B & H Supply Co. v. United States

35 Cont. Cas. Fed. 75,698, 17 Cl. Ct. 544, 1989 U.S. Claims LEXIS 141, 1989 WL 83134
CourtUnited States Court of Claims
DecidedJuly 25, 1989
DocketNo. 168-86C
StatusPublished

This text of 35 Cont. Cas. Fed. 75,698 (B & H Supply Co. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
B & H Supply Co. v. United States, 35 Cont. Cas. Fed. 75,698, 17 Cl. Ct. 544, 1989 U.S. Claims LEXIS 141, 1989 WL 83134 (cc 1989).

Opinion

OPINION

ANDEWELT, Judge.

This government contract action involves a contract for maintenance and repair work at 813 Naval housing units at the Naval Air Station in Corpus Christi, Texas. On January 11, 1985, the Department of the Navy (the Navy) issued a Change Order which deleted 74 housing units from the contract and ordered a corresponding decrease in the contract price. In this action, plaintiff, B & H Supply Company (B & H), contests the Navy’s authority to make any such deduction in the contract price. This action is presently before the court on cross-motions for summary judgment. For [545]*545the reasons explained herein, the parties’ respective motions are each denied.

Facts 1

The contract in issue2 involves the provision of maintenance services at six groups of family housing units at the Corpus Christi Naval Air Station. The six groups, identified in Appendix A of the contract, encompass a total of 813 housing units, 28 trailer sites, and a community center. Performance of the contract commenced on February 1, 1984, and the contract expired on January 31, 1987.3

The contract is separated into two bid items. The competing bidders submitted bids on each bid item and the winner was determined based upon the aggregate of the two bids. Bid Item No. 1 covers a variety of specified maintenance tasks. The competing bidders each proposed a single fixed fee for performance of all of the listed maintenance tasks at all of the Appendix A properties.

Bid Item No. 2 covers different maintenance tasks (referred to as “Indefinite Quantity Work Items”) for which the contractor would receive payment on a per-call basis. The competing bidders established their own respective prices for each task listed in Bid Item No. 2 (e.g., $17 for each pilot light lit and $55 for each gas range disconnected, moved, and reconnected). The total bid for Bid Item No. 2 was calculated by multiplying the price for each task by the number of times the government estimated that particular task would be performed during the course of the contract, and then by adding together the products for each of the tasks. The government’s frequency-of-call estimates used in calculating the bid were not, however, binding on the government in that the winning bidder was not guaranteed any minimum number of calls for any task listed in Bid Item No. 2.

On May 21, 1984, less than four months after performance commenced under the contract, defendant notified plaintiff that after June 1, 1984, it would no longer be necessary for plaintiff to perform maintenance services at one of the six housing groups listed in Appendix A of the contract — the 74-unit Southgate Housing. The Navy decided to inactivate Southgate Housing because age had deteriorated those units beyond economic repair. Defendant requested that plaintiff supply a detailed cost estimate to cover the deletion of such services from the scope of the contract for the period from June 1, 1984, through January 31, 1985.

On December 19, 1984, plaintiff responded that defendant’s plan to delete South-gate Housing and to reduce the contract price was unacceptable because such a deletion would not produce overall cost savings for plaintiff. In addition, plaintiff asserted that its original bid on Bid Item No. 2 was based upon the expectation that it would perform maintenance work on all 813 units and that the withdrawal of South-gate Housing was inconsistent with this expectation.

On December 20, 1984, the Navy informed plaintiff that because plaintiff had not supplied the requested cost estimates, the Navy had made its own calculations as to the appropriate decrease in the Bid Item No. 1 contract price to account for the withdrawal of Southgate Housing. The Navy calculated this deduction from information contained in a “Schedule of Deductions” (the Schedule) thát plaintiff had submitted to the Navy shortly after entry into the contract. Plaintiff was required under the contract to provide the Schedule for the Navy’s use in calculating payment deductions in the event of nonperformance or unsatisfactory performance by plaintiff. The form for the Schedule, as provided by the Navy, listed various Bid Item No. 1 tasks and estimated the number of times each such task would be performed per year. For each work task listed, plaintiff was required to fill in a per-unit price and a [546]*54612-month total item price. The 12-month price was calculated by multiplying the unit price for a particular task by the government’s estimate of the number of times that task would be performed during a year. The contract required that the Schedule prepared by the contractor be balanced, i.e., that the sum of the 12-month total item prices for the various listed tasks equal the total lump-sum bid that plaintiff had submitted for Bid Item No. 1.

The Navy calculated the deduction of Southgate Housing from the contract price by using the per-unit prices supplied by plaintiff in the Schedule. It subtracted from the Bid Item No. 1 lump-sum bid an amount to account for the Navy’s estimated decrease in the tasks that would be required under Bid Item No. 1 as a result of the deletion of the 74 Southgate Housing units.

On January 11, 1985, pursuant to the contract’s changes clause, defendant issued Change Order No. 20, which deleted South-gate Housing from the contract and decreased the contract lump-sum price covering Bid Item No. 1. Over the three-year term of the contract, the contracting officer deducted a total of $43,018 from the contract price to account for this deletion. The deduction covered not only the time period after the January 11, 1985, Change Order, but also the period from June 1, 1984, up through the issuance of the Change Order on the ground that maintenance work actually ceased on June 1, 1984. Plaintiff filed this action to recover the monies deducted.4

Discussion

I.

In their respective summary judgment motions, the parties dispute whether the changes clause provides a contractual basis for decreasing the contract price as a result of the deletion of Southgate Housing. Plaintiff argues that the contract is properly characterized as a requirements contract and that the government cannot use the changes clause to reduce a fixed fee in a requirements contract when it is faced with a downward fluctuation in government requirements. In response, defendant contends first that Bid Item No. 1 is properly characterized as a fixed-price, lump-sum contract rather than a requirements contract, and second that even if it were a requirements contract, the changes clause can support a downward equitable adjustment based on the deletion of Southgate Housing.5

But it is not necessary for the court to resolve these disputes concerning the proper characterization of the contract and whether the changes clause can support defendant’s actions. In any event, there is an independent basis in the contract for deleting Southgate Housing and reducing the contract fee — the contract’s termination for convenience clause. The termination for convenience clause provides:

The Contracting Officer, by written notice, may terminate this contract, in whole or in part, when it is in the best interest of the Government.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bruce Construction Corporation v. The United States
324 F.2d 516 (Court of Claims, 1963)
Brown & Son Electric Company v. The United States
325 F.2d 446 (Court of Claims, 1963)
Charles R. Nesbitt v. The United States
345 F.2d 583 (Court of Claims, 1965)
Maxima Corporation v. The United States
847 F.2d 1549 (Federal Circuit, 1988)
Salsbury Industries v. United States
35 Cont. Cas. Fed. 75,661 (Court of Claims, 1989)
Nesbitt v. United States
170 Ct. Cl. 666 (Court of Claims, 1965)
G. C. Casebolt Co. v. United States
421 F.2d 710 (Court of Claims, 1970)
Varo, Inc. v. United States
548 F.2d 953 (Court of Claims, 1977)
Torncello v. United States
681 F.2d 756 (Court of Claims, 1982)
Litchfield Securities Corp. v. United States
377 U.S. 931 (Supreme Court, 1964)

Cite This Page — Counsel Stack

Bluebook (online)
35 Cont. Cas. Fed. 75,698, 17 Cl. Ct. 544, 1989 U.S. Claims LEXIS 141, 1989 WL 83134, Counsel Stack Legal Research, https://law.counselstack.com/opinion/b-h-supply-co-v-united-states-cc-1989.