AvalonBay Communities, Inc. v. Sewer Commission

853 A.2d 497, 270 Conn. 409, 2004 Conn. LEXIS 303
CourtSupreme Court of Connecticut
DecidedJuly 27, 2004
DocketSC 17131
StatusPublished
Cited by18 cases

This text of 853 A.2d 497 (AvalonBay Communities, Inc. v. Sewer Commission) is published on Counsel Stack Legal Research, covering Supreme Court of Connecticut primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
AvalonBay Communities, Inc. v. Sewer Commission, 853 A.2d 497, 270 Conn. 409, 2004 Conn. LEXIS 303 (Colo. 2004).

Opinion

Opinion

NORCOTT, J.

This appeal arises out of an action brought by the named plaintiff, AvalonBay Communities, Inc. (AvalonBay),1 against the defendants, the sewer commission of the city of Milford and its chairman, Peter Vita (collectively, the commission), and the city of Milford (city), seeking a writ of mandamus ordering the commission to approve its application to connect a proposed housing development to the city’s sanitary sewer system. After a bench trial, the trial court denied the writ requested. AvalonBay appealed from the judgment of the trial court to the Appellate Court, and we transferred the appeal to this court pursuant to General Statutes § 51-199 (c) and Practice Book § 65-1.

On appeal, AvalonBay claims that the trial court improperly denied its request for a writ of mandamus because: (1) its application complied with all of the applicable regulations of the commission, and, therefore, it had a legal right to performance; (2) the commission had no discretion to depart from the ministerial task of approving the application; and (3) it had no adequate remedy at law. Additionally, AvalonBay claims that the trial court’s factual findings were clearly erroneous, and that the judgment of the trial court thwarts this state’s public policy in favor of the development of affordable housing. In response, the commission claims [413]*413that: (1) the trial court properly found that the commission had discretion to deny AvalonBay’s application; (2) the trial court properly exercised its discretion in denying the relief requested; and (3) the trial court’s evidentiary findings were not clearly erroneous. We agree with the commission. Accordingly, we affirm the judgment of the trial court.

The following facts, as set forth by the trial court in its memorandum of decision, are relevant to this appeal. “The property, which is subject of the mandamus, is owned by the [e] state of Patricia McGannon and is presently under contract of sale to AvalonBay . . . the proposed developer of the property. . . . The property consists of some forty-two acres . . . and is located in the northwestern section of the city ... in the immediate vicinity of and south of the Wilbur Cross Parkway. More specifically, the property is located southwest of the intersection of Wheeler’s Farm Road and Wolf Harbor Road. The property is presently unimproved. AvalonBay proposes to erect thereon [a development containing] some 284 units of luxury housing,”2 a percentage of which would be set aside as “moderate income housing” under General Statutes § 8-30g (3).

The commission “was created by [29 Spec. Acts 142, No. 139 (1959)] of the 1959 General Assembly .... In its present form, the provisions establishing and maintaining the commission may be found in article IV, [§§ 2 and 9] of the Milford charter. As the water pollution control authority, the commission holds the powers vested in such an authority by way of chapter 103 of the . . . General Statutes.3

“Pursuant to the authority contained therein, a facility plan and environmental assessment dated January, [414]*4141981, [was] filed with the state of Connecticut. Included with the plan was a 1979 map of the proposed sewer system and extensions . . . [which demonstrated] that the city and [the] commission contemplated the eventual expansion of the sanitary sewer system so as to encompass the entire city. Since that time, the area of coverage has been steadily extended by a series of contracts designated by year and number. . . .

“Contract No. 1998-1 called for the extension of the sewer system to serve an area south of the Wilbur Cross Parkway, including Wolf Harbor Road and several other streets in the area. . . . [Specifically] contract No. 1998-1 was designed as an extension of the [city] sanitary sewer system to run from West River Street westerly along Wolf Harbor Road to a point approximately 200 feet easterly of [AvalonBay’s] property.”4

“On February 26, 2000, a contract was let to perform the work specified in [contract No.] 1998-1. During the course of that work, serious difficulties were encountered. Located in Wolf Harbor Road [were] a natural gas main and a sixteen inch water main. As the construction proceeded, the contractor encountered bedrock. . . . Attempts to remove the bedrock by blasting caused several breaks [in the water main], disrupting the water flow in the area. On May 4, 2000, the blasting disrupted the water main for the third time, causing the regional water authority to demand a halt to the project. The commission ordered a halt to the project, although it allowed an extension of the sewer main to station 12-40 ... . The bedrock was removed by mechanical means [in that limited area]. The contractor offered to continue the project removing the bedrock by mechanical means. This would . . . [have] entail[ed] an addi[415]*415tional cost for which funds would have to be appropriated. . . .5

“In an effort to find a solution to the problem, the commission, on July 6, 2000, voted to halt the construction in Wolf Harbor Road under contract No. 1998-1 and to include that section of Wolf Harbor [Road] under the design contract No. 2000-1 . . . [which the commission] had entered into . . . with its consultants for the design and extension of the sanitary sewer system covering an area north of Wilbur Cross Parkway .... The area covered by [contract No.] 2000-1 is to be connected to the area covered by [contract No.] 1998-1.

. . . An amendment to contract [No.] 2000-1 was entered into to consider the Boy’s Village tie-in and the redesign of the sewers in Wolf Harbor Road west of station 12-40, the termination point for contract [No.] 1998-1.”

During 2000, AvalonBay had “applied to various land use boards in the city . . . seeking various approvals for its proposed development of a luxury apartment community with an affordable housing component, pursuant to ... § 8-30g.” More specifically, in “July, 2000, AvalonBay [had] filed an application for sewer approval. The commission, in August, 2000, denied the application without prejudice, giving as its reason that no sewer line was then available. The following November, [AvalonBay] filed a second application asking for permission to connect their development to the sewerage system. The commission, on December 17, 2000, denied the application without prejudice, giving as [its] reason for [denial] that a design study was under way [416]*416for the Wheeler’s Farm Road and Wolf Harbor Road area, and the study was then only 10 percent complete.”

“A mandamus action was brought by . . . AvalonBay on April 27, 2001, seeking an order directing the [commission] to permit the connection of [its proposed] development to the city . . . sewer system.6 [Subsequently, a] third application was filed with the [commission] on July 19, 2001. The matter was tabled awaiting finalized plans for the preliminary design [under contract No. 2000-1] of that segment of the [sewer system] that would service the area, including [AvalonBay’s] property. ”7 AvalonBay’s third application is still pending before the commission. Consequently, because work under contract No. 1998-1 was halted, and the plans being developed under contract No. 2000-1 were still in the preliminary stages of design, there was no sewer system in the road closest to AvalonBay’s property, namely, Wolf Harbor Road, at the time of trial.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Baywing, LLC v. Water Pollution Control Authority
Connecticut Appellate Court, 2026
Aldin Associates Ltd. Partnership v. State
230 Conn. App. 223 (Connecticut Appellate Court, 2025)
Borelli v. Renaldi
Supreme Court of Connecticut, 2021
Cooke v. Commissioner of Correction
194 Conn. App. 807 (Connecticut Appellate Court, 2019)
Wozniak v. Colchester
193 Conn. App. 842 (Connecticut Appellate Court, 2019)
Summit Saugatuck, LLC v. Water Pollution Control Authority
193 Conn. App. 823 (Connecticut Appellate Court, 2019)
JPMorgan Chase Bank, National Assn. v. Virgulak
Connecticut Appellate Court, 2019
City of Hartford v. McKeever
55 A.3d 787 (Connecticut Appellate Court, 2012)
Zahrijczuk v. Water Pollution Control Authority of Branford
50 A.3d 421 (Connecticut Superior Court, 2012)
Stewart v. Town of Watertown
38 A.3d 72 (Supreme Court of Connecticut, 2012)
Water Pollution Control Authority v. Johnson
26 A.3d 87 (Connecticut Appellate Court, 2011)
Traylor v. STATE SUPERIOR COURT
15 A.3d 1173 (Connecticut Appellate Court, 2011)
Dauti Construction, LLC v. Water & Sewer Authority
10 A.3d 84 (Connecticut Appellate Court, 2010)
Greenfield v. Reynolds
1 A.3d 125 (Connecticut Appellate Court, 2010)
Forest Walk, LLC v. Water Pollution Control Authority
968 A.2d 345 (Supreme Court of Connecticut, 2009)
Jalowiec Realty Associates, L.P. v. Planning & Zoning Commission
898 A.2d 157 (Supreme Court of Connecticut, 2006)
Morris v. Congdon
893 A.2d 413 (Supreme Court of Connecticut, 2006)
Alter and Associates, LLC v. Lantz
876 A.2d 1204 (Connecticut Appellate Court, 2005)
River Bend Associates, Inc. v. Planning Commission
856 A.2d 959 (Supreme Court of Connecticut, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
853 A.2d 497, 270 Conn. 409, 2004 Conn. LEXIS 303, Counsel Stack Legal Research, https://law.counselstack.com/opinion/avalonbay-communities-inc-v-sewer-commission-conn-2004.