Balaban-Gordon Co. v. Brighton Sewer District No. 2

67 Misc. 2d 76, 323 N.Y.S.2d 724, 1971 N.Y. Misc. LEXIS 1370
CourtNew York Supreme Court
DecidedAugust 9, 1971
StatusPublished
Cited by4 cases

This text of 67 Misc. 2d 76 (Balaban-Gordon Co. v. Brighton Sewer District No. 2) is published on Counsel Stack Legal Research, covering New York Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Balaban-Gordon Co. v. Brighton Sewer District No. 2, 67 Misc. 2d 76, 323 N.Y.S.2d 724, 1971 N.Y. Misc. LEXIS 1370 (N.Y. Super. Ct. 1971).

Opinion

James H. Boomer, J.

Plaintiff, a construction contractor, brings this action to rescind a bid submitted by it to the defendant sewer district, and for the return of its bid bond, because of an alleged mistake in the bid. The action was tried before me without a jury and this is my decision under CPLR 4213.

The facts proven are as follows:

The sewer district advertised for bids for the construction of improvements to two existing sewage treatment plants in the district. The construction work for each plant was divided into four separate sections: general construction, plumbing and equipment, electrical, and heating. Bidders were invited to sub[77]*77mit bids on any one or more of these sections and on any combinations of sections for either or both plants and the sewer district reserved the right to award contracts based upon the lowest responsible bid for each section or combination of sections.

The plaintiff submitted several bids, one for the general construction for both plants; one for the plumbing and equipment for both plants; one for the electrical work for both plants; and other bids for the work at both plants based upon an award of various combinations of general construction, plumbing and equipment, and electrical work. When the bids were opened on October 19,1967, it appeared that the plaintiff was the lowest bidder for the general construction contract for both plants, but was not the lowest bidder for the plumbing and equipment contract. Its bid of $2,249,700 for the general construction work for both plants was $330,300 lower than the next highest bidder, while its bid on the plumbing and equipment work was $376,230 higher than the only other bidder for that work.

The day after the bids were opened, the plaintiff sent a telegram to the engineer for the sewer district stating that, in computing its bid for the general construction contract, it erroneously omitted certain items of equipment and included these items in computing its bid for the plumbing and equipment contract ; that it wished to withdraw its bids; and that it was prepared to meet with the engineer at once with its bid worksheets to substantiate this mistake.

Three days later, on October 23, 1967, representatives of the plaintiff met with representatives of the .sewer district and its engineer and, with their worksheets, plaintiff’s representatives explained their mistake. At that time, plaintiff’s representatives stated that, since their combined bid for the general construction and plumbing contract was lower than any other combination of bids submitted by others for the work, they were willing to accept an award to them based upon their bid on the general construction work and plumbing and equipment work combined. The sewer district refused to permit the plaintiff to withdraw its bid and awarded to it the general construction contract only, for both plants.

Plaintiff’s worksheets demonstrate that the plaintiff listed items of mechanical equipment of a toal cost of $230,054 in its calculations for the plumbing bid and omitted these items in its calculations for the general construction bid. The engineer for the .sewer district interpreted the specifications as requiring these items to be furnished under the general construction, con[78]*78tract. The court agrees that this is the proper interpretation. Plaintiff, therefore, was mistaken in omitting these items from its calculations for general construction bid. If it had correctly included these items in its general construction bid calculations, and added 22% for profit and overhead (as it did on the other items), its bid for the general construction contract would have been $305,065 higher than the figure it submitted.

Plaintiff claims it was misled by certain ambiguous phraseology in the specifications, which states: Treatment Plant — Plumbing and Equipment: Shall cover all equipment, piping and appurtenances within the blower, prechlorination, postchlorination, utility and generator buildings and the efficient water ¡systems valve unit at Allens Creek Plant; and the control and service buildings at Rich’s Dug-way Plant; except only such work as is specifically covered by items 31AH, 31RH, 41AAE and 41RE. These items include all equipment, piping and appurtenances, within these structures specified under sections 28, 32, 36, 65, 66, 67, 70, 77 and 79 of the specifications.” Plaintiff interpreted this paragraph to mean that all items of equipment in the enumerated sections (28, 32, etc.) were to be included under the plumbing and equipment contract. The engineer for the sewer district, on the other hand, meant this paragraph to mean that the items of equipment to be included in the plumbing and equipment contract were only those items in the enumerated sections which were to be located in the buildings referred to in the first sentence. In other words, the plaintiff assumed that the word these structures ” referred to the structures specified under the enumerated sections and the engineer intended the words, these structures ” to refer to the buildings described in the first sentence of the paragraph.

Nevertheless, a reading of the specifications in their entirety leads to the conclusion that the items in question were intended to be furnished under the general construction contract and not under the plumbing and equipment contract. On page 100 PI-IX of the specifications it is stated that the general contract shall include 1 furnishing and installing all equipment, piping and appurtenances * * * within ‘1 certain specified structures. The equipment in question, as shown by the plans, is located in the structures specified on page 100 PI-IX and consequently was to be furnished under the general construction contract.

Plaintiff, therefore, made a mistake. And due to this mistake it failed to include in its bid calculations for the general construction contract items of equipment it valued at approximately $350,000. The defendant sewer district contends that the plain[79]*79tiff should not be relieved from its bid, for the mistake was due to the negligence of the plaintiff. It also contends that this was not such a mistake for which a court of equity will grant relief to a contractor who has submitted a bid on a public contract.

Section 105 of the General Municipal Law provides that bids made to political subdivisions, such as the defendant, shall be accompanied by a bid bond and the bid bond may be withdrawn “ if no award of the contract be made within 45 days after receipt thereof.” This section has the effect of making a bid upon a public contract irrevocable for a period of 45 days. Nevertheless, the fact that a bid is irrevocable and may not be withdrawn, does not prevent a court from granting equitable relief rescinding the bid upon the ground of mistake. ‘ ‘ Prohibitions of and restrictions upon withdrawal of bids for public contracts, whether evidenced by rules of law or provisions created by parties, have been uniformly construed as inapplicable to prevent, when the need arises, equitable relief from the consequences of a submission of a bid based upon a mistake which is remediable in equity.” (Ann. 52 ALR 2d 792, 806.)

The courts of this State have long recognized that one who makes a bid based on an honest and unintentional mistake can in the interest of equity be relieved from his contractual obligations [citing cases].” (People v. Rouse Constr. Corp., 26 A D 2d 405, 407).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Arlington Park Racetrack Ltd. v. SRM Computers, Inc.
674 F. Supp. 986 (E.D. New York, 1987)
State v. Atlantic Audio-Visual Corp.
118 A.D.2d 998 (Appellate Division of the Supreme Court of New York, 1986)
Triple a Contractors, Inc. v. Rural Water District No. 4
603 P.2d 184 (Supreme Court of Kansas, 1979)
De Paola v. City of New York
90 Misc. 2d 379 (New York Supreme Court, 1977)

Cite This Page — Counsel Stack

Bluebook (online)
67 Misc. 2d 76, 323 N.Y.S.2d 724, 1971 N.Y. Misc. LEXIS 1370, Counsel Stack Legal Research, https://law.counselstack.com/opinion/balaban-gordon-co-v-brighton-sewer-district-no-2-nysupct-1971.