Baker Group v. Burlington Northern
Opinion
United States Court of Appeals FOR THE EIGHTH CIRCUIT
No. 99-3054 No. 99-3426
The Baker Group, L.C., et al., *
*
Plaintiffs - Appellants, * * Appeals from the United States v. * District Court for the * Western District of Missouri.
Burlington Northern and Santa Fe * Railway Company, *
*
Defendant - Appellee. *
No. 00-2215
In Re: The Baker Group, L.C., et al., *
*
Petitioners. *
Submitted: May 10, 2000
Filed: October 3, 2000
Before BOWMAN, FLOYD R. GIBSON,1 and LOKEN, Circuit Judges.
1 Complications from an automobile accident have prevented Judge Gibson from reviewing this opinion prior to its being filed.
LOKEN, Circuit Judge.
In 1987, The Baker Group, L.C., and the MTY Profit Sharing Plan and Trust (collectively “the Baker Group”) leased over 600 covered grain railcars to the Burlington Northern and Santa Fe Railway Company (“BNSF”) for a lease term ending October 31, 1997.2 Article 8 of the lease governed maintenance and modification of the railcars during the term of the lease. Article 14 governed return of the railcars to the Baker Group at the end of the lease. In March 1996, the Baker Group sued BNSF in a Kansas state court for alleged breaches of Article 8. That lawsuit ended in a judgment on the merits in favor of BNSF after the lease expired. In this case, the Baker Group sued BNSF for breaches of Article 14, alleging that BNSF failed to return the railcars in proper condition when the lease expired. The district court granted BNSF summary judgment, concluding that the Baker Group’s Article 14 claims are barred by claim preclusion (res judicata). The Baker Group appeals, challenging this and other rulings. The parties agree that Kansas law governs. Applying that law, we conclude that claim preclusion does not bar breach-of-contract claims that arose after the first action was filed. Accordingly, we reverse in part.
I. The Claim Preclusion Issue.
“[A] federal court must give to a state-court judgment the same preclusive effect as would be given that judgment under the law of the State in which the judgment was rendered.” Migra v. Warren City Sch. Dist. Bd. of Educ., 465 U.S. 75, 81 (1984). The doctrine of claim preclusion under Kansas law bars a party from relitigating claims that were litigated or could have been litigated in a prior suit. See In re Reed, 693 P.2d 1156, 1160-61 (Kan. 1985). The Kansas law of claim preclusion does not differ significantly from federal law. See Stanfield v. Osborne Indus., Inc., 949 P.2d 602,
2 The lease was initially entered into by the parties’ predecessors-in-interest, but that is irrelevant to the issues on appeal.
608, 610-11 (Kan. 1997). Here, the critical issue is whether the Baker Group litigated or could have litigated its Article 14 claims in the prior Kansas lawsuit.
Article 8 of the lease provides that, during the term of the lease, BNSF as lessee must “maintain the cars in good condition and repair,” “not alter the physical structure” of the cars without the Baker Group’s approval, and indemnify the Baker Group “for all loss, damage and destruction of cars.” In the Kansas case, the Baker Group alleged that BNSF breached Article 8 by modifying railcars and scrapping damaged railcars without the Baker Group’s prior permission. In this case, the Baker Group alleges that BNSF breached Article 14 of the lease, which provides that, within ten days after expiration, BNSF must return each railcar --
free from residue, and in the same order and condition as it was delivered by [the Baker Group] to [BNSF], except for and subject to ordinary wear and tear and modifications permitted under this Agreement.
The Baker Group filed its Petition commencing the Kansas case in March 1996.
Obviously, no claim for breach of Article 14 could have been asserted at that time, because BNSF was not obligated to return the railcars until the lease expired in October 1997. It is well settled that claim preclusion does not apply to claims that did not arise until after the first suit was filed. See Florida Power & Light Co. v. United States, 198 F.3d 1358, 1360-61 (Fed. Cir. 1999), and cases cited. Thus, “[a] judgment in an action for breach of contract does not normally preclude the plaintiff from thereafter maintaining an action for breaches of the same contract that consist of failure to render performance due after commencement of the first action.” RESTATEMENT (SECOND) OF JUDGMENTS § 26, cmt. g (1982). The Supreme Court of Kansas applied these principles in Gordon v. Consolidated Sun Ray, Inc., 352 P.2d 951, 953 (Kan. 1960), holding that a separate cause of action for unpaid rent arose each month of a lease, and the lessor “could not recover any deficiency until it had actually occurred.”
The Kansas case was tried on the merits one year after the lease expired.
Because the Baker Group’s Article 14 claims arose at expiration, BNSF argues they could have been brought in the Kansas case and are therefore precluded in this case. We disagree. Both rule 15(d) of the Federal Rules of Civil Procedure and its Kansas counterpart, KAN. STAT. ANN. § 60-215(d), provide that the trial court may permit a plaintiff to supplement its complaint with a cause of action arising after the original complaint. The rule is permissive for the parties and discretionary for the court. Thus, the Baker Group’s failure to supplement its already-commenced Kansas lawsuit did not raise a res judicata bar that precludes a second suit based upon BNSF’s later conduct. See Maharaj v. Bankamerica Corp., 128 F.3d 94, 97 (2d Cir. 1997).
BNSF next argues that the Article 14 claims are precluded because they were actually litigated in the Kansas lawsuit. This contention requires a close look at the Kansas proceedings. To put the inquiry in clearer focus, we begin by quoting a relevant passage from the RESTATEMENT (SECOND) OF JUDGMENTS § 26, cmt. g:
In the event of a “material” breach . . . the plaintiff is entitled to treat the contract as at an end and to recover damages for performances not yet due as well as those already due on the theory that there has been a total breach of contract. If the plaintiff does this, a judgment extinguishing the claim under the rules of merger or bar precludes another action by him for further recovery on the contract. On the other hand, although the breach is material, the plaintiff may elect to treat it as being merely a partial breach. If he so elects, he is entitled to maintain an action for damages sustained from breaches up to the time of the institution of the action, and the judgment does not preclude a further action by him for a breach occurring after that date.
Immediately after commencing the Kansas lawsuit, the Baker Group moved for a temporary injunction declaring the lease in default and ordering BNSF to return the railcars “to contract shops for inspection and repairs under Article 14.” This remedy is consistent with a claim of material breach, and had the Kansas court granted that
injunctive relief, the lease would have been effectively terminated, and claims for “performances not yet due” -- to use the above-quoted Restatement terminology -- would have been extinguished by the final judgment in the Kansas action. But the Kansas court denied a temporary injunction, finding no threat of irreparable injury primarily because BNSF’s continuing lease payments more than covered the Baker Group’s monthly debt service. Thereafter, BNSF tried to force Article 14 damage issues into the Kansas case. However, ignoring BNSF’s threat to invoke claim preclusion in any later action, the Baker Group refused to amend its Kansas petition to add Article 14 claims. Ultimately, at the Kansas trial, the court excluded evidence relating to return of the railcars because those issues belonged in this Missouri lawsuit, which by that time had been commenced.
The above-quoted Restatement commentary does not address this situation --
Free access — add to your briefcase to read the full text and ask questions with AI
Baker Group v. Burlington Northern (Baker Group v. Burlington Northern) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.