Balfour/S&P Two, A Joint Venture

CourtArmed Services Board of Contract Appeals
DecidedSeptember 1, 2015
DocketASBCA No. 58067
StatusPublished

This text of Balfour/S&P Two, A Joint Venture (Balfour/S&P Two, A Joint Venture) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Balfour/S&P Two, A Joint Venture, (asbca 2015).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of -- ) ) Balfour/S&P Two, A Joint Venture ) ASBCA No. 58067 ) Under Contract No. W9126G-09-C-0054 )

APPEARANCE FOR THE APPELLANT: Douglas L. Patin, Esq. Bradley Arant Boult Cummings LLP Washington, DC

APPEARANCES FOR THE GOVERNMENT: Thomas H. Gourlay, Jr., Esq. Engineer Chief Trial Attorney Jane Holt-Duecaster, Esq. Engineer Trial Attorney U.S. Army Engineer District, Ft. Worth

OPINION BY ADMINISTRATIVE JUDGE WILSON

This appeal arises from the denial of a claim for costs associated with performing remedial work to correct alleged deficiencies in drilled concrete foundation piers due to alleged defective specifications and the government preclusion of appellant's means and methods to complete construction. A six-day hearing was held in San Antonio, Texas, on entitlement only. The parties have submitted post-hearing and reply briefs. The Board has jurisdiction over this matter pursuant to the Contract Disputes Act of 1978 (CDA), 41 U.S.C. §§ 7101-7109. For the reasons stated below, we deny the appeal.

FINDINGS OF FACTS

1. On 17 September 2009, the United States Army Corps of Engineers, Fort Worth District (Corps or government), awarded Contract No. W9126G-09-C-0054 to Balfour/S&P Two, A Joint Venture (Balfour or appellant) in the amount of $46,437,194 (R4, vol. 1, tab 4). The parties involved in the joint venture were Balfour Beatty and Satterfield & Pontikes, JV (supp. R4, vol. 10, tab 168). The contract was for the construction of the Airmen Training Complex Dormitory 1, at Lackland Air Force Base (Lackland AFB), in San Antonio, Texas. This project, which was the first dormitory to be constructed out of eight identical dormitories, was part of a larger program at Lackland AFB called the Airman Training Complex (ATC). The contract performance period was 730 days from receipt of the Notice to Proceed (NTP). (R4, vol. 1, tab 4) The contract included a structural design for the foundation that consisted of 136 reinforced drilled piers (also referred to as drilled caissons) installed to a depth of approximately 65 feet below grade (R4, vol. 2, tabs 13-19). The relevant contract drawings required that the upper section of each pier be installed using a sonotube, which is a round cardboard formwork (akin to a giant cardboard paper towel roll) (R4, vol. 2, tab 20; supp. R4, vol. 40, tab 797).

2. The contract also contained the following special technical provisions:

SECTION 31 63 26

DRILLED CAISSONS 08/08

PART 1 GENERAL

1.1 UNIT PRICES

1.1.1 Basis of Bids

Base the bid on the number and total length of caissons, established by top and bottom elevations and diameters.... The Contractor will not receive payment for rejected caissons or for those not conforming to specifications.

1.7 SEQUENCING

1. 7 .1 Caisson Excavation

Perform excavation of caissons or groups of caissons so that reinforcing steel and concrete placement is a continuous operation performed the same day that the excavation is completed. Do not leave excavations open overnight.

2.1 MATERIALS

2.1.1 Concrete Work

2 Perform all concrete work in accordance with requirements of Section 03 3100.0010 CAST-IN- PLACE STRUCTURAL CONCRETE, as modified herein:

2 .1.1.1 Strength

Provide 3000 psi strength concrete at 28 days, with slump from 4 to 6 inches.

2.1.1.3 Reinforcing Steel

Provide reinforcing steel conforming to ASTM A 615/A 61 SM Grade 60, welded into cages in accordance with AWS Dl . 4/Dl . 4M and inserted securely in the caissons, in position and alignment, as shown, prior to concrete placement.

2.1.3 Casing Steel

... Provide casings with an outside diameters [sic] not less than indicated shaft sizes and a minimum of 114 inch thick. Temporary casings shall extend down 40 feet below existing grade ....

3.2 INSTALLATION

b. Bring concrete to a true level surface inside the shaft and a full width cross key formed, or dowels installed, if it becomes necessary to interrupt placing concrete in any caisson. Prior to placing additional concrete, clean surfaces of laitance and slush with one-

3 •I ' to-one portland cement grout, having a water-cement ratio not exceeding that of the concrete.

(R4, vol. 1, tab 12 at 417, 420-22) The drilled pier foundation is created as follows:

The process begins with drilling a hole with an aug[ e]r. And the soils are displaced ....

... [A] casing is placed down in the hole, as the hole is started. And then once placed inside the hole, the auger action goes inside and continues the drilling until it gets to what's called the proper bearing depth.

And once it reaches a certain resistance that is acceptable to the Government's geotechnical representatives it's considered proper to begin the placement of concrete.

(Tr. 1/14-15) Before the concrete is placed, a rebar cage (approximately 60 feet in length) is inserted inside the drilled shaft. Additionally, the contractor is required to "[ c]ontinuously remove all water that flows into the excavations and from the excavation bottom, to the extent possible prior to concrete placement." The applicable contract provisions further state:

The maximum permissible depth of water is 2 inches. In the event of a severe water condition that makes it impossible or impractical to dewater the excavation, place concrete using an underwater tremie after water movement has stabilized.

(R4, vol. 1, tab 12 at 422) The record reflects that a "tremie" is a solid pipe that concrete is pumped through to fill the previously-drilled shaft. The tremie may be inserted directly in the freshly-poured concrete to continue filling the excavated area; effectively filling the shaft with concrete while flushing out water and other t contaminates from below. (Tr. 1116)

3. The contract contained the following Federal Acquisition Regulation clauses in pertinent part: I 52.236-5, MATERIAL AND WORKMANSHIP (APR 1984)

4 (c) All work under this contract shall be performed in a skillful and workmanlike manner. The Contracting Officer may require, in writing, that the Contractor remove from the work any employee the Contracting Officer deems incompetent, careless, or otherwise objectionable.

(R4, vol. 1, tab 4 at 166)

56 .23 6-21, SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION (FEB 1997)

(a) The Contractor shall keep on the work site a copy of the drawings and specifications and shall at all times give the Contracting Officer access thereto. Anything mentioned in the specifications and not shown on the drawings, or shown on the drawings and not mentioned in the specifications, shall be of like effect as if shown or mentioned in both. In case of difference between drawings and specifications, the specifications shall govern. In case of discrepancy in the figures, in the drawings, or in the specifications, the matter shall be promptly submitted to the Contracting Officer, who shall promptly make a determination in writing. Any adjustment by the Contractor without such a determination shall be at its own risk and expense ....

(Id. at 171) 52.246-12, INSPECTION OF CONSTRUCTION (AUG 1996)

(b) The Contractor shall maintain an adequate inspection system and perform such inspections as will ensure that the work performed under the contract conforms to contract requirement. ...

(f) The Contractor shall, without charge, replace or correct work found by the Government not to conform to contract requirements, unless in the public interest the Government

5 consents to accept the work with an appropriate adjustment in contract price.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. Spearin
248 U.S. 132 (Supreme Court, 1918)
Al Johnson Construction Company v. The United States
854 F.2d 467 (Federal Circuit, 1988)

Cite This Page — Counsel Stack

Bluebook (online)
Balfour/S&P Two, A Joint Venture, Counsel Stack Legal Research, https://law.counselstack.com/opinion/balfoursp-two-a-joint-venture-asbca-2015.