Bangor Hydro-Electric Company v. Federal Energy Regulatory Commission

925 F.2d 465
CourtCourt of Appeals for the D.C. Circuit
DecidedFebruary 15, 1991
Docket90-1109
StatusPublished

This text of 925 F.2d 465 (Bangor Hydro-Electric Company v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bangor Hydro-Electric Company v. Federal Energy Regulatory Commission, 925 F.2d 465 (D.C. Cir. 1991).

Opinion

925 F.2d 465

288 U.S.App.D.C. 234

BANGOR HYDRO-ELECTRIC COMPANY, Petitioner,
v.
FEDERAL ENERGY REGULATORY COMMISSION, Respondent,
Fitchburg Gas and Electric Light Company, et al., Public
Service Company of New Hampshire, Intervenors.

Nos. 89-1742, 90-1109.

United States Court of Appeals,
District of Columbia Circuit.

Argued Dec. 7, 1990.
Decided Feb. 15, 1991.

Petitions for Review of Orders of the Federal Energy Regulatory Commission.

Leonard W. Belter, with whom William J. Madden, Jr. was on the brief, Washington, D.C., for petitioner in 89-1742 and 90-1109.

Hanford O'Hara, Atty., F.E.R.C., with whom Jerome Feit, Sol., F.E.R.C., was on the brief, Washington, D.C., for respondent in 89-1742 and 90-1109.

Albert R. Simonds, Jr. was on the brief, Washington, D.C., for intervenor Public Service Co. of New Hampshire in 89-1742 and 90-1109.

Harry H. Voigt and Diane B. Schratwieser, Washington, D.C., entered appearances for intervenor Fitchburg Gas & Elec. Light Co., et al., in 89-1742.

Before MIKVA, Chief Judge, EDWARDS and D.H. GINSBURG, Circuit Judges.

Opinion for the Court filed PER CURIAM.

Opinion concurring in part and dissenting in part filed by Circuit Judge D.H. GINSBURG.

PER CURIAM:

In 1989, intervenor Public Service Company of New Hampshire (PSNH), an electric utility, filed a tariff raising rates for its non-firm transmission service. Petitioner Bangor Hydro-Electric Company, a customer for that service, intervened to oppose the increase. The FERC accepted PSNH's rate schedule for filing in an order dated March 31, 1989. 46 F.E.R.C. p 61,419.

Bangor filed a Request for Rehearing, in which it claimed that the tariff rate was improperly calculated because it failed to account for two PSNH services--those for entitlements in New England Power Pool (NEPOOL) planned units, and those for delivery of Yankee generating unit entitlements--as firm transmission services. In its Order Denying Rehearing, the FERC apparently agreed with Bangor that "only certain firm transmission services have been added to PSNH'S system loads to compute the annual peak demand." 49 F.E.R.C. p 61,030, at 61,117 (October 6, 1989). It nevertheless concluded that since PSNH had reflected these other transmission loads in the calculation by crediting the revenue requirement for the revenues received from these services, PSNH had taken a reasonable approach. Id.

That basis for upholding PSNH's rate calculation was undercut, however, when PSNH itself acknowledged, in response to Bangor's Motion for Clarification or Reconsideration, that it had not credited the revenue requirement in the way the FERC had assumed in its Order Denying Rehearing. In a subsequent Order (Denying Reconsideration and Clarifying in Part Order Denying Rehearing), the FERC recognized that the earlier rationale regarding revenue credits was no longer viable. The agency adhered to its earlier conclusion, nonetheless, 50 F.E.R.C. p 61,107, at 61,352 & n. 13 (February 1, 1990), on the new ground that the NEPOOL transmission service was non-firm, for which it relied on its decision in a prior case, Boston Edison Company, 44 F.E.R.C. p 61,199 (August 1, 1988). Id. It made no finding as to the character of, nor otherwise mentioned, the Yankee service.

Bangor argues in this court that the FERC's determination that NEPOOL service is non-firm, and that PSNH's rate is properly calculated, is not based upon substantial evidence.* We agree.

Section 13.2 of the NEPOOL Agreement suggests that transmission of NEPOOL entitlements enjoys some priority over other transmission service. The FERC concedes in this court that the agreement gives higher priority to transmission service involving participants than to that involving non-participants, but it claims that the NEPOOL service still has lower priority than firm transmission service.

There are two difficulties with this argument. First, that factual claim is contested by Bangor, and the FERC offers no evidence to support the claim. Had the FERC opinions analyzed the relative priorities of customers transmitting NEPOOL entitlements and other, concededly firm transmission service customers, we might well defer to its conclusion; it did not, however, address this issue in its opinions in this case or in the Boston Edison opinion upon which it relied for its conclusion that the service was non-firm. Second, even if the order of priority is (1) "firm" transmission customers, (2) NEPOOL customers, and (3) "non-firm" transmission customers, it is unclear why NEPOOL-related transmission service should be classified as "non-firm" rather than as "firm." If it is necessary to classify a service with intermediate priority as one or the other, then we would uphold a decision, based upon a reasoned explanation, to classify that service as "non-firm." Again, however, the FERC opinions do not undertake this analysis.

The FERC also failed to reconcile its position with a prior opinion in which it cited Sec. 13.2 of the NEPOOL Agreement and stated that "under the terms of the NEPOOL pooling agreement, [pool members] are guaranteed transmission access to pool planned generation facilities." Ocean State Power, 44 F.E.R.C. p 61,261, at 61,982 (August 19, 1988). This statement might reasonably be interpreted to mean that pool participants have a right to transmission service for entitlements that is not conditioned upon the availability of transmission capacity. So read, the statement is inconsistent with the agency's determination in this case, but the FERC neither distinguished the statement nor disavowed that interpretation.

At least in light of these apparent inconsistencies, the FERC's earlier finding in Boston Edison does not amount to "substantial evidence" upon which to base its holding in this case. In Boston Edison, the FERC stated that the complainant

ha[d] provided no evidence to support its allegation that the NEPOOL system was designed to provide firm transmission of non-firm loads all over New England.... While the NEPOOL participants coordinate transmission planning, the NEPOOL grid is the result of each NEPOOL participant building facilities to meet the needs of its own firm load. Utilities do not, by virtue of their NEPOOL association, construct facilities to serve other utilities' loads. [The utility], therefore, has built its transmission facilities to serve its own firm generation customers, plus [its firm transmission customers].

44 F.E.R.C. at 61,707-08 (footnote omitted). As Bangor points out, Boston Edison was not specifically directed to the character of the transmission service for NEPOOL entitlements. In any event, Boston Edison did not consider the specific language of Sec. 13.2, and since it preceded Ocean State, it did not, of course, explain the FERC's arguably inconsistent construction of Sec. 13.2 in the latter case.

We therefore remand the matter to the FERC in order that it may address these points.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
925 F.2d 465, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bangor-hydro-electric-company-v-federal-energy-regulatory-commission-cadc-1991.