Balf Co. v. Planning & Zoning Commission

830 A.2d 836, 79 Conn. App. 626, 2003 Conn. App. LEXIS 414
Connecticut Appellate Court·Decided September 23, 2003·No. AC 23313·Published·Cited by 12 cases

Opinion

Opinion

WEST, J.

The defendant, the planning and zoning commission of the town of Manchester (commission), appeals from the judgment of the trial court sustaining the appeal by the plaintiff, Balf Company, from the commission’s denial of a special exception permit for the construction and operation of a concrete manufacturing plant on the plaintiffs property. On appeal, the defendant claims that the court improperly (1) exercised subject matter jurisdiction over the plaintiffs appeal and (2) interpreted the commission’s regulations in concluding that the plaintiff was not obligated to [628] apply for a special exception permit for the proposed construction. We affirm the judgment of the trial court.

The following facts are relevant to our resolution of the commission’s appeal. The plaintiff is the owner of two contiguous parcels of land, totaling 55.6 acres, located in an industrial zone in Manchester. During the relevant time periods and thereafter, the plaintiff has operated an asphalt production plant on that property. The plaintiff desired to construct and to operate a concrete production plant on a 1.9 acre portion of its industrially zoned property. The town’s senior planner stated that special exception approval was required because the plaintiffs property was more than four acres. Pursuant to § 16.02 of Manchester’s industrial zone regulations, the plaintiff on December 1, 2000, applied for a special exception from the commission. The commission held a public hearing on the plaintiffs application on March 19 and April 2, 2001. Following the presentation of evidence and arguments for and against the proposed project, the commission denied the special exception.

Pursuant to General Statutes § 8-8, the plaintiff appealed to the Superior Court from the commission’s denial of the special exception. The court found that the commission improperly had interpreted its regulations when it required the plaintiff to apply for a special exception where the actual site on which the proposed plant was to be constructed was only 1.9 acres. The commission filed a petition for certification to appeal to this court, which granted certification to appeal. The commission then appealed.

I

We first address the defendant’s claim that the court did not have subject matter jurisdiction over the plaintiffs zoning appeal on the ground that the plaintiff had failed to exhaust its administrative remedies. The defen[629] dant argues that the plaintiff never raised the issue of whether it should be required to submit to the special exception process until its appeal to the trial court. According to the defendant, if the plaintiff did not think it was required to submit to the special exception process, it had options available to it by which it could raise that issue. Because the plaintiff did not avail itself of those options, the defendant contends that the plaintiff failed to exhaust its administrative remedies and, therefore, the court was without jurisdiction over the plaintiffs appeal. We disagree with the defendant.

According to the defendant, if the plaintiff believed that it could proceed with the concrete plant without the special exception, it need not have submitted to the special exception process. Rather, the plaintiff could have filed a site plan and applied lor a certificate of zoning compliance. If the town zoning enforcement officer denied the plan and ruled that the plaintiff was required to submit to the special exception process, the defendant argues, the plaintiff would then have had two alternatives. The plaintiff could have submitted to the special exception process and raised that issue before the commission. Alternatively, the defendant argues that the plaintiff could have appealed to the town’s zoning board of appeals from the zoning enforcement officer’s decision. We conclude, however, that the plaintiff exhausted the administrative procedures available to it by submitting the application for a special exception and then appealing to the court from the commission’s denial of the application pursuant to § 8-8.

“It is a settled principle of administrative law that if an adequate administrative remedy exists, it must be exhausted before the Superior Court will obtain jurisdiction to act in the matter. . . . The doctrine of exhaustion is grounded in a policy of fostering an orderly process of administrative adjudication and judicial review in which a reviewing court will have the [630] benefit of the agency’s findings and conclusions. . . . The doctrine of exhaustion furthers the salutary goals of relieving the courts of the burden of deciding questions entrusted to an agency ... in advance of possible judicial review. ... In addition, the administrative agency may be able to resolve the issues, making judicial review unnecessary.” (Citations omitted; internal quotation marks omitted.) Fish Unlimited v. Northeast Utilities Service Co., 254 Conn. 1, 11-13, 756 A.2d 262 (2000), overruled in part on other grounds, Waterbury v. Washington, 260 Conn. 506, 545, 800 A.2d 1102 (2002).

A

We first address the defendant’s argument that the plaintiff, in the first instance, could have ignored the town planner’s direction to seek a special exception permit and instead sought a certificate of zoning compliance, and whether that amounts to a failure to exhaust administrative remedies. The defendant argues that had the zoning enforcement officer issued the certificate of zoning compliance, the plaintiff would have had no obligation to apply as directed for a special exception permit. On the other hand, if the zoning enforcement officer denied the plaintiff a certificate of zoning compliance on the basis of its failure to seek a special exception, the defendant argues, then the plaintiff would have had available to it two administrative options. It could have submitted to the special exception and raised the issue to the commission. Alternatively, according to the defendant, the plaintiff could have appealed to the zoning board of appeals from the decision of the town official.1

Free access — add to your briefcase to read the full text and ask questions with AI

Balf Co. v. Planning & Zoning Commission, 830 A.2d 836, 79 Conn. App. 626, 2003 Conn. App. LEXIS 414 (Colo. Ct. App. 2003).

830 A.2d 836 (Balf Co. v. Planning & Zoning Commission) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Kobyluck Bros., LLC v. Planning & Zoning Comm'n of Waterford
142 A.3d 1236 (Connecticut Appellate Court, 2016)
Stamford v. Ten Rugby Street, LLC
Connecticut Appellate Court, 2016
Paul v. Town Plan & Zoning Commission
26 A.3d 100 (Connecticut Appellate Court, 2011)
Caltabiano v. L & L Real Estate Holdings II, LLC
998 A.2d 1256 (Connecticut Appellate Court, 2010)
Fillion v. Hannon
943 A.2d 528 (Connecticut Appellate Court, 2008)
Melnick v. Zoning & Planning Commission
931 A.2d 314 (Connecticut Appellate Court, 2007)
Trumbull Falls, LLC v. Planning & Zoning Commission
902 A.2d 706 (Connecticut Appellate Court, 2006)
200 Associates, LLC v. Planning & Zoning Commission
851 A.2d 1175 (Connecticut Appellate Court, 2004)
Blakeman v. Planning & Zoning Commission of Shelton
846 A.2d 950 (Connecticut Appellate Court, 2004)
Balf Co. v. Planning & Zoning Commission of Manchester
835 A.2d 474 (Supreme Court of Connecticut, 2003)