B & D Investment Corp. v. Petticord

659 P.2d 400, 61 Or. App. 585, 1983 Ore. App. LEXIS 2226
CourtCourt of Appeals of Oregon
DecidedFebruary 16, 1983
Docket77-6-414; CA A22762
StatusPublished
Cited by1 cases

This text of 659 P.2d 400 (B & D Investment Corp. v. Petticord) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
B & D Investment Corp. v. Petticord, 659 P.2d 400, 61 Or. App. 585, 1983 Ore. App. LEXIS 2226 (Or. Ct. App. 1983).

Opinion

RICHARDSON, P. J.

This case is now before us on the parties’ appeals from the judgment entered after our remand in B & D Investment v. Petticord, 48 Or App 345, 617 P2d 276, rev den 290 Or 302 (1980).

Plaintiff B & D Investment Corporation initially brought the action to foreclose a construction lien and to recover damages in connection with plaintiffs efforts to construct a residence for defendants James and Doris Petticord. Defendants Pioneer National Title Insurance Company (Pioneer) and First National Bank of Oregon (bank) are, respectively, the trustee and beneficiary of a trust deed that plaintiff claimed was subordinate to the lien. At the first trial, the trial court decreed foreclosure of the lien and awarded plaintiff damages against the Petticords. We reversed the foreclosure and remanded the case to the trial court to award appropriate quantum meruit damages.

On remand, the trial court, inter alia, awarded plaintiff damages of $20,436.26 against the Petticords, dismissed the complaint as to Pioneer and the bank and awarded Pioneer, the bank and plaintiff costs and disbursements but not attorney fees. The Petticords appeal from the damage award. Pioneer and the bank appeal from the denial of attorney fees. Plaintiff cross-appeals from the denial of the attorney fees it sought. We again reverse and remand.

In our earlier decision, we found generally that plaintiffs attempt to construct the residence was seriously impeded by defects in the plans prepared by the Petticords’ architect. Plaintiff deviated from the plans, apparently with the architect’s authorization. However, the contract required plaintiff to obtain the Petticords’ approval before departing from the plans, but plaintiff did not do so. We therefore concluded:

“When a contractor makes intentional and substantial deviations from the contract plans and specifications without the owner’s consent, he is not entitled to foreclose a construction lien. * * *
<<* * * * *
“* * * B & D bypassed the written change order procedure provided for in the contract, and intentionally built [588]*588the house in a manner materially different from that set out in the plans. * * *” 48 Or App at 348, 354. ■

We instructed the trial court on remand to

“* * * determine the reasonable value, if any, of the materials furnished and services rendered by the plaintiff to the defendants Petticord. Welch v. Webb, 47 Or App 771, 615 P2d 391 (1980); Betz [Construction] v. Peterson, 47 Or App 333, 614 P2d 1184 [rev 289 Or 677] (1980).” 48 Or App at 355. (Footnote omitted.)

Against that background, we turn to the present appeals.

Plaintiff and the Petticords devote large parts of their briefs to conflicting recitations of the facts. In our view, those factual disagreements are of limited relevance to our disposition and will be discussed only as they bear on the legal issues we consider.

Plaintiff and the Petticords disagree about what test the trial court should have applied in determining plaintiffs quantum meruit damages. It can be ascertained from the court’s written findings that the method used was to determine the “reasonable value of the total work and materials” and to subtract from that amount, first, the value of services and materials “in excess of [those] authorized by the contract” and, second, the amounts previously paid plaintiff.

Each party contends, essentially, that the other breached the contract and that it did not. Given its view of the facts, plaintiff argues that the trial court applied the correct standard in measuring damages and that there was substantial evidence to support the award. See City of Portland v. Hoffman Const. Co., 286 Or 789, 596 P2d 1305 (1979). Given their factual premises, the Petticords argue that the trial court should have measured damages in accordance with Restatement of Contracts, § 357 (1932). The Petticords rely on Welch v. Webb, 47 Or App 771, 615 P2d 391 (1980), where we said;

“* * * rpj^ mje jg sta£e(j jn Restatement of Contracts, § 357 (1) (1932):
“ ‘(1) Where the defendant fails or refuses to perform his contract and is justified therein by the plaintiffs own breach of duty or non-performance of a condition, but the plaintiff has rendered a part performance under the [589]*589contract that is a net benefit to the defendant, the plaintiff can get judgment, * * * for the amount of such benefit in excess of the harm that he has caused to the defendant by his own breach, in no case exceeding a ratable proportion of the agreed compensation, if
“ ‘(a) the plaintiffs breach or non-performance is not wilful and deliberate; or
“ ‘(b) the defendant, with knowledge that the plaintiffs breach of duty or non-performance of condition has occurred * * * accepts the benefit of [the part performance]
* :}: * ft
“See Trachsel v. Barney, 264 Or 29, 34, 503 P2d 696 (1972).
“The trial court has already made findings as to the reasonable value of the work done by plaintiffs. Defendant counterclaimed for the costs incurred in completing the work plaintiffs had started. Defendant had presented evidence of those costs. We therefore remand the matter to the trial court to make findings regarding the extent to which plaintiffs’ work benefited defendant and the amount, if any, of defendant’s offsetting damages. * * *” 47 Or App at 775-76. (Footnote omitted.)

See also City of Portland v. Hoffman Const. Co., supra, 286 Or at 803, n 10.

If the Petticords’ view of the facts is correct, damages should have been determined in accordance with Welch v. Webb, supra, rather than in accordance with the formula the trial court used. However, the court did not make the findings necessary to enable us to know whether Welch should have been applied.

The court’s only finding bearing on breach or nonperformance by either party was that “defendants] Petticord [have] failed to prove that a breach of contract by plaintiff caused damage which would constitute a basis for recoupment by [the Petticords].” We found in the first appeal that plaintiff had intentionally breached the contract by not complying with the provision governing approval of change orders; our de novo finding was binding on the trial court on remand.1 It is not clear whether the [590]*590trial court’s finding is consistent with ours. If the former is read to mean only that no damages that the Petticords could recover by counterclaim resulted from plaintiffs breach, our finding and that of the trial judge are not necessarily inconsistent. Our opinion did not address a number of contentions by the Petticords regarding acts or omissions by plaintiff that allegedly caused damage. Most significantly, the Petticords argue that inferior workmanship by plaintiff was the source of much of the damage they sustained. On remand, the trial court found that the Petticords had not proved that plaintiffs work was not performed in a good and workmanlike manner.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

B & D Investment Corp. v. Petticord
689 P.2d 1052 (Court of Appeals of Oregon, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
659 P.2d 400, 61 Or. App. 585, 1983 Ore. App. LEXIS 2226, Counsel Stack Legal Research, https://law.counselstack.com/opinion/b-d-investment-corp-v-petticord-orctapp-1983.