B and S Equipment Co., Inc. v. Central States Underwater Contracting, Inc.

District Court, E.D. Louisiana·Decided April 23, 2020·No. 2:19-cv-14769·Unknown

Opinion

UNITED STATES DISTRICT COURT EASTERN DISTRICT OF LOUISIANA

B AND S EQUIPMENT CO., INC. CIVIL ACTION

VERSUS NO. 19-14769

CENTRAL STATES UNDERWATER SECTION M (2) CONTRACTING, INC.

ORDER & REASONS Before the Court is a motion by plaintiff and defendant-in-counterclaim B&S Equipment Co., Inc. (“B&S”) to dismiss1 the tortious interference with contract claim brought against B&S by defendant and plaintiff-in-counterclaim Central States Underwater Contracting, Inc. (“CSU”).2 CSU responds in opposition.3 Having considered the parties’ memoranda, the record, and the applicable law, the Court concludes that B&S’s motion should be denied because CSU pleaded the elements of a claim for tortious interference with business relations, even though CSU mistitled it as a claim for tortious interference with contract.

I. BACKGROUND

This case involves a breach-of-contract claim arising from a failure to pay. According to B&S, on August 27, 2018, CSU approached B&S to supply manpower and equipment to support CSU’s pipeline abandonment project (the “Project”).4 The parties entered into a contract (the “Contract”), B&S performed the Contract, and B&S eventually issued three invoices to CSU totaling $351,135.68.5 To date, CSU has paid B&S only $150,000.00.6 On October 16, 2019,

1 R. Doc. 14. 2 R. Doc. 1-10 at 6 (CSU’s counterclaim). 3 R. Doc. 17. 4 R. Doc. 1-8 at 2. 5 Id. at 4. 6 Id. B&S filed the instant action in state court against CSU seeking damages for breach of contract, alleging that “[d]espite repeated amicable demand, [CSU] has failed to pay B&S anything toward the outstanding balance.”7 B&S claims that as a result of this breach, it “has incurred, and continues to incur, significant costs and damages.”8 B&S served its state-court petition on CSU on December 2, 2019.

On December 23, 2019, CSU filed an answer and reconventional demand (i.e., counterclaim) in state court, telling a different story than B&S.9 According to CSU, upon its contacting Scott Ryals of B&S on August 27, 2018, about the Project, B&S proposed a flat rate of $7,500 per day and indicated that B&S could commence work on September 7, 2018 (which CSU refers to as the first attempt to mobilize for repair of the pipeline, or “First Mob Attempt”).10 CSU accepted B&S’s terms and “stressed to B&S that time was of the essence.”11 On September 6, 2018, B&S informed CSU that its charges would be higher than previously agreed.12 Then on September 10, 2018, three days after B&S said it could commence work on the Project, Ryals informed CSU that B&S’s boat was inoperable due to mechanical problems.13 When B&S finally

arrived to the job site on September 13, 2018, the Project was “canceled due to the unsafe conditions caused by the rising river.”14 On September 28, 2018, after the unsafe conditions subsided, CSU contacted B&S about remobilizing to repair the pipeline (“Second Mob Attempt”), with Ryals assuring CSU it would only take “two to three days to Mob in.”15 On October 9, 2018,

7 Id. 8 Id. 9 R. Doc. 1-10. 10 Id. at 4. 11 Id. 12 Id. 13 Id. at 4-5. 14 Id. at 5. 15 Id. CSU informed B&S that the Second Mob Attempt would begin on October 16, 2018.16 According to CSU, B&S invoiced CSU for the First and Second Mob Attempts despite B&S’s failure to meet its obligations under the Contract.17 In its answer and reconventional demand, CSU alleges B&S breached its duties under the Contract “[t]hrough its actions and inactions ... including but not limited to failing to arrive at the job site on time during the First Mob Attempt and ongoing delays

on both the First Mob Attempt and the Second Mob Attempt.”18 CSU claims that as a result of this breach, it “has incurred significant costs and damages.”19 Additionally, CSU alleges it lost “valuable contracts” for 2019 with its clients Enterprise Products (“Enterprise”) and Marathon Petroleum (“Marathon”) as a result of statements made by Ryals and B&S, who allegedly contacted both companies to inform them that “CSU does not pay its bills” and to demand that they “stop working with CSU.”20 According to CSU, Ryals and B&S knew of these existing contracts at the time Ryals made these “defamatory and disparaging statements … in bad faith and/or with malicious intent” to both Enterprise and Marathon “with the intent to cause CSU to lose work” and, as a result of these statements, CSU lost its 2019 contracts with both clients.21 CSU claims, then, that B&S tortiously interfered with CSU’s contracts with

Enterprise and Marathon. On December 27, 2019, less than 30 days following the date of service of B&S’s petition on CSU (i.e., December 2, 2019), CSU removed this action to this Court alleging diversity subject- matter jurisdiction under 28 U.S.C. § 1332.22 B&S moved to remand this action arguing that CSU waived its right to removal by filing in state court a permissive counterclaim for tortious

16 Id. 17 Id. 18 Id. 19 Id. 20 Id. 21 Id. at 6. 22 R. Doc. 1 at 1. interference with contract.23 The Court denied the remand motion, finding that CSU had not clearly and unequivocally waived its right to removal because one of the two claims CSU asserted in its state-court reconventional demand was a compulsory counterclaim (breach of contract) even though the other was a permissive counterclaim (tortious interference with contract).24 In so holding, the Court noted that CSU’s claim for tortious interference with contract may not be valid

because: Louisiana recognizes “only a corporate officer’s duty to refrain from intentional and unjustified interference with the contractual relation between his employer and a third person.” 9 to 5 Fashions, Inc. v. Spurney, 538 So. 2d 228, 234 (La. 1989). CSU does not make a claim against any individual, much less one of its own corporate officers, but asserts its claim against B&S’s corporate officer not for interference with any of B&S’s contracts with third parties, but for interference with CSU’s contracts with third parties.25

Understandably, the next day, B&S filed the instant motion to dismiss CSU’s counterclaim for tortious interference with contract essentially for the reasons stated by the Court in this footnote from its prior Order & Reasons.26 B&S argues that while Louisiana courts recognize a narrow cause of action for tortious interference with contract, it is limited to a claim against a corporate officer for interference with the contractual relations between his or her corporate employer and a third person or entity.27 According to B&S, CSU’s claim does not fit this mold because it is asserted against a corporate entity (B&S), not one of CSU’s own officers.28 In opposition, CSU concedes that it does not have a claim for tortious interference with contract as outlined in 9 to 5 Fashions, but argues that the claim so labeled should not be dismissed because it is actually a claim for tortious interference with business relations.29 CSU argues that

23 R. Doc. 8. In its motion to remand, B&S failed to address CSU’s breach-of-contract counterclaim. 24 R. Doc. 13. 25 Id. at 12 n.39. 26 R. Doc. 14. 27 R. Doc. 14-1 at 3-5. 28 Id. 29 R. Doc. 17 at 5-6. it has adequately stated such a claim against B&S for Ryals’s deliberate and malicious interference with CSU’s contracts with Enterprise and Marathon.30 II. LAW & ANALYSIS A. Rule 12(b)(6) Standard The Federal Rules of Civil Procedure require a complaint to contain “a short and plain statement of the claim showing that the pleader is entitled to relief.” Fed. R. Civ. P. 8(a)(2).

Free access — add to your briefcase to read the full text and ask questions with AI

B and S Equipment Co., Inc. v. Central States Underwater Contracting, Inc., (E.D. La. 2020).

B and S Equipment Co., Inc. v. Central States Underwater Contracting, Inc. (B and S Equipment Co., Inc. v. Central States Underwater Contracting, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Junior Money Bags, Ltd. v. Segal
970 F.2d 1 (Fifth Circuit, 1992)
Collins v. Morgan Stanley Dean Witter
224 F.3d 496 (Fifth Circuit, 2000)
Kitty Hawk Aircargo, Inc. v. Chao
418 F.3d 453 (Fifth Circuit, 2005)
Dorsey v. Portfolio Equities, Inc.
540 F.3d 333 (Fifth Circuit, 2008)
Harrington v. State Farm Fire & Casualty Co.
563 F.3d 141 (Fifth Circuit, 2009)
Lone Star Fund v (U.S.), L.P. v. Barclays Bank PLC
594 F.3d 383 (Fifth Circuit, 2010)
Conley v. Gibson
355 U.S. 41 (Supreme Court, 1957)
Tellabs, Inc. v. Makor Issues & Rights, Ltd.
551 U.S. 308 (Supreme Court, 2007)
Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Turner v. Pleasant
663 F.3d 770 (Fifth Circuit, 2011)
Rocky Mountain Choppers, L.L.C v. Textron Financia
540 Fed. Appx. 408 (Fifth Circuit, 2013)
9 to 5 Fashions, Inc. v. Spurney
538 So. 2d 228 (Supreme Court of Louisiana, 1989)
JCD Marketing Co. v. Bass Hotels and Resorts, Inc.
812 So. 2d 834 (Louisiana Court of Appeal, 2002)
Bogues v. Louisiana Energy Consultants, Inc.
71 So. 3d 1128 (Louisiana Court of Appeal, 2011)
IberiaBank v. Darryl Broussard
907 F.3d 826 (Fifth Circuit, 2018)
Whitney Bank v. SMI Companies Global, Inc.
949 F.3d 196 (Fifth Circuit, 2020)