ERIC F. MELGREN, UNITED STATES DISTRICT JUDGE

MEMORANDUM AND ORDER

This case involves a dispute regarding the demolition of a hotel and the personal property contained within the hotel. Plaintiffs, The Balmer Fund, Inc. and Rosalea Hostetler, allege that Defendant, the City of Harper, Kansas, violated their due process rights, converted their property, committed a trespass upon their property, intentionally inflicted emotional distress on Hostetler, negligently inflicted emotional distress on Hostetler, intentionally interfered with Plaintiffs' prospective business expectancy and advantage, and acted negligently when it demolished Plaintiffs' hotel and personal property contained within the hotel.

This matter comes before the Court on Defendant's motion for summary judgment and/or motion to dismiss (Doc. 20) and Plaintiffs' motion to strike (Doc. 29). For the reasons stated below, Defendant's motion is granted in part and denied in part, and Plaintiffs' motion is denied.

I. Factual and Procedural Background1

In 1999, Rosalea Hostetler quitclaimed a hotel located at 121 West Main Street, Harper, Kansas, to The Balmer Fund, Inc., while reserving a life estate in the property. In 2013, Plaintiffs hired Engineering Consultants, P.A., to evaluate the structural integrity of the hotel. Plaintiffs' consultants confirmed that the hotel was deteriorating, found that saving the hotel would require significant money and effort, recommended various repairs, and recommended that the public not be allowed in the building or along the sidewalk near one corner of the building until repairs are completed. In 2014, the City hired D & B Engineering, LLC, to inspect the property, and on May 22, 2014, D & B performed an inspection of the exterior of the hotel. D & B determined that none of the repair work recommended in the 2013 evaluation had been started, and that protective measures for the public were needed right away.

On June 2, 2014, a special City Council meeting was held to discuss the hotel. Plaintiffs attended the meeting. The City *1141Council passed a resolution declaring the hotel an immediate hazard, and the City immediately padlocked the hotel and restricted access to it. On July 14, 2014, the City Council began advertising for bids to demolish the hotel, and on August 25, 2014, the City Council began opening bids for the hotel's demolition.

Defendant sent Plaintiffs a letter on August 27, 2014, requesting that Plaintiffs provide proof of their financial ability to pay for repairs to make the hotel safe. Plaintiffs did not provide a statement documenting their ability to pay for the necessary repairs by the City Council's meeting held on September 8, 2014, and the City Council voted to accept a bid to demolish the hotel for $148,000.

The next day, Plaintiffs filed a Petition in the Thirtieth Judicial District, District Court, Harper County, Kansas, requesting an order temporarily restraining Defendant from taking steps to demolish the hotel. Approximately one week later, the state court issued an Agreed Journal Entry. The order included the following excerpts:

1. Plaintiffs represent that they have secured a plan from Richard B. Kraybill...to make the building and premises at 121 West Main Street,...safe...
2. Plaintiffs shall have until January 15, 2015 to secure $110,000 cash to pay for the improvements and repairs needed to complete the Kraybill plan,...
3. Should Plaintiffs secure and document possession of the $110,000 cash on or before January 15, 2015 then Plaintiffs will have until July 1, 2015 to complete the Kraybill plan....
4. Should Plaintiffs fail to secure and document possession of the $110,000 cash by January 15, 2015 or having successfully secured the funds fail to complete and document completion of the Kraybill plan by July 1, 2015 then the Defendant may proceed with demolition of the building at 121 West Main.
....
7. Should the Plaintiffs successfully complete the Kraybill plan then this Court case will be dismissed, the planned demolition will not take place and possession to the building and property will be relinquished to Plaintiffs, otherwise Defendants shall remain in the exclusive possession of the building and premises at 121 West Main, Harper, Kansas.

Plaintiffs did not provide notice that they had secured $110,000 by January 15, 2015, and on January 20, 2015, the City signed a demolition contract and notice to proceed with the demolition. The City Council scheduled the demolition work to begin on February 26, 2015.

On March 5, 2015, the City Council convened a special meeting at Plaintiffs' request. At the meeting Plaintiffs revealed that they had secured $21,000 for repairs, but the City Council did not vote to breach the demolition contract. The City Council asked Plaintiffs if they had plans to remove property from the hotel before demolition, and Plaintiffs responded that there were no plans. The parties disagree as to when demolition actually began, but Plaintiffs allege that the hotel and all of its contents were demolished on March 6, 2015.

On February 24, 2017, Plaintiffs filed this action alleging violations of Plaintiffs' due process rights, conversion, trespass, intentional infliction of emotional distress, negligent infliction of emotional distress, intentional interference with prospective business advantage, and negligence.

II. Legal Standards

A. Motion for Summary Judgment

Summary judgment is proper if the moving party demonstrates that there is *1142no genuine issue as to any material fact, and the movant is entitled to judgment as a matter of law.2 A fact is "material" when it is essential to the claim, and issues of fact are "genuine" if the proffered evidence permits a reasonable jury to decide the issue in either party's favor.3 The movant bears the initial burden of proof and must show the lack of evidence on an essential element of the claim.4 If the movant carries its initial burden, the nonmovant may not simply rest on its pleading, but must instead "set forth specific facts" that would be admissible in evidence in the event of trial from which a rational trier of fact could find for the nonmovant.5 These facts must be clearly identified through affidavits, deposition transcripts, or incorporated exhibits-conclusory allegations alone cannot survive a motion for summary judgment.6 The Court views all evidence and reasonable inferences in the light most favorable to the non-moving party.7

B. Motion to Dismiss

Under Rule 12(b)(6), Defendant may move for dismissal of any claim where Plaintiffs have failed to state a claim upon which relief can be granted. Upon such motion, the Court must decide "whether the compliant contains 'enough facts to state a claim to relief that is plausible on its face.' "8

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
294 F. Supp. 3d 1136, Counsel Stack Legal Research, https://law.counselstack.com/opinion/balmer-fund-inc-v-city-of-harper-ksd-2018.