Baird v. United States

76 Ct. Cl. 599, 1933 U.S. Ct. Cl. LEXIS 357, 1933 WL 1901
CourtUnited States Court of Claims
DecidedJanuary 9, 1933
DocketK-146
StatusPublished
Cited by4 cases

This text of 76 Ct. Cl. 599 (Baird v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Baird v. United States, 76 Ct. Cl. 599, 1933 U.S. Ct. Cl. LEXIS 357, 1933 WL 1901 (cc 1933).

Opinion

GeeeN, Judge,

delivered the opinion of the court:

The plaintiff is trustee in bankruptcy for the Bickel Dredging Corporation and brings this suit to recover $62,166.12 alleged to have been due the Bickel Corporation for dredging done under a contract made with the defendant. The defendant denies any liability.

[605]*605It appears without controversy that a written contract was entered into between the Bickel Corporation and the defendant about September 14, 1928, under which the Bickel Corporation, hereinafter referred to as the contractor, agreed to. do certain dredging in the vicinity of Norfolk harbor at an agreed price per cubic yard and in accordance with certain provisions and specifications to which reference will hereinafter be made. The contractor began the work about the date last mentioned and was paid for the work which it did in the months of September, October, and November, in accordance with the contract, less retained percentages, but when the contractor presented its claim for work done in December, the engineer officer who had general charge and supervision of the work on behalf of the Government having been informed in substance that the contractor had been dumping material excavated at a place other than that fixed by the contract, payment was made to the contractor only after a large deduction had been made. The contractor, however, continued the work, but when the time for payment again arrived no payment was made for the additional work done and the contractor was notified by the engineer officer that payment was subject to further deduction for the removal of material improperly dumped, which deduction would be made at the time of final settlement. The contractor continued the work until March 2, 1929, and then stopped. It had then dredged a total of 870,251 cubic yards of material, which, at the contract rate, amounted to $150,553.43. It has been paid for dredging a total of $88,387.31, leaving unpaid the amount for which it now brings suit. About April 29, 1929, the engineer officer notified the contractor that its right to proceed with the work under the contract was terminated. In the latter part of June a bonding company, which had become surety for the performance of the contract by the contractor, was authorized to complete the work and did proceed with it, but a considerable portion of it finally had to be done by the defendant. After the work was completed, the defendant, through the Comptroller General’s office, made a settlement with the bonding company, in which it deducted $51,694.55, being the cost [606]*606of certain redredging of material which was claimed to have been wrongfully dumped by the contractor. A further deduction of $2,350 was made as liquidated damages for delay in completing the contract. Credit was given for the work which the bonding company had done, and it was paid $38,340.27.

The contract provided in substance that the material excavated must be transported and deposited within the limits of certain established dumping grounds, that material deposited elsewhere would not be paid for, and the contractor might be required to redredge such material and deposit it where directed. The contract further provided that if, in the opinion of the contracting officer, any material was dumped so as to be dangerous to or obstruct navigation, the contractor should give notice thereof and remove the same with the utmost dispatch, and in case it neglected or delayed so to do, the material could be removed by the contracting officer and the cost of such removal be deducted from any money due or to become due the contractor. (See latter part of finding IV for exact language used in the contract.)

There was also a provision in the contract for liquidated damages in case of delay. (See finding IV.)

It will be observed on consideration of the case that the issue between the parties is primarily one of fact, the question being whether any dumping was done contrary to the provisions of the contract, and if so to what extent and quantity. It is contended on behalf of the defendant that the contractor did such dumping and to such an extent that considering the payments made there is now nothing due on the contract. On behalf of the plaintiff it is contended that there was no such dumping and that in any event it was very much less than the quantity for which deductions were made by the defendant.

It would serve no useful purpose to undertake to review at length the testimony given in the case. The testimony as to dumping is conflicting and the evidence as to the quantity thereof indefinite, where it would seem it might well have been made reasonably exact and it would seem that the wrongful dumping could not have been done without the [607]*607connivance of the Government inspector who accompanied the scows. But from the whole of the evidence we are entirely satisfied that there was wrongful dumping, that it was intentional, and that it obstructed navigation; but as to the amount thereof, beyond a certain definite figure which will be specified further on, we find no testimony from which even an approximation may be made. Some facts appear from the evidence as to which there is little or no controversy. The material excavated was to be moved about twenty miles to the established dumping grounds to which reference has been made above. On the way to the dumping grounds, about fifteen miles therefrom, was the channel of the Elizabeth River which had heretofore been dredged and its depth and the amount of fill from natural causes observed. After being informed that the contractor was making short dumping, defendant’s engineer in charge caused a survey to be made of this channel, which, in connection with the other facts established by the evidence, showed that 158,352 cubic yards of material had recently been dumped in the channel of the Elizabeth River opposite the site of the Army Base within a strip thereof approximately 3,370 feet long. Another survey was later made which showed that more material had been dumped at the same place but beyond this nothing is shown by the evidence as to the results of the second survey. The testimony also shows that the contractor did other short dumping but the amount thereof is not anywhere shown by the evidence. In this connection it should be said that the fact that the defendant introduced no evidence of what the second survey showed with reference to the amount of dumping in the Elizabeth River channel tends to show that its claim with reference thereto is not well founded.

The plaintiff, however, contends that even if there was short dumping the contractor could not be charged with the cost of removal unless it had been notified to remove the material by defendant and that no such notice was ever given. We do not so construe the contract. As we view its provisions, if the contractor deposited any material where it would obstruct navigation, it was required forthwith to remove such material and in event of its failure so to do the [608]*608defendant could remove it at the contractor’s expense. Plaintiff also insists, and as we think rightly, that the contractor could not be properly charged with the entire cost of the dredging done by defendant in the channel of the Elizabeth River. Attention is called to the fact that the Government removed 600,000 yards of material from this channel, and that the total amount dredged, up to the time when it is practically conceded that the wrongful dumping was stopped, was only about 572,871 cubic yards.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kellogg Brown & Root Services, Inc. v. United States
99 Fed. Cl. 488 (Federal Claims, 2011)
Veridyne Corp. v. United States
83 Fed. Cl. 575 (Federal Claims, 2008)
Jerman v. United States
96 Ct. Cl. 540 (Court of Claims, 1942)

Cite This Page — Counsel Stack

Bluebook (online)
76 Ct. Cl. 599, 1933 U.S. Ct. Cl. LEXIS 357, 1933 WL 1901, Counsel Stack Legal Research, https://law.counselstack.com/opinion/baird-v-united-states-cc-1933.