Baltimore Contractors, Inc. v. Renegotiation Board

43 T.C. 611, 1965 U.S. Tax Ct. LEXIS 131
CourtUnited States Tax Court
DecidedFebruary 9, 1965
DocketDocket Nos. 953-R, 954-R.
StatusPublished
Cited by3 cases

This text of 43 T.C. 611 (Baltimore Contractors, Inc. v. Renegotiation Board) is published on Counsel Stack Legal Research, covering United States Tax Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Baltimore Contractors, Inc. v. Renegotiation Board, 43 T.C. 611, 1965 U.S. Tax Ct. LEXIS 131 (tax 1965).

Opinion

Respondent has determined by unilateral orders dated December 6, 1956, that petitioner realized excessive profits of $50,000 on three contracts completed in 1951 and $100,000 on one contract completed in 1952. Petitioner contests respondent’s determination of excessive profits for both years.

The evidence was heard by a commissioner of the Court and his findings are the basis for our findings of fact herein. Some of the facts have been stipulated.

FINDINGS OF FACT

The stipulated facts are included herein by this reference.

Petitioner is a Maryland corporation engaged in the general construction business with its principal office in Baltimore, Md. It was incorporated in 1945 and took over the business formerly conducted by Victor Frenkil who became petitioner’s president and the owner of substantially all of its common stock.

Petitioner kept its books and records and filed its Federal income tax returns on a completed-contract and a calendar year basis.

Some of petitioner’s contracts were with private industries, some with States and municipalities, and some with the Federal Government. Its total net sales and profits for the years 1946 to 1952, inclusive, were as follows:

[[Image here]]

Petitioner completed three contracts in 1951 and one in 1952 for the General Services Administration (GSA), all of which were renegotiable contracts as defined in the Renegotiation Act of 1951. The contracts were:

Dated
WA-lpb-6398 (Kevere Copper & Brass plant)_June 23,1960
G-S-03-B-1194 (Sun Building)_as of June 11, 1961, executed July 16, 1962
GS-00-B-2166 (Dayton warehouse)_Jan. 31, 1951
GS-00-B-2083 (Sbaronville warehouse)_Oct. 13, 1960

Contract WA-lpb-6398 was for processing machinery and equipment and for repairs and preservation of structures at the Revere Copper & Brass Co. plant at Halethorpe, Md. This was a negotiated cost-plus-fixed-fee contract. Petitioner was to be reimbursed for all costs incurred at the contract site and receive a fixed fee, as finally agreed upon, of $8,412. Upon completion of the contract petitioner received a payment of $198,133. Its total costs, including prime costs, indirect and selling expenses, and general administrative expenses, prorated on the basis of total prime costs, were $202,865. This amount included subcontracting costs of $64,670. Petitioner sustained a loss on the contract of $4,732.

Contract GS-00-B-2166 was for the installation of fire protection facilities, including a sprinkler system, at the Dorothy Lane Warehouse, Dayton, Ohio. Petitioner was awarded the contract as the lowest bidder after GSA had advertised for competitive sealed bids. Petitioner’s bid of $358,500 was approximately $6,000 lower than the only other bid. The contract price was later increased by changes in specifications to $365,370. The Dorothy Lane Warehouse was being used for storage of crude rubber. It was said to contain bales of crude rubber of a value of $50 million.

In preparing its bid on the job petitioner estimated its overhead and profits at 20 percent of costs, other than the cost of the sprinkler system, and 10 percent of the sprinkler system cost. It added $14,725 for “Contingent — Unknowns & Escalation” and $7,500 unidentified.

At the time petitioner submitted its bid it had a quotation from Automatic Sprinkler Co. to install the sprinkler system called for in the contract for $172,000.

The contract was declared “substantially completed” by November 2, 1951. The time for completion was extended for 75 days.

Petitioner’s total pay on the contract was $365,370. Prime costs were $303,721, including subcontracting in the amount of $250,576.60. Under an accounting agreement between respondent and petitioner, based on the ratio of contract prime costs to total prime costs, there were allocated to the contract indirect expenses of $6,277 and selling, general, and administrative expenses of $12,456, making total costs of $322,454 and net profits of $42,916.

Contract GS-00-B-2083, completed in 1952, was for the installation of fire protection facilities, including a sprinkler system, at the Federal Supply Service warehouses at Sharonville, Ohio. Those warehouses, nine in number, also were used for storing crude rubber and other products. They were said to contain about 288 million pounds of rubber of a value of approximately $170 million.

The contract was executed by OSA and petitioner on October 13, 1950. Its completion was required within 250 days of the notice to commence, which petitioner received October 30,1950. For justifiable delay the time for completion was extended 187 days. The contract was declared substantially completed January 10, 1952.

In letting this contract GSA advertised for sealed competitive bids August 31, 1950. Petitioner’s bid of $1,118,000 was the lowest of six bids received. The highest of the six bids was $1,411,000. The bids were all in excess of GSA’s estimate and were all rejected. On reexamination of the specifications, GSA found that the pipe called for was larger and of a more expensive type than was required and modified the specifications in that respect, reducing its estimate to $949,440.

Thereafter, GSA conferred with petitioner requesting a reduction of its bid to reflect the change in specifications. Petitioner estimated that the resulting savings would not exceed $70,075. However, by letter dated October 11,1950, petitioner offered to accept the contract for $955,000, reducing its bid by the approximate amount of the minimum savings estimated by GSA on the changes in specifications.

The original contract price of $955,000 was subsequently increased by changes in specifications to $1,005,500.52. Petitioner’s prime costs were $767,070, of which the amount of $637,340.27 was paid to subcontractors. There were allocated to the contract $16,844 indirect expenses and $32,748 selling, general, and administrative expenses on the basis of the ratio of prime costs of the contract to total prime costs for the entire year. This resulted in a total cost of $816,662 and a net profit of $188,839.

Before closing the contract, petitioner had received a commitment from Blaw-Knox Co. to install the sprinkler system for $535,176. The final cost of the sprinkler system, which was subcontracted to another company, was $426,365.

The most important feature of the Sharonville and Dayton contracts was the installation of complete automatic sprinkler systems. The related work included excavating, constructing reservoirs, pump and valve houses, and laying pipe. Petitioner was directly responsible to GSA for the sprinkler systems as well as the other work. The cost of the work performed by subcontractors amounted to $637,340.27.

Some of the work performed by petitioner and its subcontractors at Sharonville was unsatisfactory. Operational difficulties developed in both the sprinkler system and other equipment. There were numerous complaints by GSA officials about delays in the work and the inefficiency of the workmen.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

S. S. Silberblatt, Inc. v. Renegotiation Board
51 T.C. 907 (U.S. Tax Court, 1969)
Baltimore Contractors, Inc. v. Renegotiation Board
43 T.C. 611 (U.S. Tax Court, 1965)

Cite This Page — Counsel Stack

Bluebook (online)
43 T.C. 611, 1965 U.S. Tax Ct. LEXIS 131, Counsel Stack Legal Research, https://law.counselstack.com/opinion/baltimore-contractors-inc-v-renegotiation-board-tax-1965.