B. L. Metcalf General Contractor, Inc. v. Earl Erne, Inc.

212 Cal. App. 2d 689, 28 Cal. Rptr. 382, 1963 Cal. App. LEXIS 2898
CourtCalifornia Court of Appeal
DecidedFebruary 5, 1963
DocketCiv. 7026
StatusPublished
Cited by18 cases

This text of 212 Cal. App. 2d 689 (B. L. Metcalf General Contractor, Inc. v. Earl Erne, Inc.) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
B. L. Metcalf General Contractor, Inc. v. Earl Erne, Inc., 212 Cal. App. 2d 689, 28 Cal. Rptr. 382, 1963 Cal. App. LEXIS 2898 (Cal. Ct. App. 1963).

Opinion

MONROE, J. pro tem. *

InMarch of 1959 the petitioner, as a general contractor, entered into a contract for the construction of the Pacoima Memorial Lutheran Hospital and thereafter, under date of March 23, 1959, entered into a subcontract with defendant whereby the latter undertook to furnish labor and materials for the plumbing, heating, ventilating, and fire protection system for the agreed price of $374,-970. This agreement contained the following provisions:

I ‘ Seventh: If, in the opinion of the Contractor or the Owner’s representative or the Architect, the Subcontractor fails to perform his work in accordance with this agreement, and should such failure continue for twenty-four consecutive hours after service of a written notice to the Subcontractor, specifying the particulars of such failure, served personally or mailed to the Subcontractor, then such failure and continuance thereof shall constitute a breach of contract by the Subcontractor, and such breach shall entitle the Contractor to terminate the contract and complete the work himself, or cause the work to be completed by others, and the Subcontractor agrees immediately to repay all costs and damages sustained by the Contractor on account of such failure; and any and all material and equipment of the Subcontractor on the site or in the Subcontractor’s plant, may at the option of the Contractor be used or rejected.

II Eighth: If at any time any controversy should arise between the Contractor and the Subcontractor regarding anything pertaining to this agreement and which the parties hereto do not adjust and determine, or which the Owner’s representative or Architect cannot decide to the satisfaction of both parties, then the written orders of the Contractors shall be followed and said controversy shall be decided by arbitration upon completion of the work.”

The defendant proceeded with performance under the contract. Petitioner claimed that defendant had breached the contract by faulty performance in a number of particulars and after having given notices thereof, sent to the defendant a telegram dated July 19, 1960, stating as follows:

*692 “Due to your continued failure after two written notices to supply 1 sufficient material and workmen 2 comply with urgent schedules 3 laxity in cooperation and coordination we ar- forced to terminate your contract and for Aticl 7 on Paeoima Hospital datd March 23rd 1959-”

Thereafter, on December 14, 1960, petitioner made written demand on defendant to submit their differences concerning the contract to arbitration, which demand was refused. Thereupon, this proceeding was started for the purpose of securing an order for statutory arbitration.

The defendant filed an answer in opposition to the petition in which he claimed in substance that the subcontract was prepared by petitioner and should be construed against petitioner, and further claimed that the agreement for arbitration applied only to a situation where performance of the subcontract was completed and did not apply where the contract was terminated.

The trial court held that the answer raised no issues of fact with reference to the right to arbitration, and appointed Mr. A. K. Phelps, an attorney at law, as arbitrator. After a lengthy hearing, the arbitrator made an award in favor of petitioner in the amount of $70,007.60, for which amount judgment was rendered. The defendant appeals.

Appellant and respondent are in accord that the orders and judgment of the trial court constitute a determination of the construction to be placed upon the terms of the contract as a matter of law. The defendant and appellant contends, in substance, that a correct interpretation and construction of the contract is that the provisions for arbitration apply only to disputes which may arise during the course of the work but the performance of the contract is nevertheless completed, leaving the disputes to be determined by arbitration after such completion. Appellant further contends that the determination of the subcontract by written notice destroyed and terminated the contractual relation and that therefore no provision for arbitration remained. Respondent contends that the correct interpretation is that any dispute or claim arising out of the performance of the contract was properly subject to arbitration; that termination for breach by notice given left undetermined the amount of damages to be awarded; that such claim for damages was a proper one for arbitration; and that the award should be upheld. This, evidently, was the construction by the trial court.

*693 It is well established that where the interpretation and construction of a contract is based upon the contract alone and not upon extrinsic evidence, the proper interpretation upon appeal is a matter of law. In such a situation the appellate court has no alternative except to consider and interpret the contract. (Moffatt v. Tight, 44 Cal.App.2d 643 [112 P.2d 910]; Estate of Helfman, 193 Cal.App.2d 652 [14 Cal.Rptr. 482]; Apra v. Aureguy, 55 Cal.2d 827 [13 Cal.Rptr. 177, 361 P.2d 897].)

Therefore, the rule that the court will prefer the construction placed upon the document by the trial court, if reasonable, as set forth in O'Sare v. Peacock Dairies, Inc., 26 Cal. App.2d 345 [79 P.2d 433], and Estate of Sandersfeld, 187 Cal.App.2d 14 [9 Cal.Rptr. 447], does not apply. In this ease, no attempt was made by either party to present extrinsic evidence reflecting upon the meaning of the contract.

It is true that if a contract which contains provision for arbitration has been entirely rescinded or abandoned the provision for arbitration ceases to exist. (Silva v. Mercier, 33 Cal.2d 704, 709 [204 P.2d 609].)

However, each contract must be construed in order to effectuate the intent of the parties, if that intent can be ascertained from an examination of the document. It is established that where a contracting party in the course of performance has committed a breach or breaches, the other party has the right and option to determine what remedy he will pursue. In such a situation he has the option to terminate the contract for cause and such right to terminate may be provided by the terms of the contract. (12 Cal.Jur.2d 406.) The giving of notice to terminate the contract for breach does not prevent the party giving such notice from presenting his cause of action for damages accruing up to the time of the breach. (12 Cal.Jur.2d 492.) In Sobelman v. Maier, 203 Cal. 1 [262 P. 1087], the court commented on page 8 that the parties had given notice of termination and had thus elected to hold the defendants responsible for damages up to the date of the notice. The court stated, “In this action plaintiffs are standing upon the contract and could at least hold appellants liable for all damages accruing prior to the service of notice.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Varga v. Twitch Interactive CA1/1
California Court of Appeal, 2024
Perez v. Graham CA1/1
California Court of Appeal, 2024
Multani v. Knight
California Court of Appeal, 2018
Multani v. Knight
233 Cal. Rptr. 3d 537 (California Court of Appeals, 5th District, 2018)
DE GREZIA v. Superior Court
131 Cal. Rptr. 2d 443 (California Court of Appeal, 2003)
International Billing Services, Inc. v. Emigh
101 Cal. Rptr. 2d 532 (California Court of Appeal, 2000)
Blatt v. Farley
226 Cal. App. 3d 621 (California Court of Appeal, 1990)
Gutzi Associates v. Switzer
215 Cal. App. 3d 1636 (California Court of Appeal, 1989)
Conejo Valley Unified School District v. William Blurock & Partners, Inc.
111 Cal. App. 3d 983 (California Court of Appeal, 1980)
Moss Development Co. v. Geary
41 Cal. App. 3d 1 (California Court of Appeal, 1974)
Sauter v. Superior Court
2 Cal. App. 3d 25 (California Court of Appeal, 1969)
Whitney Investment Co. v. Westview Development Co.
273 Cal. App. 2d 594 (California Court of Appeal, 1969)
Rabinowitch v. Cal. Western Gas Co.
257 Cal. App. 2d 150 (California Court of Appeal, 1967)
Morris v. Zuckerman
257 Cal. App. 2d 91 (California Court of Appeal, 1967)
A. Teichert & Son, Inc. v. State of Cal.
238 Cal. App. 2d 736 (California Court of Appeal, 1965)
Warington Lumber Co. v. Fullerton Mortgage & Escrow Co.
222 Cal. App. 2d 706 (California Court of Appeal, 1963)
Bertero v. Superior Court of Los Angeles County
216 Cal. App. 2d 213 (California Court of Appeal, 1963)

Cite This Page — Counsel Stack

Bluebook (online)
212 Cal. App. 2d 689, 28 Cal. Rptr. 382, 1963 Cal. App. LEXIS 2898, Counsel Stack Legal Research, https://law.counselstack.com/opinion/b-l-metcalf-general-contractor-inc-v-earl-erne-inc-calctapp-1963.