Automatic Control Products Corp. v. Tel-Tech, Inc.

780 P.2d 1258, 119 Utah Adv. Rep. 3, 1989 Utah LEXIS 123, 1989 WL 118024
CourtUtah Supreme Court
DecidedOctober 6, 1989
Docket20422
StatusPublished
Cited by9 cases

This text of 780 P.2d 1258 (Automatic Control Products Corp. v. Tel-Tech, Inc.) is published on Counsel Stack Legal Research, covering Utah Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Automatic Control Products Corp. v. Tel-Tech, Inc., 780 P.2d 1258, 119 Utah Adv. Rep. 3, 1989 Utah LEXIS 123, 1989 WL 118024 (Utah 1989).

Opinions

HOWE, Associate Chief Justice:

This action was brought by plaintiff Automatic Control Products Corp. (ACP) to recover $25,790.34 it claimed was due on an oral contract with defendant Tel-Tech, Inc. The trial court awarded ACP judgment for only $3,874.81, and ACP appeals.

Defendant Tel-Tech is engaged in the sale and installation of dairy and food processing equipment and machinery and in automating dairies and other food processing plants. Since its inception in 1975, Tel-Tech has often subcontracted with ACP to supply and install electric control panels which serve to turn on and off valves and pumps on the equipment and machinery which it sells. Until this litigation, Tel-Tech and ACP enjoyed a good relationship, with ACP installing approximately 200 panels on various Tel-Tech jobs. Although all contracts between Tel-Tech and ACP have been oral, these parties have not had any significant problems in their dealings with each other over the course of their seven-year business relationship.

. In the summer of 1981, Randy Telford, President of Tel-Tech, met with Larry Florence, President of ACP, to discuss the building of panels on a job Tel-Tech was bidding for at the Cache Valley Dairy Association (CVDA) plant at Amalga, Utah. The two men examined some sketches and piping diagrams of the proposed installation. Telford wrote on a piece of paper, “Control Panel Estimates from Larry (ACP)” and beneath that heading listed four kinds of panels that would be needed and a figure opposite each kind, ranging from $3,000 to $10,000 each. Below that was listed an additional panel without any figure opposite it. Telford testified that based on this estimate, the two men determined that ACP could build the required [1260]*1260panels for $31,600 and that he incorporated that figure into his bid to CVDA.

Tel-Tech was the successful bidder, and ACP did later construct and install the required panels. However, the parties are in sharp disagreement as to the contract price. Tel-Tech contends that the two men agreed on $31,600 as a firm figure and that although changes were made as the work progressed, they were largely substitutions which should not have increased ACP’s price above the estimate. Florence testified that only price estimates were discussed at their meeting, that ACP billed Tel-Tech on a material and time basis as it had done on previous jobs, and that many changes were made as the CVDA job progressed, increasing ACP’s costs. Both men acknowledged that Tel-Tech needed prices from ACP before it could bid the CVDA job. During the course of the work, ACP submitted invoices for payment to Tel-Tech. The latter paid $28,378.94 but refused to pay ACP’s final invoices, which would bring the total price to $54,169.28.

After a four-day trial, the trial judge, sitting without a jury, concluded that he could not determine from the evidence “whether plaintiff (ACP) and Tel-Tech entered into a firm bid contract or a time and materials contract.” However, the court .ruled that ACP was entitled to reasonable compensation for its services and materials, which it determined to be $32,253.75, a figure the court explained was “the mid point between the $37,707 and $33,968 high and low values of the services and materials involved less 10% to reflect prices at the time of contracting and performance.” These high and low values had been testified to by defendant’s expert, Raido Lanni. Consequently, judgment was awarded to ACP for the difference between $32,253.75 and $28,378.94, which had already been paid by Tel-Tech to ACP, or a net judgment of $3,874.81.

I.

ACP first contends that the trial court erred in mechanically adopting findings of fact and conclusions of law prepared and submitted by counsel for Tel-Tech without modifying or changing them in any respect. This contention finds its basis in Boyer Co. v. Lignell, 567 P.2d 1112 (Utah 1977), where we cautioned trial courts not to mechanically adopt findings of fact prepared and submitted by the prevailing party’s attorney. ACP points out that there is what appears to be a typographical error and a transposition of figures in the finding which indicate lack of care and circumspection by the trial court. We find no error. There is no indication from the record here that the trial judge failed to adequately deliberate and consider the merits of the case. The errors in the findings pointed out by ACP do not render the findings in any way ambiguous. After the trial, the court took the case under advisement, allowing both parties to submit memoranda, and later requested both parties to submit proposed findings of fact and conclusions of law. The fact that the trial court did not completely agree with the contentions made by either party would indicate that there was no “mechanical” adoption of the theory or evidence of either party.

Nor was there any error in the failure of the trial court to notify ACP’s counsel promptly after he had signed his findings of fact and conclusions of law and the judgment. Our rules do not require the court to give notice but put the burden on counsel to check periodically with the clerk of the court as to the date of entry of the findings and judgment so that post-trial motions may be timely filed.1

II.

ACP assails the findings of fact and conclusions of law made by the trial court in several respects.

First, ACP contends that the trial court erred in not awarding it as a base figure $31,600, which was the estimate giv[1261]*1261en by ACP to Tel-Tech, and then adding to that figure the cost of all extra items not included in the estimate. We conclude that the trial court was justified in not having done so since not all of the panels on the estimate were built. Substitutions were made for some of the panels which were not necessarily of equal value. However, three panels listed on the estimate were built, and ACP’s argument as to those three panels is sound. Since it is Tel-Tech’s position that the parties firmly agreed on prices for these three panels and ACP does not dispute these prices, the trial court should have used those agreed-upon prices instead of resorting to Lanni’s expert opinion of the reasonable and fair value of the three panels. The receiving panel was listed on the estimate at $3,000, but the trial court awarded the slightly lower sum of $2,985.50. Similarly, the main panel was listed on the estimate at $10,000. Yet the trial court awarded only $8,246. The third panel, a dual eductor panel, was included in-the estimate at $6,000 according to Telford. But Lanni and the trial court fixed a value of only $4,787.50. The judgment in favor of ACP should be increased by those differences which total $2,981, since it is Tel-Tech’s position that these estimated amounts were fair and reasonable and had been firmly agreed upon. No changes or substitutions were made affecting them, as was the case with the other panels listed on the estimate.

Second, ACP contends that because Tel-Tech paid invoices totalling $28,378.94 submitted by it as the job progressed without any objection, Tel-Tech cannot now object to or question the amounts charged for material and labor shown on those invoices. Thus ACP asserts that it was error for the trial court to allow Tel-Tech’s expert to testify and for the trial court to award lesser amounts for the items shown on the paid invoices. This argument might be valid if it were not Tel-Tech’s position that there was a firm bid and commitment to do the job for $31,600.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rothwell v. Rothwell
2023 UT App 50 (Court of Appeals of Utah, 2023)
Henshaw v. Estate of King
2007 UT App 378 (Court of Appeals of Utah, 2007)
Whitear v. Labor Commission
973 P.2d 982 (Court of Appeals of Utah, 1998)
West v. Grand County
942 P.2d 337 (Utah Supreme Court, 1997)
State v. James
858 P.2d 1012 (Court of Appeals of Utah, 1993)
Automatic Control Products Corp. v. Tel-Tech, Inc.
780 P.2d 1258 (Utah Supreme Court, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
780 P.2d 1258, 119 Utah Adv. Rep. 3, 1989 Utah LEXIS 123, 1989 WL 118024, Counsel Stack Legal Research, https://law.counselstack.com/opinion/automatic-control-products-corp-v-tel-tech-inc-utah-1989.