Avery v. Fredericksen and Westbrook

154 P.2d 41, 67 Cal. App. 2d 334, 1944 Cal. App. LEXIS 1316
CourtCalifornia Court of Appeal
DecidedDecember 18, 1944
DocketCiv. 7079
StatusPublished
Cited by15 cases

This text of 154 P.2d 41 (Avery v. Fredericksen and Westbrook) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Avery v. Fredericksen and Westbrook, 154 P.2d 41, 67 Cal. App. 2d 334, 1944 Cal. App. LEXIS 1316 (Cal. Ct. App. 1944).

Opinion

ADAMS, P. J.

Appellant Avery, and respondents Fredericksen and Westbrook, a copartnership, entered into a contract which recited that the latter had entered into a contract with the United States War Department which required the use of material (granite sand) believed to be available on land owned by Avery; that ■ ‘ ‘ Owner grants to Contractor the right to enter upon the property and to remove, and the Contractor agrees to remove, therefrom such quantities of the material as Contractor may require in the performance of its said Contract”; that “Contractor agrees to pay to Owner, and Owner agrees to accept from Contractor, the sum of twenty-five dollars ($25.00) per acre for the acres used in the performance of its contract. Payment of ($150.00) one hundred and fifty dollars for the site of six acres shall be payed [sic] upon the signing of this agreement”; that “Before removing the required material, Contractor agrees to strip one foot of top *335 soil from said property. After all of the required material has been removed, Contractor agrees to level .off any. portion of the property from which material is removed, and to replace the top soil, and to replace all fences which it may have removed. ’ ’ The land was described as a six-acre site situated on the southeast corner of the owner’s property.

Respondents entered upon the land and removed 100,000 cubic yards of material from a three and one-half acre portion thereof, but did not level off such portion, nor replace the top soil. Appellant sued for damages in the sum of $10,400, alleged to be the reasonable cost of leveling off said three and one-half acres and replacing the top soil. The action was tried by the court sitting without a jury, and resulted in a judgment for appellant for $87.50 which the court found to be the value of the three and one-half acres, at $25 per acre. While the court found that the reasonable cost of leveling the area and replacing the top soil is $10,400, it held that' damages in an amount greater than the total value of the land would be excessive and unreasonable.

The only question raised on this appeal is whether the court applied the correct measure of damages. It is agreed by the parties that the measure of damages is fixed by section 3300 of the Civil Code which reads: “For the breach of an obligation arising from contract, the measure of damages, except where otherwise expressly provided by this code, is the amount which will compensate the party aggrieved for all the detriment proximately caused thereby, or which, in the ordinary course of things, would be likely to result therefrom.” Section 3358 of the Civil Code provides: “Notwithstanding the provisions of this chapter, no person can recover a greater amount in damages for the breach of an obligation than he could have gained by the full performance thereof on both sides, except in the eases specified in the articles on exemplary damages and penal damages, and in sections three thousand three hundred and nineteen, three thousand three hundred and thirty-nine, and three thousand three hundred and forty.” And section 3359 of the Civil Code also provides: “Damages must, in all cases, be reasonable, and where an obligation of any kind appears to create a right to unconscionable and grossly oppressive damages, contrary to substantial justice, no more than reasonable damages can be recovered.”

In spite of these provisions and though, according ;to the evidence in the case, plaintiff’s land, if restored to its origi *336 nal condition, would have no greater value than the amount awarded as damages, appellant contends for the right to recover from defendants $10,400, as the cost of filling the pit left by defendants, the leveling of the three and one-half acres, and the replacement of the top soil thereon.

We agree with the finding of the trial court that an amount greater than the total value of the land would be excessive and unreasonable, and are of the opinion that the amount awarded fully compensates plaintiff for the detriment suffered by him by reason of the acts of defendants. It is said in 8 Ruling Case Law 434-435, that one who has been injured by the breach of a contract or the commission of a tort is entitled to a just and adequate compensation for such injury, and no more; that in no case should he be placed in a better position than he would be in had the wrong not been done or the contract not been broken. Also, at page 453, the same authority states that courts generally agree that the rule of compensation to an injured party controls the measure of damages both in actions ex contractu and ex delicto, and that many authorities hold that the liability for loss incident to and resulting from a breach of a contract is generally not so extensive as that for a loss resulting from the commission of a tort. Also, page 454, that the loss or injury actually sustained rather than the. price paid or agreed to be paid on full performance, is the proper measure of damages, except where the contract provides by way of stipulated damages that the consideration shall be'the amount recoverable.

We also find it stated in 15 American Jurisprudence 400, that the fundamental principle of the law of damages is that one injured by a breach of a contract or by a wrongful or negligent act or omission shall have fair and just compensation commensurate with the loss sustained in consequence of defendant’s act which gives rise to the action; also, pages 402-404, that “The fundamental principle of the law of damages being compensation for the injury sustained, the plaintiff in a civil action for damages cannot, except in the eases in which punitive damages may be recovered, hold a defendant liable in damages for more than the actual loss which he has inflicted by his wrong. In other words, one injured by the breach of a contract or the commission of a tort is entitled to a just and adequate compensation for such injury, but no more. His recovery is, in the absence of circumstances giving rise to an allowance of punitive damages, limited to a fair compensation *337 and indemnity for the injury which he suffered. The law will not put him in a better position than he would be in had the wrong not been done or the contract not been broken.” These same principles are stated in 8 California Jurisprudence 821, where it is said that the general rule as to the measure of damages for breach of contract is the actual loss sustained; that it is a fundamental rule of law that courts will not, except where exemplary damages are given, allow a party to a contract to recover more upon its breach than he would have received by its due performance. It is also said, at page 742, that the object of damages is to give compensation for the loss from the injury sustained, and that they should be exactly commensurate with the injury, neither more nor less; that, as stated in Coburn v. California etc. Cement Co., 144 Cal. 81, 84 [77 P. 771], “The law seeks to give the complaining party the value of his bargain—to prevent a loss which the fulfillment of the contract would have prevented—to put the injured party, so far as money can do it, in the same position as if the contract had been performed. ’ ’

In the early case of De Costa v. Massachusetts etc. Min. Co., 17 Cal. 613, defendant dug a ditch on plaintiff’s land. Plaintiff sued to have the ditch abated and filled up, and for damages.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ryu v. Choi CA2/7
California Court of Appeal, 2013
Clayworth v. Pfizer, Inc.
165 Cal. App. 4th 209 (California Court of Appeal, 2008)
Mozzetti v. City of Brisbane
67 Cal. App. 3d 565 (California Court of Appeal, 1977)
Pepitone v. Russo
64 Cal. App. 3d 685 (California Court of Appeal, 1976)
People v. Southern California Edison Co.
56 Cal. App. 3d 593 (California Court of Appeal, 1976)
Wickman v. Opper
188 Cal. App. 2d 129 (California Court of Appeal, 1961)
Estate of De Laveaga
326 P.2d 129 (California Supreme Court, 1958)
Somavia v. Betts
326 P.2d 129 (California Supreme Court, 1958)
Basin Oil Co. v. Baash-Ross Tool Co.
271 P.2d 122 (California Court of Appeal, 1954)
Rakish v. Valerga
270 P.2d 50 (California Court of Appeal, 1954)
Coughlin v. Blair
262 P.2d 305 (California Supreme Court, 1953)

Cite This Page — Counsel Stack

Bluebook (online)
154 P.2d 41, 67 Cal. App. 2d 334, 1944 Cal. App. LEXIS 1316, Counsel Stack Legal Research, https://law.counselstack.com/opinion/avery-v-fredericksen-and-westbrook-calctapp-1944.