that “not more than 85 per cent, of the contract price * * * shall he paid in advance of the full completion and acceptance *637 of - the work.” Payments were to be made each month according to the estimates made for the highway department by its engineer in-charge of the work. The construction company needed financial help, and so in the beginning it entered into an “arrangement” with the Alabama Bank & Trust Company by which the bank was to furnish money from time to time to carry on the work, taking as security the promissory notes of the construction company each of which contained a pledge of “estimates due F. A. P. 93-B.” The work, financed in this way except'in the item of $1,000 advanced by the Bank of Luverne in December, 1922, progressed until about April 1,1923, when the construction eonjpany, evidently seeing that no profit would result to it, abandoned the work of construction. Pri- or to that time the state (the Alabama highway commission) had paid to the construction company on account of work done'on the road the sum of $26,594.34, all of which except $3,209.68 went to the Alabama Bank. At that time the construction company was indebted to the Alabama Bank on account of money furnished for work on the road in the sum of $6,692.43. The road was then unfinished, and thereafter, in July, 1923, the Bank of Luverne, to which Rawlinson individually was largely indebted on account of money loaned on previous road contracts, with the assent and concurrence of the highway department and of Rawlinson, who was the controlling partner of the construction company, entered into a contract with Mims Bros, for the completion of the project. About that time the construction company executed to the Bank of Luverne an assignment of all funds due or to become due to it on account of the work on 1?. A. P. -93-B and released all claim to the fund in the hands of the highway department. Payments made to Mims Bros, by the Bank of Luverne aggregated $3,728.55. There remained in the hands of the highway department $7,290.71, of which $5,082.75 represented the IS per cent, reserved against the completion and acceptance of the road. The parties to this cause, the Alabama Bank and the Bank of Luverne, not being agreed as to the proper disposition of the fund in the hands of the highway department, the construction company, by Rawlinson, filed an interpleader,' at the same time paying the sum of $7,290.71 into the registry of the court, and now, the Alabama Bank and the Bank of Luverne having propounded their respective claiftis, the question is, How, in equity, should the fund be distributed between them?

Much is said in the briefs concerning the assignability of the claims against the fund in the. hands of the highway department. This discussion is provoked by the various assignments heretofore mentioned and the fact that on August 28, 1922, after work on the road under the arrangement between the construction company and the Alabama Bank had-been in progress for some weeks, the construction company sent to the state highway engineer (state highway department) the following :

“Please pay the Bank of Luverne, Luverne, Ala., retainage [meaning the 15 per cent, retained] which is now due or may become due us on Project 93-B, Monroe county. [Signed] 1 Alabama Construction Company, by L. C. Rawlinson.”

But, in bur opinion, the discussion of the assignability of such claims, whether in whole or in part, and .the order of precedence among the assignees of such claims as affected by the dates of the assignments should have little or nothing to do with result to be adjudged. . It is enough for the purposes of this case to say that the several assignments shown by the record were, in equity, sufficient, as between the parties to them, to pass the right to the funds in question. Wells v. Cody, 112 Ala. 278, 20 So. 381. It is of no consequence whether the several assignments in question undertook to pass the right to an entire fund- or a part only, since the rule against partial assignments is made for the protection of the debtor in whose hands the fund may be. The state highway department gave no attention to these assignments; its payments out of the fund set apart for the road contract, P. A. P. 93-B, were made directly to the construction company so long as that company continued to earn them by work upon the road. The balance of the sum provided by the contract remained in the hands of the department until the road was completed and •accepted, after which, as we have shown, the balance remaining in the hands of the department was paid into court through Rawlinson, thus relieving the department of all concern about the application of the fund. As for the matter of precedence as affected by the dates of the several assignments, it seems to us that, on obvious grounds of equity, the amounts earned by the construction company, with the aid of money advanced by the Alabama Bank for that purpose and on the faith of the promise that they should stand as security for such money, should, so far as definitely separable, be so applied in repayment of the- money advanced by the Alabama Bank, and, certainly, the fact — as we find the case to be — that the Alabama Bank put out its money without knowledge or notice that the Bank of Luverne claimed under a prior assignment of the fund from which the earnings came ought not to affect adversely the claim of the- Alabama Bank under its equitable assignment. The application of this principle to the facts in evidence would assign to the Alabama Bank without abatement on any account the sum of $2,207.96, the amount, apart from the retain-age, so-called, due to the construction company for work done by it.

The Bank of Luverne contends that *638 it contributed to tbe earning of tbe whole amount paid to tbe construction company by reason that at tbe beginning of tbe work it held and owned a past-due mortgage on tbe construction company’s road-building outfit, viz., teams, road scrapers, trucks, etc., without wbicb tbe construction company could not bave undertaken to build tbe road, and its agreement to let Rawlinson have the use of the outfit contributed as materially to tbe earning of tbe amounts paid by tbe highway department to the construction company and the money in controversy as did the money borrowed from tbe Alabama Bank. Among tbe obstacles standing in tbe way of the allowance of this contention with any definite effect, are these: The debt which the Bank of Luverne sought in this way to find security for was tbe individual debt of Rawlinson, not tbe debt of tbe construction company, and, as against tbe Alabama Bank, a creditor of tbe company, a partnership, as above stated, tbe individual partner bad not the right to appropriate tbe partnership earnings to the payment of his individual debt without tbe consent of the other partners, and not then if tbe effect was to leave partnership creditors unpaid (Jones v. Nichols, 202 Ala. 233, 80 So. 71; Cannon v. Lindsey, 85 Ala. 198, 3 So. 676, 7 Am. St. Rep.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Spencer v. Bley Bros.
166 So. 776 (Supreme Court of Alabama, 1936)
Wade v. Brantley & Crawley Const. Co.
161 So. 101 (Supreme Court of Alabama, 1935)
Morgan Hill Paving Co. v. Fonville
119 So. 610 (Supreme Court of Alabama, 1928)

Cite This Page — Counsel Stack

Bluebook (online)
117 So. 219, 217 Ala. 635, 1928 Ala. LEXIS 95, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bank-of-luverne-v-alabama-bank-trust-co-ala-1928.