B-W Construction Co. v. United States

104 Ct. Cl. 608, 1945 U.S. Ct. Cl. LEXIS 102
CourtUnited States Court of Claims
DecidedNovember 5, 1945
DocketNo. 43915
StatusPublished
Cited by1 cases

This text of 104 Ct. Cl. 608 (B-W Construction Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
B-W Construction Co. v. United States, 104 Ct. Cl. 608, 1945 U.S. Ct. Cl. LEXIS 102 (cc 1945).

Opinion

Jones, Judge,

delivered the opinion of the court.

This suit arises out of the construction of a Post Office building in Washington, D. C. By contract dated April 23, 1932, the plaintiff, a corporation with its principal office in Chicago, Illinois, undertook to build an extension to and greatly enlarge the Post Office building near the Union Station. The contract price was $2,999,000.

The old building had wings, three stories high, on the east and the west sides. The wings were connected by a low center covered by a corrugated roofing. On the north side of the building was a loading platform with metal covering. The old building, which was constructed in 1912, had a basement. The north side of the block was vacant except for a [640]*640garage which was to be tom down. Here the new building was to be constructed, a three-story affair with basement and subbasement. It was to be connected with and made a part of the old building, which was to be entirely remodeled.

The notice to proceed was received by plaintiff on June 22, 1932. The completion date was to be June 12,1934, a period of 720 days. During the progress of the work plaintiff was granted extensions of time totaling 362 days, of which 267' days were because of change orders, and 95 days because of strikes, bad weather, and defaulting subcontractors. The work was completed within the contract time as thus extended.

The old building had become badly congested due to the growth of the Post Office activities at Washington.

The specifications clearly provided that the work should be done in such a way as not to interrupt the Government’s business, and stipulated that there should be no unreasonable delay or interference in the operations of the Post Office. The contractor was to provide satisfactory temporary facilities to permit such business to be continued during the operations under the contract.

At a conference representatives of the Post Office told the plaintiff it would not be possible to surrender many spaces in the old building and suggested that plaintiff go forward with the construction of the new building so that some of the postal employees could be moved into the new building, which they claimed would permit the remodeling of the old building without interrupting the business of the Post Office. However, plaintiff felt that the only practicable way was to construct the new building and remodel the old at the same time, due to the fact that they were to be joined together and finally finished as one single large building with uniform construction, design, and appearance. It therefore submitted to defendant a schedule showing numerous spaces in the old building that it desired defendant to surrender, the times at which it desired such surrender and the length of time the spaces would be needed.

It was impossible for defendant to surrender a good many of the spaces set out in the schedules without interrupting the business of the post office. In August 1932 plaintiff, at [641]*641the suggestion of defendant, constructed as a temporary facility a mezzanine floor, containing 3,200 square feet, in the first floor of the old building. This mezzanine was sufficient to take care of the post office employees working at and near to the north wall in the old building, but was not large enough to take care of the post office employees working in many other spaces in the old building designated in the schedules and possession of which was desired by the plaintiff. The mezzanine was used by the post office employees to its full capacity for two or three months, but by the end of the year its use had dwindled to half capacity, and at the end of 18 months only 20 persons out of a capacity of about 75 were using it. It was not practicable to use the mezzanine for some phases of the work. It could not be used by any unit or postal employees who had to deal with the public. It was not practicable to use it for distribution of the mail' It did enable the defendant to surrender a few of the spaces which plaintiff desired, and defendant surrendered them.

By far the greater part of plaintiff’s claim is for damages alleged to have resulted from the failure of the defendant to surrender spaces in the old building so that plaintiff could proceed promptly and efficiently with the performance of the work required by the contract.

However, in the light of the inability of the defendant to surrender many of the spaces in the old building which plaintiff desired without seriously interrupting the business of the Post Office, the evidence to support many of these claims is not satisfactory.

The evidence shows that the Post Office at Washington was one of the busiest and most congested of the post offices in the country, a fact that plaintiff knew at the time it entered into the contract.

Plaintiff claims total damages in the sum of $441,812.60 as a result of alleged long and unreasonable delays upon the part of the defendant in acting upon change proposals, interpreting vague plahs and specifications and correcting errors in the drawings, plans and specifications. It is necessary to deny most of these claims since plaintiff did not pursue the remedy clearly set out in the contract.

[642]*642A number of errors were found in the specifications which required changes and modifications. In some instances the defendant was inexcusably slow in properly interpreting and in acting upon the necessary change proposals. These are set out in the findings and it will not be necessary to repeat them in detail.

On October 15,1932, plaintiff called defendant’s attention to errors in contract drawing P-450 relating to the subsoil drainage system below the subbasement of the new building. The system as specified would have been improperly pitched so that the water would not have been carried off. Defendant did not reply to this letter, and on December Y, 1932, plaintiff submitted a change proposal in the amount of $2,630.54. On January 20,1933, defendant requested plaintiff to submit a modified proposal with some additional changes. This plaintiff did, but the modified proposal was rejected as excessive. On March 3, 1933, plaintiff submitted another proposal, somewhat modified, which was accepted by the defendant on April 3, 1933. Because of these unreasonable delays plaintiff paid out $254.65 in actual storage charges, which it is entitled to recover. Arnold M. Diamond v. United States, 98 C. Cls., 543, 551.

One of the first things to be done in the performance of the contract was to underpin the two 60-foot sections of the north wall of the old building in the wings so that the footings for the columns of the new building could be put in at the lower depth required by the subbasement of the new building. The contract contemplated that this underpinning should be done from the inside of the basement of the old building. To do this it was necessary to tear down two 60-foot sections of the north wall and open up the columns thereof so as to connect the weight-carrying steel therein with the steel framework of the new building.

The Government’s draftsmen of the specifications overlooked the fact that the electric elevator near column 32 could not do the work of the hydraulic elevator in the north wall near column 35, and when plaintiff asked for the surrender of the hydraulic elevator and machinery thereof near the north wall and column 35 so that it could underpin the north wall in the east wing near First Street, the defendant refused to [643]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
104 Ct. Cl. 608, 1945 U.S. Ct. Cl. LEXIS 102, Counsel Stack Legal Research, https://law.counselstack.com/opinion/b-w-construction-co-v-united-states-cc-1945.