Baldi Construction Engineering, Inc. v. Wheel Awhile, Inc.

284 A.2d 248, 263 Md. 670, 1971 Md. LEXIS 731
CourtCourt of Appeals of Maryland
DecidedDecember 13, 1971
Docket[No. 102, September Term, 1971.]
StatusPublished
Cited by8 cases

This text of 284 A.2d 248 (Baldi Construction Engineering, Inc. v. Wheel Awhile, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Baldi Construction Engineering, Inc. v. Wheel Awhile, Inc., 284 A.2d 248, 263 Md. 670, 1971 Md. LEXIS 731 (Md. 1971).

Opinion

Finan, J.,

delivered the opinion of the Court.

This appeal involves the question of whether a verbal understanding between the parties to a cost plus construction contract, that the proposed project would be within a given cost range, justified the cancellation of the written contract by the property owner when the contractor presented an estimate substantially in excess of the price range contemplated between the parties, the written contract containing no mention of any cost estimate.

The appeal arises from the execution on February 18, 1969, of an American Institute of Architects (A.I.A.) *672 standard form of “cost of the work plus a fee” contract by the appellant, Baldi Construction Engineering, Inc. (Baldi), and the appellee, Wheel Awhile, Incorporated (Wheel Awhile). The contract provided for Baldi to construct a roller skating rink for Wheel Awhile on property owned by the appellee in Lanham, Maryland. The price to be paid by Wheel Awhile for the erection of the rink was to be all actual costs of engineering, architectural, surveying and testing work plus a 5% fee and all construction costs plus a 10% fee. Although plans' and specifications were not incorporated into the contract at the time of execution, it was provided that they were “to be listed when approved by Owner and Contractor.”

Prior to the execution of the A. I. A. contract, Mr. Eugene F. Baldi, the President of the appellant corporation, together with Mr. John D. Becker and Mr. Maurice E. Hankey, agents for Wheel Awhile, inspected a roller rink which had been built by Mr. Hankey in Reading, Pennsylvania and which was to serve as a prototype for the rink to be constructed in Lanham. The testimony adduced in the lower court reveals a discrepancy as to what took place during the meeting in Reading. Mr. Becker testified that Mr. Baldi was made aware of the fact that Wheel Awhile had only $160,000.00 to spend for the Lanham project and that Mr. Baldi stated that he could build the Lanham rink for that amount or at a figure lower than the $160,000.00 cost of the Reading rink. Mr. Hankey confirmed Mr. Becker’s testimony, however, Mr. Baldi testified that he could not recall any discussion concerning the cost of the proposed rink.

Mr. Lewis, an architect in Prince George’s County, was given a copy of the plans and specifications for the type of structure which had been built in Reading, Pennsylvania, and for the sum of $1,000.00 took on the assignment of adjusting the plans to the Lanham site. The building as finally constructed in Prince George’s County was some 20 feet longer than the Reading building and some 2,000 square feet larger in area. The architect com *673 pleted the first preliminary drawings on March 4, 1969, although the written contract executed February 18, 1969, states they were then prepared. The building permit applied for on April 29, 1969, stated the construction cost to be $80,000.00.

In June, 1969, some weeks after Baldi had begun work on the Lanham site, Baldi presented Wheel Awhile a cost-run-down, showing a projected total construction cost of $230,651.00 for the rink. Upon receipt of the rundown, Mr. Hankey of Wheel Awhile demanded that Baldi - stop work on the project. Wheel Awhile then proceeded to complete the construction of the rink at a cost of $167,705.74.

Baldi brought suit against Wheel Awhile in the Circuit Court for Prince George’s County alleging that the appellee breached the contract that it signed with Baldi and sought damages in the form of profits lost because of the breach. At the request of the defendant the case was removed to the Circuit Court for Calvert County where it was heard by Bowen, J., without a jury. The court ruled that Wheel Awhile was justified in refusing to perform the contract since it would have been impossible for it to pay the projected cost of $230,651.00. However, the court proceeded to award Baldi a judgment in the amount of $3,264.23 on a quantum meruit basis from which Baldi now appeals.

In this case we agree with the conclusion reached by the lower court but for a different reason. The court below predicated its finding that Wheel Awhile should not be liable on the cost plus contract, on the theory that Baldi knew that the outer limits of Wheel Awhile’s financial capability was in the $160,000.00 cost range and that by presenting it with an estimate of $230,651.00 for the building, rendered the contract on the part of Wheel Awhile impossible of performance. However, we do not believe that the financial inability of one of the contracting parties to meet the contract price is an adequate ground upon which to grant rescission of a contract on the basis of impossibility of performance. See 6, Corbin *674 on Contracts, Section 1332, p. 362-363 and Christy v. Pilkinton, 273 S.W.2d 533 (Ark. 1954), wherein the distinction between subjective impossibility of performance and objective impossibility is discussed.

In reaching its conclusion the lower court did make the finding of fact that Baldi knew that Wheel Awhile could not finance a building substantially in excess of $160,000.00. Implicit in such a finding is the conclusion that the court believed the testimony of witnesses Becker and Hankey, agents of Wheel Awhile, who testified as to the discussions they had with Mr. Baldi, representing Baldi, wherein it was made clear to him that Wheel Awhile could not afford a building in excess of $160,000.-00. Witnesses Becker and Hankey both testified that they informed Baldi that they had $80,000.00 in cash and could obtain financing for an additional $80,000.00. This discussion took place in October or November of 1968, while the representatives of the parties were viewing the prototype roller rink in Reading, several months prior to the execution of the contract. Mr. Hankey also testified that after execution of the contract and prior to the commencement of the construction, he had repeatedly tried to obtain an estimate from Baldi but to no avail. Maryland Rule 886 requires that we accept the finding of facts of the lower court unless they appear to be clearly erroneous, which in this instance they do not. The question then to be answered is, what relevance did the fact that the contracting parties shared a mutual knowledge of this $160,000.00 limitation on construction cost have on the contract subsequently executed on February 18, 1969.

No objection was raised as to the admissibility of the testimony regarding the $160,000.00 limitation on construction costs by Baldi’s counsel; Mr. Baldi simply denied it in his own testimony. However, in the case at bar, although we are not faced with the admissibility of parol evidence vel non, as we were in Pumphrey v. Kehoe, 261 Md. 496, 504, 276 A. 2d 194 (1971), and Mascaro v. Snelling and Snelling, 250 Md. 215, 229, 243 A. 2d 1 (1968), *675 we must view the relevance of this parol evidence with reference to the written cost plus contract.

In Ebert v. Millers Fire Ins. Co., 220 Md. 602, 610, 155 A. 2d 484 (1959), Chief Judge Bruñe writing for the court, commented:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Claggett v. Maryland Agricultural Land Preservation Foundation
957 A.2d 1083 (Court of Special Appeals of Maryland, 2008)
East Capitol View Community Development Corp. v. Robinson
941 A.2d 1036 (District of Columbia Court of Appeals, 2008)
Housing Opportunities Commission v. Lacey
585 A.2d 219 (Court of Appeals of Maryland, 1991)
Sornberger v. Chesapeake & Ohio Railway Co.
566 A.2d 503 (Court of Special Appeals of Maryland, 1989)
Stone v. Stone
368 A.2d 496 (Court of Special Appeals of Maryland, 1977)
Ryan v. Thurston
347 A.2d 834 (Court of Appeals of Maryland, 1975)
Levine v. Rendler
320 A.2d 258 (Court of Appeals of Maryland, 1974)
Harford Sod Co. v. Randall Development Corp.
285 A.2d 656 (Court of Appeals of Maryland, 1972)

Cite This Page — Counsel Stack

Bluebook (online)
284 A.2d 248, 263 Md. 670, 1971 Md. LEXIS 731, Counsel Stack Legal Research, https://law.counselstack.com/opinion/baldi-construction-engineering-inc-v-wheel-awhile-inc-md-1971.