Baldridge v. Morgan

106 P. 342, 15 N.M. 249
CourtNew Mexico Supreme Court
DecidedJanuary 6, 1910
DocketNo. 1249
StatusPublished
Cited by6 cases

This text of 106 P. 342 (Baldridge v. Morgan) is published on Counsel Stack Legal Research, covering New Mexico Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Baldridge v. Morgan, 106 P. 342, 15 N.M. 249 (N.M. 1910).

Opinion

■OPINION OP THE COURT'.

MECHEM, J.

The facts in this case are: That on the 27th day of May, 1905, the appellant contracted with one A. L. Morgan for the erection of a building on appellant’s land by the terms of which contract Morgan was to build the building, furnish the necessary labor and materials for the sum of $10,000.00. The appellee on July 10, 1905, entered into an oral contract with Morgan to furnish lumber and building material' for use in the construction of appellant’s building and did furnish such ’materials, which were so used, to the amount of $4,290.53 on which appellee received the sum of $1,000.00 and no more. That the said material was furnished from time to time between July 10, 1905, and February 7, 1906. On March 27, 1906, appellee filed his notice and claim of lien in the office of the probate clerk of ¡Bernalillo County and at that time Morgan had ceased work on the building for a period "of about forty-five days. Thereafter appellant’ continued to- work, completing the building about July 1, 1906. And it also appears instead of getting the building completed according to the original plans and specifications for $10,000.00 it cost appellant, about $20,-000.00.

The court below allowed the appellee a lien for $3,251.36 with interest and costs, including costs for filing lien and $250.00 as an attorney’s fees. From this decree-the appellant appeals and seeks a reversal upon the following propositions:

1. That the claim of lien was prematurely filed and therefore void.
2. That our mechanics lien statute is unconstitutional.
3. That the mechanic’s- lien statute is in. conflict with the grant of legislative power contained in the' Organic Act, and
4. That no attorney’s fees should' have been allowed-

It is an admitted fact as shown by the record that the notice and claim of lien was filed March 27, 1906, and that the building was not completed until about July 1, of the same year. Our statute fixing the time for filing a lien is as follows:

“Every original contractor, within ninety days after the completion of his contract, and every person save the-original contractor, claiming the benefit of this act, must within sixty days after the completion of any building, file-for record 'with the county recorder of the county in which said property or some part thereof is situated, a-. claim containing a statement of his demands, etc.” Compiled Laws 1897, sec. 2221.

In his brief the able counsel for the appellant says that he finds “this court committed to the proposition that a substantial completion of the building is requisite before a lien can be filed.” Citing Genest v. Building Assn., 11 N. M. 251, 67 Pac. 743.

We cannot agree with this statement for we are of the opinion that the only question decided in that case was that a substantial completion- was a completion within the terms of the statute and that the court neither in express terms ox by implication held that a completion of the building was a requisite to the filing of a lien. That question was not before the court in that case.

Here the question is squarely presented to us whether the legislature fixed a period of time during which a lien of a sub-contractor must be filed or did it fix a point of time after which such a lien could not be filed.

In the ease of Davies v. Miller, 9 Sup. Ct. 560, 130 U. S. 284, 32 L. ed. 932, the court says:

“The clause requiring the importer to give such notice” within ten days after the ascertainment and liquidation of the duties “must therefore, according to the fair and reasonable interpretation of the words as applied to the subject matter, be held to fix only the terminus ad quern, the limit beyond which the notice shall not be given, and .not to fix the final ascertainment and liquidation of the duties as the terminus a quo, or the first point of time at which the notice may be given.”

To hold that the completion of a building was a requisite to the filing of a lien by a sub-contractor -would not be a fair and reasonable interpretation of the words “within sixty days after the completion of any building, etc.,” as applied to the subject matter. When the sub-contractor has performed labor or furnished materials his contract is executed. The building might be years in construction or it might never be completed, and when by force of the statute a privity of contract exist between the -owner and a sub-contractor without reference to the original contractor there is no good reason, nor is it just that the sub-contractor should be compelled to wait upon the happening of an event which neither fixes nor affects, his rights, and which he cannot control. Hobbs v. Spiegelberg, 3 N M. 357, 5 Pac. 529.

1 We therefore hold that the clause that requires a subcontractor to file his claim of lien “within sixty days after the completion of anjr building, etc.,” fixes a time after which such lien is not to be filed and does not fix a period of time during which it must be filed or in other words that the time for filing does'not commence to run from or await the completion of the building. Hunter et al, v. Truckee, Lodge, 14 Nev. 24.

Our attention has been called to numerous cases, especially from California and Kansas, where a different rule has been announced but it is to be observed that the statutes under consideration there gave the sub-contractor a lien solely by way of subrogation to the rights of the original contractor, while under our statute the sub-contractor has a direct lien. Hobbs v. Spiegelberg, 3 N. M. 357, 5 Pac. 529.

2. That because our mechanic’s lien statute permits liens- to be asserted in excess of the contract price of the building or other improvements, the appellant contends that it is a restraint on the liberty of contract and it is a taking of property without due process of law.

Since its adoption in' 1880, different phases of this” act have been the subject of many cases in this court, but never before has its validity been questioned.

However, in a number of states the constitutionality of statutes permitting liens in excess of the contract price agreed upon between owner and original contractor, have been upheld. Bowen, et al., v. Phinney, 162 Mass. 593, 39 N. E. 283, 44 Am. St. Rep. 39; Laird v. Noonan, 32 Minn. 358, 20 N. W. 354; Cole Mfg. Co. v. Falls, 90 Tenn. 466, 16 S. W. 1045; Mallory v. La Crosse Abattoir Co., 80 Wis. 170; 49 Wis. 1071.

In Great Southern Fire Proof Hotel Co. v. Jones, 193 U. S. 532

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Coldiron v. Gaster
278 A.2d 328 (Superior Court of Delaware, 1971)
Allison v. Schuler
36 P.2d 519 (New Mexico Supreme Court, 1934)
National Surety Co. v. W. H. Holliday Co.
295 P. 913 (Wyoming Supreme Court, 1931)
Hume v. Seattle Dock Co.
137 P. 752 (Oregon Supreme Court, 1914)
Arizona Eastern Railroad v. Globe Hardware Co.
129 P. 1104 (Arizona Supreme Court, 1913)
Gray v. New Mexico Pumice Stone Co.
15 N.M. 478 (New Mexico Supreme Court, 1910)

Cite This Page — Counsel Stack

Bluebook (online)
106 P. 342, 15 N.M. 249, Counsel Stack Legal Research, https://law.counselstack.com/opinion/baldridge-v-morgan-nm-1910.