Baker v. Flint Engineering & Construction Co.

137 F.3d 1436, 4 Wage & Hour Cas.2d (BNA) 673, 1998 Colo. J. C.A.R. 1353, 1998 U.S. App. LEXIS 3904, 1998 WL 97208
CourtCourt of Appeals for the Tenth Circuit
DecidedMarch 6, 1998
Docket96-2133
StatusPublished
Cited by106 cases

This text of 137 F.3d 1436 (Baker v. Flint Engineering & Construction Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Tenth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Baker v. Flint Engineering & Construction Co., 137 F.3d 1436, 4 Wage & Hour Cas.2d (BNA) 673, 1998 Colo. J. C.A.R. 1353, 1998 U.S. App. LEXIS 3904, 1998 WL 97208 (10th Cir. 1998).

Opinion

*1439 BRISCOE, Circuit Judge.

Plaintiffs are a group of rig welders in the natural gas pipeline construction industry. They filed this action against Flint Engineering & Construction Company for overtime compensation under the Fair Labor Standards Act (FLSA), 29 U.S.C. § 201 et seq. Flint appeals the district court’s entry of summary judgment in favor of plaintiffs, contending the court erred in concluding plaintiffs were employees of Flint rather than independent contractors. We exercise jurisdiction under 28 U.S.C. § 1291 and affirm.

I.

Flint is a corporation engaged in the construction, installation, and servicing of oil and gas pipelines and related facilities for the oil and gas industry in the “Four Corners” region of New Mexico. In particular, Flint is routinely hired as a general contractor by oil and gas companies to build natural gas pipelines and compressor stations which transport natural gas from the wellheads to the owner’s main processing plants.

When Flint is the successftd bidder on a project (or is otherwise hired to complete a project), it hires a variety of workers, including rig welders, to assist in completion of the project. Rig welders (a/k/a pipe welders) perform skilled welding on pipes, sheet metal, and other portions of gas industry facilities. They are routinely tested and certified by project owners to insure they can perform their jobs. They provide their own welding equipment, which is typically mounted on flat-bed pickup trucks. The equipped trucks are referred to as “welding rigs,” and each welding rig costs between $35,000 and $40,-000. Rig welders are also responsible for costs of stocking their welding rigs with supplies,, as well as for necessary repairs to the rigs. Rig welders do not bid on jobs and do not have contractor’s licenses that would enable them to do so. Flint simply hires rig welders at a set hourly rate to work on particular projects. Flint does not negotiate the hourly rate, and sometimes pays on a “straight contract” basis at approximately $27 to $30 per hour, and sometimes on a “split check” basis at a rate of $10 per hour for labor and $17 per hour for rig rental.

Work on a project is typically conducted six days a week, twelve to fourteen hours per day. Rig welders are supervised by Flint foremen and are required to arrive, take breaks, and leave at times specified by the foremen. They are not allowed to complete their work when they want and, in most cases, it would be impossible for them to do so because they must coordinate their work with the other crafts and because other equipment and workers are necessary to move pipe for welding. Rig welders are not provided project blueprints. Instead, the foremen map out what pipes they want built and in what order. The foremen do not establish the welding specifications and standards, nor do they tell rig welders how to weld or how-long a particular weld should take. Welding specifications and standards are established by the customer (i.e., the project owner) and the quality of welding is overseen by an inspector hired by the customer. Because of the nature of their work, rig welders (and other pipeline workers) would be unemployed after completion of a project if they did not seek work on new projects. Accordingly, it is common for rig welders to work for several different-companies during the course of a year.

Prior to July 1, 1991, Flint considered rig welders as independent contractors and asked each rig welder to sign a document entitled “Agreement With Independent Contractor,” which stated:

It is the intent of the parties involved to establish and maintain an “independent relationship” rather than an employer-employee relationship. All Federal, State and Local laws, regulations, and guidelines should be adhered to accordingly. The Independent Contractor is responsible for maintaining adequate amounts of insurance.

R. I at 49. The agreements did not indicate how long the “independent relationship” was to last, did not refer to specific projects or project specifications, and did not indicate how much the welder was, to be paid. Although Flint began characterizing rig welders as employees on and after July 1, 1991, *1440 no other substantial changes took place in the way they were hired or treated.

Flint treats the majority of workers on each project as employees. For example, job foremen are treated and paid as employees, as are laborers, pipefitters, and welders’ helpers (all of whom, like rig welders, are hired on a per project basis). Flint treats a few other workers (e.g., insulation workers, electrical workers) on each project as subcontractors or independent contractors. These subcontractors are paid on a lump-sum basis or a unit basis.

Plaintiffs filed this action on February 5, 1993, claiming violations of the FLSA. The parties filed cross-motions for summary judgment, all of which focused on whether plaintiffs were employees of Flint prior to July 1, 1991, for purposes of the FLSA. The district court conducted an evidentiary hearing and, on May 26, 1994, granted summary judgment in favor of plaintiffs on the independent contractor/employee issue, concluding plaintiffs were employees prior to July 1, 1991. Thereafter, the parties reached a settlement of other issues unrelated to the independent contractor/employee issue. On June 3, 1996, the court entered final judgment in favor of plaintiffs on the independent contractor/employee issue, consistent with its May 24, 1994, order, and concluded the settlement between the parties resolved all remaining issues asserted by plaintiffs against Flint. The court further found that, pursuant to Rule 54(b) of the Federal Rules of Civil Procedure, there was no just reason for delay of entry of final judgment on the order granting summary judgment in favor of plaintiffs.

II.

The FLSA defines an employee as “any individual employed by an. employer.” 29 U.S.C. § 203(e)(1). In turn, “employer” is defined as including “any person acting directly or indirectly in the interest of an employer in relation to an employee.” 29 U.S.C. § 203(d). The FLSA “defines the verb ‘employ’ expansively to mean ‘suffer or permit to work.’” Nationwide Mut. Ins. Co. v. Darden, 503 U.S. 318, 326, 112 S.Ct. 1344, 1350, 117 L.Ed.2d 581 (1992) (quoting 29 U.S.C. § 203(g)). The Supreme Court has emphasized that the “striking breadth” of this latter definition “stretches the meaning of ‘employee’ to cover some parties who might not qualify as such under a strict application of traditional agency law principles.” Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
137 F.3d 1436, 4 Wage & Hour Cas.2d (BNA) 673, 1998 Colo. J. C.A.R. 1353, 1998 U.S. App. LEXIS 3904, 1998 WL 97208, Counsel Stack Legal Research, https://law.counselstack.com/opinion/baker-v-flint-engineering-construction-co-ca10-1998.