Balfour Beatty Infrastructure, Inc. v. Mayor of Baltimore

855 F.3d 247, 2017 WL 1476147, 2017 U.S. App. LEXIS 7252
CourtCourt of Appeals for the Fourth Circuit
DecidedApril 25, 2017
Docket16-1322
StatusPublished
Cited by33 cases

This text of 855 F.3d 247 (Balfour Beatty Infrastructure, Inc. v. Mayor of Baltimore) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Balfour Beatty Infrastructure, Inc. v. Mayor of Baltimore, 855 F.3d 247, 2017 WL 1476147, 2017 U.S. App. LEXIS 7252 (4th Cir. 2017).

Opinion

PAMELA HARRIS, Circuit Judge:

Balfour Beatty Infrastructure, Inc. (“BBII”) sued the City of Baltimore for *249 breach of contract, alleging that the City unlawfully assessed liquidated damages against the company for failure to complete a construction project on time. The issue in this appeal is whether BBII must exhaust its administrative remedies against the City before suing in federal court. We agree with the district court that BBII is not excused from the normal requirement of administrative exhaustion under Maryland law, and therefore affirm the district court’s dismissal for lack of subject matter jurisdiction.

I.

A.

This case involves two public works contracts entered into by the City of Baltimore and BBII, 1 under which BBII agreed to build certain parts of a wastewater treatment system aimed at reducing pollution in the Chesapeake Bay. The contracts stipulate that “[t]ime is of the essence,” J.A. 72, 75, and BBII committed to completing its work by February 28, 2015. If it did not, then the City would have the right to assess liquidated damages for each day past the deadline, by withholding a portion of its monthly payments to BBII.

The contracts also incorporate provisions for the resolution of claims and disputes, which require BBII to seek administrative review of any dispute related to its contracts with the City before suing in court. Those provisions are grounded in the City’s Charter, which authorizes the City to establish an administrative process for the resolution of disputes arising from City construction contracts. See Charter of Baltimore City, art. II, § 4(A)(g) (2002 revision). Pursuant to that authority, the City has provided for an administrative dispute resolution process that governs all claims by contractors related to public works projects, set forth in the City’s “Department of Public Works Specifications— Materials, Highways, Bridges, Utilities and Incidental Structures 2006,” generally known as the “Green Book.”

Neither party disputes that the Green Book dispute resolution process is incorporated into the contracts at issue here. Under that dispute resolution process, a contractor is required to give “prompt notice” of any claim or dispute to the Department of Public Works engineer assigned to its project. J.A. 99. That engineer, along with the project’s inspector and division head, is charged with initial review of the claim, with the contractor responsible for providing any additional information requested by the City. If the contractor chooses to appeal, then review proceeds up through a Department of Public Works bureau head and, if the contractor remains dissatisfied, to ultimate review by the Director of Public Works, who acts as a hearing officer during an on-the-record administrative hearing and issues a final decision. At that point - and only at that point — the contractor may bring its claim to a “court of competent jurisdiction.” J.A. 101.

B.

During the course of its work on the wastewater treatment system, BBII ran into what it calls a “series of design errors, omissions and inconsistencies” on the part of the City that made it impossible to finish the project by the February 28, 2015 deadline. J.A. 11. On March 2, 2015, two days after the deadline had expired and before final action on several BBII extension requests, the City informed BBII that *250 it would exercise its contractual right to assess liquidated damages at the rate of $20,000 per day on each contract, until the projects were completed. The City then began to deduct $40,000 per day from its monthly payments to BBII.

BBII bypassed the administrative process incorporated into its contracts with the City and went directly to federal court to file this suit. 2 Naming as defendants the Mayor and City Council of Baltimore (“the City”), BBII alleged that the City had materially breached its contracts with BBII by declaring BBII in default and assessing liquidated damages without first pursuing its own claims through the administrative dispute resolution process and affording BBII an administrative hearing. According to BBII, the City’s actions amounted to an illegal and ultra vires “abandonment” of the Green Book administrative process, relieving BBII of any obligation to use that process itself. J.A. 366.

The district court disagreed, and held that BBII was required to exhaust the administrative remedies provided for by its City contracts. The court began by describing Maryland law’s “strong preference for administrative exhaustion,” J.A. 362 — a preference, it noted, that is consistent with federal law, as well. Under Maryland law, the court explained, it is well established that “[wjhere an administrative agency has primary or exclusive jurisdiction over a controversy, the parties to the controversy must ordinarily await a final administrative decision before resorting to the courts for resolution of the controversy.” J.A. 363 (quoting Heery Int’l, Inc. v. Montgomery Cty., Md., 384 Md. 129, 862 A.2d 976, 981 (2004)). And that general principle, the court determined, governs this case, where the Green Book provisions incorporated into BBII’s contracts “mandate[] that the prescribed administrative procedures are the exclusive procedures for the prosecution and resolution of all claims and disputes.” J.A. 365 (internal quotation marks omitted).

The district court recognized that the exhaustion requirement applies only where the agency designated to hear a dispute actually has “jurisdiction over [the] controversy,” Heery, 862 A.2d at 981—or, correspondingly, that there is an exception to the exhaustion requirement when the “reviewing agency is ‘palpably without jurisdiction’ ” to adjudicate a party’s claim. J.A. 365 (quoting Heery, 862 A.2d at 989). That exception, the district court explained, also “requires a complaining party to plead an ‘irreparable injury’ if it is forced to navigate the prescribed administrative process.” J.A. 365-66 (quoting Heery, 862 A.2d at 989). Because BBII could show neither that the City officials designated to review its contract dispute are “palpably without jurisdiction” to do so, nor that it would be irreparably damaged if required to postpone litigation until completion of the.administrative process, the court concluded, the exception does not apply.

Whether the City acted unlawfully by assessing liquidated damages without first engaging in the Green Book administrative process, as alleged by BBII, is a different question, the court explained — and precisely the kind of regulatory interpretation issue that “should be decided administratively before proceeding to judicial review” *251 under Maryland law. J.A. 367 (citing Heery, 862 A.2d at 986). Even assuming, as BBII argued, that the City acted without authority in taking liquidated damages absent administrative review, that would not excuse BBII from exhausting its administrative remedies: Maryland courts have not adopted an exception to exhaustion for cases in which “the act of an administrative agency is alleged to be ultra vires or illegal.” J.A.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
855 F.3d 247, 2017 WL 1476147, 2017 U.S. App. LEXIS 7252, Counsel Stack Legal Research, https://law.counselstack.com/opinion/balfour-beatty-infrastructure-inc-v-mayor-of-baltimore-ca4-2017.