Baldwin v. Vantage Corp.

676 P.2d 413, 1984 Utah LEXIS 748
CourtUtah Supreme Court
DecidedJanuary 18, 1984
Docket18202
StatusPublished
Cited by19 cases

This text of 676 P.2d 413 (Baldwin v. Vantage Corp.) is published on Counsel Stack Legal Research, covering Utah Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Baldwin v. Vantage Corp., 676 P.2d 413, 1984 Utah LEXIS 748 (Utah 1984).

Opinion

HOWE, Justice:

Plaintiffs Carl Baldwin and Larry Gleim, partners in the construction business, bring this appeal from an adverse judgment in a suit which they brought for the rescission of a contract and the restitution of all amounts they had paid under it. Defendant Vantage Corporation is a wholly-owned subsidiary of Deseret Federal Savings and Loan Association. Vantage was engaged in the development of Blackhawk Estates in Pleasant Grove, Utah. Doug Boulton was the project manager of Vantage and also a vice-president of Deseret Federal.

In the spring of 1978, plaintiffs met with Boulton and negotiated a contract to purchase seven lots in Plat C of the Blackhawk Estates from Vantage. No written contract was ever presented at trial; however, most of the terms of the sale were undisputed. Plaintiffs paid $8,950 as a 10% down payment on lot numbers 18, 19 and 28 (at $13,500 per lot) and on lot numbers 34, 35, 49 and 58 (at $12,500 per lot). The interest rate was 11% per annum for the first year after electrical power was made available to the lots and 13% per annum thereafter. No duration of the contract was set; however, it can be assumed that it was short-term given its high interest rate and considering Vantage’s objectives for entering into the sale. In addition, Vantage agreed to subordinate its interest in the lots so that plaintiffs could secure construction financing, provided that such financing came from Deseret Federal. There was likewise no dispute that plaintiffs made interest payments of $4,278.59 and $2,990.32 and sold three of the seven undeveloped lots to third parties in 1979.

In the spring of 1980, plaintiffs sought a construction loan from Deseret Federal to build “spec homes” on two of the remaining four lots. Deseret Federal denied the request for a loan pursuant to its policy, then in force, to lend no money for building speculation; that is, building homes to put *415 on the market as opposed to building homes for particular buyers. When they could not obtain construction funds elsewhere, plaintiffs sought to rescind the contract to purchase the lots and to recover the amounts they had paid in principal and interest. Defendants counterclaimed to foreclose plaintiffs’ interest in the four lots.

At trial, both plaintiffs testified that during the 1978 negotiations Boulton “guaranteed” that construction financing would be available from Deseret Federal when they were ready to build. Boulton, who admitted that only he and the plaintiffs were present, could not remember making any guarantee. He stated further that he neither had authority to bind Deseret Federal to grant a loan in the future nor to process real property loans. In addition, there was evidence that guaranteeing the availability of future loans was not a normal practice of officers of either Vantage or Deseret Federal.

The trial court found that plaintiffs failed to prove that defendant’s agent Boul-ton made a guarantee as to the availability of construction financing. It then concluded that the statute of frauds, U.C.A., 1953, § 25-5-1, could not be used by the plaintiffs as a basis for rescission because there was either sufficient memoranda or part performance to take the contract out of the statute. Rescission was denied plaintiffs and foreclosure was granted to the defendant.

Plaintiffs first contend that the trial court erred in finding that no guarantee existed because defendant had admitted the guarantee in its answer to the plaintiffs’ complaint. Therefore, plaintiffs argue, the existence of the guarantee should stand as a stipulated fact. An admission of fact in a pleading is a judicial admission and is normally conclusive on the party making it. Yates v. Large, 284 Or. 217, 585 P.2d 697 (1978). See also Paul Schoonover, Inc. v. Ram Construction, Inc., 129 Ariz. 204, 630 P.2d 27 (1981). However, this rule is not absolute. The trial court may relieve a party from the consequences of a judicial admission. See 9 Wigmore on Evidence (1981), § 2590. See also McCormick on Evidence, 2nd Ed. 1972, § 265. In the instant case, the defendant admitted the guarantee in answering the plaintiffs’ first cause of action. However, in answering the plaintiffs’ fourth cause of action, which was based on fraud, the defendant denied that it had represented that it would guarantee financing. Thus the defendant’s answer was contradictory. Further, subsequent to the filing of the defendant’s answer, the plaintiffs propounded interrogatories to the defendant, one of which inquired whether the defendant ever stated that it would guarantee construction loans on the lots. Defendant answered this interrogatory with an unequivocal “No.” At the pretrial hearing, counsel for the defendant stated that his client had made no promise to make construction loans. Counsel for the plaintiffs made no response to that statement, but indicated that “it will be a factual issue.” At the trial, both parties presented testimony regarding the guarantee as though it had not been admitted in the pleadings. It was clear that the resolution of this issue would weigh heavily in determining the outcome of the case. Defendant tried to establish that Boulton did not make the guarantee and that such procedure was uncommon among its personnel. Plaintiffs, with equal vigor, adduced testimony both to establish the guarantee’s existence and to show its importance in their determination to make the purchase. It was not until counsel for the plaintiffs was making his final argument to the judge after the close of the evidence that he pointed out the admission in the defendant’s answer. Under these facts it is clear that while defendant may have negligently admitted its existence in answering the complaint, the conduct of both parties throughout the remainder of the proceeding showed that this question was a material issue for the judge to determine. Plaintiffs did not rely on the admission nor were they misled by it. There is authority that an admission may be waived where the parties treat the admitted fact as an issue. In Re Witking *416 ton’s Estate, 99 Cal.App. 617, 279 P. 196 (1929); 71 C.J.S. § 161, pg. 335. Therefore, we decline to interfere with the trial court’s discretion in not holding defendant to its admission in its answer.

Plaintiffs further contend that the trial court abused its discretion by arbitrarily finding that no guarantee had been made; that the uncontradicted testimony of the plaintiffs established its making, and Boul-ton did not testify that he did not make a guarantee but only that he “could not remember” making a guarantee. Plaintiffs rely upon McClellan v. David, 84 Nev. 283, 439 P.2d 673 (1968), where the Nevada Supreme Court found an abuse of discretion by the trial court in setting aside a default judgment. There, a secretary in the office of the plaintiffs attorney testified with exactness that she had conversed three times with the defendant by telephone soon after he had been served with summons about the necessity of his filing an answer to the complaint. Her recollection of the conversations was refreshed from written notes made by her at the time. The defendant did not deny the conversations, but simply testified that he did not recall them.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re Agusta National Trust 1
2023 UT App 135 (Court of Appeals of Utah, 2023)
Dale K. Barker Co PC CPA Profit Sharing v. Turner
2021 UT App 119 (Court of Appeals of Utah, 2021)
Salt Lake City v. Kunz
2020 UT App 139 (Court of Appeals of Utah, 2020)
Luna v. Luna
2020 UT 63 (Utah Supreme Court, 2020)
Luna v. Luna
2019 UT App 57 (Court of Appeals of Utah, 2019)
Stephenson v. Elison
2017 UT App 149 (Court of Appeals of Utah, 2017)
State v. Reece
2015 UT 45 (Utah Supreme Court, 2015)
Monarrez v. Utah Department of Transportation
2014 UT App 219 (Court of Appeals of Utah, 2014)
Roberts v. Roberts
2014 UT App 211 (Court of Appeals of Utah, 2014)
Rutherford Ex Rel. Rutherford v. Talisker Canyons Finance Co.
2014 UT App 190 (Court of Appeals of Utah, 2014)
Kranendonk v. Gregory & Swapp, PLLC
2014 UT App 36 (Court of Appeals of Utah, 2014)
Lawrence v. INTERMOUNTAIN, INC.
2010 UT App 313 (Court of Appeals of Utah, 2010)
J & M Construction, Inc. v. Southam
722 P.2d 779 (Utah Supreme Court, 1986)
Booms v. Rapp Construction Co.
720 P.2d 1363 (Utah Supreme Court, 1986)
Walker v. Walker
707 P.2d 110 (Utah Supreme Court, 1985)
Bentley v. Potter
694 P.2d 617 (Utah Supreme Court, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
676 P.2d 413, 1984 Utah LEXIS 748, Counsel Stack Legal Research, https://law.counselstack.com/opinion/baldwin-v-vantage-corp-utah-1984.