Bangor Hydro-Electric Co. v. Federal Energy Regulatory Commission

925 F.2d 465, 288 U.S. App. D.C. 234, 1991 U.S. App. LEXIS 2240
CourtCourt of Appeals for the D.C. Circuit
DecidedFebruary 15, 1991
DocketNos. 89-1742, 90-1109
StatusPublished
Cited by1 cases

This text of 925 F.2d 465 (Bangor Hydro-Electric Co. v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bangor Hydro-Electric Co. v. Federal Energy Regulatory Commission, 925 F.2d 465, 288 U.S. App. D.C. 234, 1991 U.S. App. LEXIS 2240 (D.C. Cir. 1991).

Opinions

Opinion for the Court filed PER CURIAM.

Opinion concurring in part and dissenting in part filed by Circuit Judge D.H. GINSBURG.

PER CURIAM:

In 1989, intervenor Public Service Company of New Hampshire (PSNH), an electric utility, filed a tariff raising rates for its non-firm transmission service. Petitioner Bangor Hydro-Electric Company, a customer for that service, intervened to oppose the increase. The FERC accepted PSNH’s rate schedule for filing in an order dated March 31, 1989. 46 F.E.R.C. ¶ 61,419.

Bangor filed a Request for Rehearing, in which it claimed that the tariff rate was improperly calculated because it failed to account for two PSNH services — those for entitlements in New England Power Pool (NEPOOL) planned units, and those for delivery of Yankee generating unit entitlements — as firm transmission services. In its Order Denying Rehearing, the FERC apparently agreed with Bangor that “only certain firm transmission services have been added to PSNH’S system loads to compute the annual peak demand.” 49 F.E.R.C. ¶ 61,030, at 61,117 (October 6, 1989). It nevertheless concluded that since PSNH had reflected these other transmission loads in the calculation by crediting the revenue requirement for the revenues received from these services, PSNH had taken a reasonable approach. Id.

That basis for upholding PSNH’s rate calculation was undercut, however, when PSNH itself acknowledged, in response to Bangor’s Motion for Clarification or Reconsideration, that it had not credited the revenue requirement in the way the FERC had assumed in its Order Denying Rehearing. In a subsequent Order (Denying Reconsideration and Clarifying in Part Order Denying Rehearing), the FERC recognized that the earlier rationale regarding revenue [236]*236credits was no longer viable. The agency adhered to its earlier conclusion, nonetheless, 50 F.E.R.C. ¶ 61,107, at 61,352 & n. 13 (February 1, 1990), on the new ground that the NEPOOL transmission service was non-firm, for which it relied on its decision in a prior case, Boston Edison Company, 44 F.E.R.C. ¶ 61,199 (August 1, 1988). Id. It made no finding as to the character of, nor otherwise mentioned, the Yankee service.

Bangor argues in this court that the FERC’s determination that NEPOOL service is non-firm, and that PSNH’s rate is properly calculated, is not based upon substantial evidence.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
925 F.2d 465, 288 U.S. App. D.C. 234, 1991 U.S. App. LEXIS 2240, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bangor-hydro-electric-co-v-federal-energy-regulatory-commission-cadc-1991.