Bachli v. Holt

200 A.2d 263, 124 Vt. 159, 1964 Vt. LEXIS 75
CourtSupreme Court of Vermont
DecidedApril 7, 1964
StatusPublished
Cited by11 cases

This text of 200 A.2d 263 (Bachli v. Holt) is published on Counsel Stack Legal Research, covering Supreme Court of Vermont primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Bachli v. Holt, 200 A.2d 263, 124 Vt. 159, 1964 Vt. LEXIS 75 (Vt. 1964).

Opinion

Holden, C. J.

The plaintiff is a plumbing and heating engineer and contractor. He instituted this action against the general contractor to recover the final payment on the heating and plumbing contract which he performed during the defendant’s construction of a restaurant for Marcelle MacDuff at Warren, Vermont. The defendant denied liability on the contention that he had no contractual agreement with the plaintiff and whatever liability existed for the plaintiff’s performance of the plumbing and heating contract attached to the owner, Miss MacDuff.

[160]*160Plans and specifications for the construction had beep prepared and submitted by the owner’s architect to several prospective bidders, including the defendant. The defendant was a friend of the owner and her family. However, due to the pressure of other work he returned the plans without bidding. As sometimes happens in such projects, the bids offered were higher than the owner and her family anticipated. At this stage, the defendant was requested to confer with the owner and the architect. The defendant was asked to figure the job with the understanding that if his estimate was equal or higher than the lowest bid he would be compensated for his effort in making the computation. The figure concluded by the defendant was about $10,000 less than that submitted by the previous lowest bidder. The owner then requested the defendant to construct the building on a cost plus basis with a warranty that the total cost would not exceed the lowest bid previously received. To this the defendant agreed.

During the course of these negotiations the defendant called the plaintiff. The defendant testified that he “asked the plaintiff for a price.” Plaintiff’s counsel inquired, “Q. To you? A. Yes.”

With this, the defendant furnished the plaintiff with drawings and specifications for the plumbing and heating details. There were further conversations and a meeting between the plaintiff and the architect. After these negotiations, the plaintiff submitted his bid to the defendant in the following letter, copies of which were offered by both parties and received as exhibits:

August 23, 1960
Mr. Earl Holt,
S. Main Street,
Barre, Vermont.
Re: M arc elle’s Restaurant
Marcel Beaudin — Architect—Project #775
Dear Earl — ■
This letter is to confirm our conversations with regards to the above subject work—
Elec., Heating, Plumbing & Ventilating zvork as originally quoted ............................$ 12,169.00
Electrical Work................................................ —2,276.00
Heat., Plumb. & Vent, work only ...$ 9,893.00
(all electrical work removed— [161]*161electrician to provide all wiring for heating & vent. & oil burner controls)
Additional for Fresh Air Duct, louvre, screen, damper and rod and teepee for fire place.................. 138.00
$ 10,031.00
Credit of $300.00 for oil tank to be supplied by others ................................. —300.00
$ 9,731.00
Above quote based on using following different materials—
1) Std. weight cast iron soil pipe — not extra heavy.
2) Use of Detroit, American or Pittsburgh valves — not Jenkins.
3) Use of Wade 15 gpm Grease trap #W5115 instead of Josam type specified.
4) 25 ft. maximum offset — (horizontal) of 2" oil tank vent.
5) 100 ft. maximum run (one line) of oil tank supply and return tubing.
6) Vent thru to roof to be provided at Bar sink and at dish washer.
7) Septic Tank to be provided but no installation or connections included (i.e. as specified).
Payments to be made twice monthly upon presentation of requisitions for above labor and materials at the job site. Payment due within ten days of presentation of requisition. No retainage to be withheld. Final payment upon completion due within thirty days.
Yours truly,
William K. Bachli.
WKB: mb

The defendant testified that he had a “so-called agreement” with the plaintiff. He did not consider that the letter constituted an agreement until such time as it was approved by the owner or her architect. The architect did approve and the plaintiff commenced work on the [162]*162project. At that time the plaintiff had no dealings with the owner and he did not meet her until the job had been underway for several weeks.

As the plumbing and heating progressed, the plaintiff submitted requisitions for payment to the defendant. Upon approval of the several requisitions by the architect, the plaintiff was paid by the defendant’s personal checks in the amount of $7,287.00, from funds provided the defendant by the owner. Upon completion of the plumbing and heating, the plaintiff’s request for final payment was refused by the defendant for the reason that he had received no funds from the owner for this purpose.

The defendant presented evidence in opposition to the plaintiff’s contention that his undertaking was with the general contractor alone. This included a letter written by the defendant to the owner on August 23, 1960 stating that the architect had engaged the plumbing, heating and electrical contractors. It stated that the defendant waived his usual five percent surcharge on the payments to the subcontractors for the reason that supervision of their work was to be done by the architect. There was no showing that the contents of this letter were communicated to the plaintiff. There was evidence that the plaintiff had endeavored to collect final payment from the owner before proceeding against the defendant. And the defendant never specifically agreed to pay the plaintiff in the event of the owner’s default. There was also evidence that the defendant had nothing to do with the problems that developed in connection with the plaintiff’s performance of his contract and that these were settled by the architect.

Upon this state of the evidence, the trial court submitted but one issue to the jury: “Was there an understanding or agreement- mutually entered into between these parties whereby it was intended by both that the plaintiff would perform the labor and furnish the material as revealed by the evidence and for which the defendant was to pay him $9,731?” The jury returned a verdict for the plaintiff. The defendant moved for judgment notwithstanding the verdict and requested the court to set aside the verdict as against the weight of the evidence. From the court’s order denying these motions the defendant has appealed.

By moving for judgment notwithstanding the verdict, the defendant raised substantially the same questions of law which attend a motion for a directed verdict. It is to be treated in the same way. [163]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Del Monaco v. Green
384 F. App'x 19 (Second Circuit, 2010)
Bixler v. Bullard
769 A.2d 690 (Supreme Court of Vermont, 2001)
Hospitality Inns, Inc. v. South Burlington R.I., Inc.
571 A.2d 40 (Supreme Court of Vermont, 1989)
Appropriate Technology Corp. v. Palma
508 A.2d 724 (Supreme Court of Vermont, 1986)
Okemo Mountain, Inc. v. Okemo Trailside Condominiums, Inc.
431 A.2d 457 (Supreme Court of Vermont, 1981)
Perkins v. Factory Point National Bank
409 A.2d 578 (Supreme Court of Vermont, 1979)
Trimount Bituminous Products Co. v. Chittenden Trust Co.
379 A.2d 1266 (Supreme Court of New Hampshire, 1977)
AG ANDERSON CO. INC. v. TC Industries, Inc.
380 A.2d 90 (Supreme Court of Vermont, 1977)
Williams v. Carter
285 A.2d 735 (Supreme Court of Vermont, 1971)
Mt. Mansfield Television, Inc. v. Farrell
223 A.2d 477 (Supreme Court of Vermont, 1966)

Cite This Page — Counsel Stack

Bluebook (online)
200 A.2d 263, 124 Vt. 159, 1964 Vt. LEXIS 75, Counsel Stack Legal Research, https://law.counselstack.com/opinion/bachli-v-holt-vt-1964.