Baldi Bros., Inc. v. United States

133 Fed. Cl. 801, 2017 WL 4052368
United States Court of Federal Claims·Decided September 13, 2017·No. No. 15-1300 C·Published·Cited by 1 cases

Opinion

OPINION

CAMPBELL-SMITH, Judge

This case involves a contract for repairs to the “Combat Air craft Loading Apron” located at the Marine Corps Air Station in Yuma, Arizona. See Compl., ECF No. 1 at 2. In its complaint, plaintiff explains that it committed an error that was “clerical in nature” in calculating its final bid amount. See id. After awarding the contract to plaintiff on the basis of the erroneous bid amount, the contracting officer denied plaintiffs request for a contract modification to correct the error. See id. at 3-4. The contracting officer subsequently denied plaintiffs certified claim, and plaintiff now seeks relief from the court. See id. at 4. Presently before the court is defendant’s motion for partial summary judgment.2 See Def.’s Mot., ECF No. 22, Defendant’s motion is fully briefed and ripe for a decision by the court. Oral argument was neither requested by the parties, nor-deemed necessary by the court. For the following reasons, the defendant’s motion is GRANTED

I. Background

In July 2013, defendant issued a request for proposal (RFP) relating to repairs and improvements to the Combat Aircraft Loading Apron at the Marine Corps Air Station in Yuma, Arizona. See ECF No. 1 at 2. See also ECF No. 22 at 2. The project included a bid for a base contract, along with five optional line items. See ECF 1 at 2. See also ECF No. 22 at 2. The RFP éxpressly states that, with regard to the evaluation of price, “[t]he Government will evaluate the total price (base items and all option items) on the basis of whether or not it is fan’ and reasonable and within the limitation stated in the RFP.” Def.’s Mot. App., ECF No. 22-1 at 116. It also states that “[ajward will be made on the basis of the lowest evaluated price of proposals meeting or exceeding the acceptability standards for non-cost factors.” Id

The technically acceptable offers were as follows:

[[Image here]]

ECF No. 22 at 2. As this chart illustrates, of the four technically acceptable offers, plaintiffs bid amount was lowest. On September 27, 2013, defendant awarded the contract to plaintiff. See ECF No. 1 at 2.

Shortly after receiving the award, plaintiff discovered—later the same day—that its bid inadvertently failed to include an applicable 6,7% state tax, amounting to $743,689.32. See id. Plaintiff immediately notified defendant of the omission, which it characterizes as a clerical error, and sought a contract modification to include the state taxes. See id. at 3. Defendant, in turn, reviewed documentation supporting plaintiffs request, but denied the modification, finding that it was not warranted. See id.

Plaintiff contends that it is entitled to an adjustment of its bid in accordance with the Federal Acquisition Regulation (FAR) 14.407-4, which applies in cases involving mistakes discovered after an award. See id. at 4. Pursuant to this regulation, plaintiff submitted a certified claim under the Contract Disputes Act to the contracting officer, seeking $961,132.39. See id. See also ECF No. 22-1 at 228-292 (plaintiffs certified claim). This figure is higher than the original contract modification for two reasons. First, it reflects an 8.4% tax. See ECF No. 1 at 3. The tax percentage was increased from 6.7% to include a county tax of 1.7% that was not included in plaintiffs initial modification request. See ECF No. 22 at 3; ECF No. 25 at 5. In addition, this figure includes costs for several line item options that defendant elected after awarding the contract, totaling $28,745.77. See ECF No. 26 at 9, Def s Reply (citing plaintiffs certified claim, ECF No. 22-1 at 280). Thus, the total value of the requested modifications to account for taxes is $932,386.62. See id.

In summary, plaintiff has, in one form or another, submitted three contract amounts in this ease: (1) its original bid that excluded taxes, (2) its modification request that included only state taxes, and (3) its certified claim that included both state and county taxes. The following table incorporates each submission for ease of reference.

See ECF No. 22 at 4-6. See also ECF No. 25 at 3-6 (detailing some of the figures in defendant’s chart).

The contracting officer denied the claim for three reasons: (1) plaintiff had not submitted clear and convincing evidence of a clerical error; (2) defendant was not on constructive notice of the error; and (3) if the contract amount were adjusted, plaintiff would no longer be the lowest bidder, and defendant would have to terminate the contract for convenience and award it to the lowest bidder. See id. at 4. In the present case, plaintiff disputes these findings, and asks the court to award damages in the amount of its certified claim, $961,132.39, plus interest. See id. at 5.

II. Legal Standards

Plaintiff brings this ease pursuant to the Contract Disputes Act. See ECF No. 1 at 1 (citing 41 U.S.C. § 609(a)(1), presumably referring to the code section that now appears as 41 U.S.C. § 7104(b)(1) (2012)). In order for this court to exercise jurisdiction under the Contract Disputes Act, “both a valid claim and a contracting officer’s final decision on that claim,” are required. M. Maropakis Carpentry, Inc., v. United States, 609 F.3d 1323, 1327 (Fed. Cir. 2010) (citing James M. Ellett Constr. Co. v. United States, 93 F.3d 1537, 1541-42 (Fed.Cir. 1996)). See also Lee’s Ford Dock, Inc., v. Sec’y of the Army, 865 F.3d 1361, 1370-71 (Fed. Cir. 2017) (holding that the court lacked jurisdiction pursuant to the Contract Disputes Act to consider plaintiffs claim that was not properly presented for final decision to the contracting officer). In addition, because the court’s review is de novo, the contracting officer’s decision is afforded no deference. See 41 U.S.C. § 7104(b)(4) (2012); Wilner v. United States, 24 F.3d 1397, 1401 (Fed. Cir. 1994) (stating that “when suit is brought following a contracting officer’s decision, the findings of fact in that decision are not binding upon the parties and are not entitled to any deference”).

Summary judgment is appropriate when there is no genuine issue of material fact and the moving party is entitled to judgment as a matter of law. RCFC 56(a); Celotex Corp. v. Catrett, 477 U.S. 317, 322, 106 S.Ct. 2548, 91 L.Ed.2d 265 (1986). A fact is material if it “might affect the outcome of the suit under the governing law.” Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 248, 106 S.Ct. 2505, 91 L.Ed.2d 202 (1986).

Free access — add to your briefcase to read the full text and ask questions with AI

Baldi Bros., Inc. v. United States, 133 Fed. Cl. 801, 2017 WL 4052368 (uscfc 2017).

133 Fed. Cl. 801 (Baldi Bros., Inc. v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Omran Holding Group, Inc. v. United States
134 Fed. Cl. 561 (Federal Claims, 2017)