Audubon Society of Central Arkansas v. Dailey

977 F.2d 428
CourtCourt of Appeals for the Eighth Circuit
DecidedOctober 13, 1992
DocketNo. 91-1764
StatusPublished
Cited by4 cases

This text of 977 F.2d 428 (Audubon Society of Central Arkansas v. Dailey) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Audubon Society of Central Arkansas v. Dailey, 977 F.2d 428 (8th Cir. 1992).

Opinion

JOHN R. GIBSON, Circuit Judge.

The City of Little Rock, Arkansas, and various city officials1 appeal from the district court’s2 order enjoining them and their contractor, Joyner-Ford & Burke Construction Company, from proceeding with construction of a bridge over Jimerson Creek until the Army Corps of Engineers3 has prepared an environmental impact statement (EIS) regarding its grant of a permit to build the bridge. 761 F.Supp. 640. The district court held that the Corps [430]*430had ignored the considerable effect increased traffic resulting from the bridge and its connected project would have on recreational use of Murray Park, Rebsa-men Park, and other recreational areas on the south bank of the Arkansas River at Little Rock. The City argues that the Corps considered the effect of the traffic and that this court has no power to require the Corps to do anything further. Alternatively, the City requests that this court remand the matter to the Corps instead of affirming the order requiring an EIS. We affirm the judgment of the district court.

In 1987 the voters of Little Rock approved a capital improvement bond issue to build streets. At the time of the bond election, the city’s list of top twenty street projects included an extension of Rebsa-men Park Road permitting access to Murray Lock and Dam and Murray, LaHarpe View and Rebsamen parks from the west, where previously the only entrance had been from central Little Rock. These parks run alongside the Arkansas River near downtown Little Rock. The City has plans eventually to connect these parks to others in a “chain of parks.” After the election, the City submitted an application to the Corps for a permit to put fill in along Jimerson Creek, a tributary of the Arkansas River, which would have to be bridged as part of the road extension. It was necessary to apply for a permit because of section 10 of the Rivers and Harbors Appropriation Act of 1899, 33 U.S.C. § 403 (1988), and section 404 of the Clean Water Act, 33 U.S.C. § 1344 (1988). Under the National Environmental Policy Act (NEPA), federal agencies must prepare an EIS before approving “major federal actions significantly affecting the quality of the human environment.” 42 U.S.C. § 4332(2)(C) (1988). The Corps determined that, though the only action affecting national waters was the placement of the fill in Jimerson Creek, NEPA required the Corps to consider the environmental impact on the entire area of “the proposed road extension plus the existing Rebsamen Park Road from gateway to gateway.”

In connection with its review, the Corps gave notice to various state and federal agencies. In response to the notice, the Arkansas Department of Parks and Tourism identified as a potential problem the effect of increased traffic on recreational use of the Parks. The Department gave conditional approval to the project:

The Department of Parks and Tourism will support the referenced project if the project’s applicant, the City of Little Rock, makes every effort to ensure the safety and enjoyment of the users of this recreational area.... This Department recommends speed limits along the length of Rebsamen Park Road be set at no greater than 35 mph and reduced to 20 mph through the activity areas. Much of the danger introduced from this road extension would result from high speed traffic. As the plans are currently proposed, bicycles and pedestrians will be exposed to incredible risks if cars are passing at high speeds.

Joint Appendix at 360.

The Corps also gave public notice of the permit application, and received 64 public responses, 12 in support of the proposed road, 49 opposed to it, and 3 not expressing an opinion. The principal concern stated in the public responses was that the new road would be used as a commuter route from West Little Rock to downtown and spoil recreational use of the areas though which it passed. The Corps sent a letter to Little Rock's mayor, asking that the City provide traffic volume statistics for the road as it existed before the proposed extension and for the road with the proposed extension. The Corps also asked for average travel times from western Little Rock to downtown on the proposed Rebsamen Park Road compared with travel times for the same trip on the existing parallel route, Cantrell Road.

The Mayor responded that traffic on the existing Rebsamen Park Road was about 2,500 vehicles per day (vpd) on the weekend and 2,900 vpd on week days. The City estimated travel times from west Little Rock to downtown at 12.5 to 15 minutes on Cantrell Road and 13 minutes “or greater” on the proposed Rebsamen Park Road. If the City maintained a posted 35 mph speed [431]*431limit on the proposed Rebsamen Park road, the City projected traffic volume on the road at 4500 vpd shortly after completion. The City projected traffic volume in the year 2010 as 19,000 to 30,000 on Cantrell Road and 8,600 to 9,000 on the proposed Rebsamen Park Road if the speed limit were 35 mph. If the speed limit on Rebsa-men Park Road were 45 mph, the prediction for 2,010 would be 15,000 vpd or greater.

The Corps then hired Peters & Associates, consulting engineers, to study the effect of the road extension. Peters issued a report concluding that the traffic volumes anticipated by the City would include commuter traffic and would pose a threat to the recreational use of the areas along the Arkansas River. The report stated:

Traffic volumes increasing to only 4,500 vpd and compliance with a 35 MPH speed limit would be tolerable on the roadway as planned_ The Pulaski Area Transportation Study (PATS) has made volume projections for this section of Rebsamen Park Road to be between 8,600 and 9,000 vpd. If volumes of this magnitude materialize, it will most likely be a result of increased thru traffic use not a greater than three-fold increase in use of recreation facilities_ As a two-lane road the facility can accommodate, from a capacity standpoint, traffic volumes of the magnitude projected by PATS, but likely not without adverse impact on the recreational uses it is intended to serve. Although the route may not attract much thru traffic initially, as traffic volumes increase and congestion worsens on arte-rials and expressways, motorists will seek what they perceive as more attractive alternate routes, such as Rebsamen Park Road, even though travel times may not be significantly different. I believe this will eventually occur, probably over a five to six year period after completion, and volumes could easily grow to 8,000 to 9,000 vpd as projected by PATS.

Joint Appendix at 391. Peters made some remedial suggestions, including providing separate bridges over Jimerson Creek for autos, on the one hand, and bicycles and pedestrians, on the other; and “curvilinear alignment” and use of stop signs on Rebsa-men Park Road.

The City responded to the Peters report by asking' the Arkansas Highway and Transportation Department to project traffic volumes for the proposed road. The Department came up with a figure for the year 2010 of 5,384 to 9,265 vpd depending on the respective speeds at which traffic could travel on Rebsamen Park Road and Cantrell Road.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
977 F.2d 428, Counsel Stack Legal Research, https://law.counselstack.com/opinion/audubon-society-of-central-arkansas-v-dailey-ca8-1992.