Babler Bros., Inc. v. Hebener

517 P.2d 653, 267 Or. 414, 1973 Ore. LEXIS 503
CourtOregon Supreme Court
DecidedDecember 31, 1973
StatusPublished
Cited by17 cases

This text of 517 P.2d 653 (Babler Bros., Inc. v. Hebener) is published on Counsel Stack Legal Research, covering Oregon Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Babler Bros., Inc. v. Hebener, 517 P.2d 653, 267 Or. 414, 1973 Ore. LEXIS 503 (Or. 1973).

Opinion

HOWELL, J.

Plaintiff filed this action in replevin to recover possession of certain gravel located on premises leased by defendants. The defendants filed a counterclaim for damages for breach of a contract between defendants *416 and plaintiff. The action was tried before the court without a jury. Findings of fact, conclusions of law and a judgment were entered in favor of plaintiff on its complaint and against defendants on their counterclaim for damages. Defendants appeal.

The plaintiff, Babler Bros., is engaged in road and highway construction. The defendants are the lessees of a rock quarry located near the city of Bums. The plaintiff secured a contract from the Oregon State Highway Department to construct a section of highway near Burns. In December, 1970, the plaintiff and defendants entered into a contract whereby plaintiff agreed to purchase rock from defendants’ quarry. The plaintiff agreed to remove the rock, crush and stockpile it on defendants’ premises, and pay defendants 15 cents per cubic yard for the crushed rock.

The contract provided in pertinent part:

“AGREEMENT '
“KNOW ALL MEN BY THESE PRESENTS, that Robert M. Hebener, and D. LaVerne Hebener, * =:s * hereinafter referred to as first party, and BABLER BROS., INC., an Oregon Corporation, * * * hereinafter referred to as the second party, and
“WHEREAS, first party has a gravel lease with Clyde Co-wing and Ruth Cowing dated the 23rd day of January, 1958, * * * and
“WHEREAS, second party does commercial paving and related work and has need for the type of rock found in said quarry situated on the leased premises for Oregon State Highway Job #92, in the' amount of 80,000 tons', now, therefore,
Ci* # & &
“FIRST PARTY AGREES:
“1. Grants to the second party the nonexclusive *417 right to set up a rock crushing plant, pugmill and A.C. Hot Plant on said leased premises and to crush and stockpile rock on said leased premises, for the period December 1, 1970 to and including July 31, 1971, or until the completion of Oregon State Highway Job #92 * * *.
ÍÍ* * * & #
“SECOND PARTY AGREES:
ÍÍ* * * #
“23. At the termination by lapse of time specified hereinabove, on cancellation by default of this agreement, any and all rock materials of any nature or kind, being shot quarry rock, crushed rock, or rejected materials, they all shall immediately become the property of the first party without any written instrument to transfer the title thereto, and in case of default, and [sic] advance payment forfeited.
* * * $
“BOTH PARTIES AGREE:
* # *
“2. In case of default of any of the provisions of this agreement hereinabove set forth by second party or their sub-contractors, Robert Hebener Avill immediately upon becoming aware of such default notify the foreman in charge at the time personally of the default, and all operations will cease immediately. Default will be explained in a registered letter and mailed to Second Party, BABLER BROS., INC., * * *. In case default is not cured within ten calendar days of date on said registered letter, this agreement will be terminated forthwith, and paragraph 23 will be in immediate effect.
* * # # ??

The plaintiff’s construction job on the Bums Highway was completed in late August, 1971, and at this time approximately 17,000 yards of crushed rock remained at the quarry. Because of various alleged breaches of *418 the contract, the defendants sent plaintiff several notices of cancellation of the contract and refused to allow plaintiff to remove the remaining rock.

The defendants alleged the above contract as an affirmative defense to plaintiff’s action in replevin and further counterclaimed, alleging that the plaintiff had breached that contract in various respects.

The trial judge, in an oral opinion given at the close of the trial, found that plaintiff had title to the rock, that the evidence established only one breach— selling rock in violation of the contract — but that the defendants had failed to prove actual damages as to that breach. In so holding, the court also found that paragraph 23 operated not as a liquidated damage clause but as a penalty clause, and therefore it could not be used to measure damage from the proven breach.

We agree with the finding of the trial court that plaintiff had title to the rock.

The portion of paragraph 23 which poses the issue of whether the clause calls for a penalty or liquidated damages is: “On cancellation by default of this agreement” the remaining rock then becomes the property of the defendant.

*419 The determination of whether a contractual provision constitutes a penalty ¡or liquidated damages is a legal question for the court. Medak v. Hekimian, 241 Or 38, 44, 404 P2d 203 (1965). In Medak and in Harty v. Bye, 258 Or 398, 483 P2d 458 (1971), we adopted the test as set forth in 1 Restatement 552, Contracts § 339. The material part of the section states:

“(1) An agreement, made in advance of breach, fixing the damages therefor, is not enforceable as a contract and does not affect the damages recoverable for the breach, unless
“(a) the amount so fixed is a reasonable-forecast of just compensation for the harm that is caused by the breach, and
“(b) the harm that is caused by the breach is one that is incapable or very difficult of accurate estimation.
& * * J5

Applying the test of the Restatement, the facts of this case do not disclose that forfeiture of the gravel was a reasonable forecast of compensation for a breach and that any harm caused by a breach was difficult to estimate.

As to the first requirement, it is apparent that paragraph 23 does not fix an amount of damages which is a reasonable forecast of just compensation for harm caused by a breach. That paragraph establishes that the amount of monetary damage, was to be measured by the quantity of gravel existing at the'time a default .Occurs. The'amount thus available as compensation . for a breach would depend entirely on the amount of gravel.that happened to be on hand at the time and would be without.any reasonable relationship'to' the ■ amount, of damages from a. breach.

*420 Additionally, there is no showing that any harm from a breach would be difficult to ascertain.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jessen v. Jessen
810 P.2d 987 (Wyoming Supreme Court, 1991)
Willamette Quarries, Inc. v. Wodtli
781 P.2d 1196 (Oregon Supreme Court, 1989)
Illingworth v. Bushong
688 P.2d 379 (Oregon Supreme Court, 1984)
Marcam Mortgage Corp. v. Black
686 P.2d 575 (Wyoming Supreme Court, 1984)
Bennett v. Hebener
643 P.2d 393 (Court of Appeals of Oregon, 1982)
Bennett v. Les Schwab Tire Centers of Oregon, Inc.
618 P.2d 455 (Court of Appeals of Oregon, 1980)
Jackson County v. Compton
609 P.2d 1293 (Oregon Supreme Court, 1980)
Dean Vincent, Inc. v. McDonough
574 P.2d 1096 (Oregon Supreme Court, 1978)
Layton Manufacturing Co. v. Dulien Steel, Inc.
560 P.2d 1058 (Oregon Supreme Court, 1977)
Chaffin v. Ramsey
555 P.2d 459 (Oregon Supreme Court, 1976)
Shaw v. Northwest Truck Repair, Inc.
541 P.2d 1277 (Oregon Supreme Court, 1975)

Cite This Page — Counsel Stack

Bluebook (online)
517 P.2d 653, 267 Or. 414, 1973 Ore. LEXIS 503, Counsel Stack Legal Research, https://law.counselstack.com/opinion/babler-bros-inc-v-hebener-or-1973.