ATS Ohio, Inc. v. EnerVenue, Inc.

CourtDistrict Court, S.D. Ohio
DecidedSeptember 25, 2025
Docket2:23-cv-04187
StatusUnknown

This text of ATS Ohio, Inc. v. EnerVenue, Inc. (ATS Ohio, Inc. v. EnerVenue, Inc.) is published on Counsel Stack Legal Research, covering District Court, S.D. Ohio primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
ATS Ohio, Inc. v. EnerVenue, Inc., (S.D. Ohio 2025).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE SOUTHERN DISTRICT OF OHIO EASTERN DIVISION

ATS OHIO, INC., : Case No. 2:23-cv-4187 : Plaintiff/Counter-Defendant, : : Judge Algenon L. Marbley v. : : Magistrate Judge Vascura ENERVENUE, INC., : : Defendant/Counter-Plaintiff. : OPINION & ORDER

This matter comes before this Court on Plaintiff/Counter-Defendant ATS Ohio, Inc.’s Motion for Sanctions against Defendant/Counter-Plaintiff EnerVenue, Inc. (ECF No. 33). For the reasons set forth herein, the Motion is GRANTED in part and DENIED in part. I. BACKGROUND This case is a contract dispute regarding a battery assembly system (the “System”). In 2021, California-based battery-producer EnerVenue, Inc. (“EnerVenue”) sought someone who could construct an “automated system for the production of EnerVenue’s 100 MWh [megawatt hour] batteries” in order to speed up its battery production. (ECF No. 18 ¶ 8). To that end, in mid- December 2021, EnerVenue engaged the Ohio-based ATS Ohio, Inc. (“ATS”) to manufacture the 100 MWh battery-production system it sought. (Id. ¶¶ 8–9; ECF No. 1 ¶¶ 2, 21, 30; see ECF No. 17 ¶ 21). The parties agree that this dispute is governed by a series of written agreements entered into between December 2021 to March 2023. (ECF No. 1 ¶¶ 1, 2, 39–41; ECF No. 18 ¶¶ 8–9). According to ATS, EnerVenue never alleged that ATS had breached the parties’ agreements from December 14, 2021 (when the Conditions of Sale were executed) to approximately March 27, 2023. (ECF No. 1 ¶ 40). Yet EnerVenue supposedly “stopped paying ATS” altogether some time after March 27, 2023, so that it now owes ATS over $5.7 million. (Id. ¶¶ 41–42). ATS alleges that because of this failure to pay, it “eventually removed its personnel from EnerVenue’s facility [in California] and cease[d] work,” ultimately terminating its relationship with EnerVenue and demanding final payment on November 3, 2023. (Id. ¶¶ 43–44; ECF No. 33-7). EnerVenue did not pay the amount ATS sought. Instead, on December 7, 2023,

EnerVenue replied to ATS, referring to a June 16, 2023 letter from EnerVenue that had supposedly notified ATS that ATS was in breach, and claiming that EnerVenue’s damages included the costs “of trying to get the line up and running after ATS left,” and the cost of “EnerVenue personnel having to do manual work” since March 21, 2022. (ECF No. 33-8). On December 19, 2023, ATS brought suit, alleging breach of contract and seeking over $5.7 million in damages. (ECF No. 1 ¶¶ 46–56). EnerVenue’s story is different. According to EnerVenue, it performed its contractual obligations or was excused from performing them. (ECF No. 18 ¶ 10). Instead, ATS breached the contract in a variety of ways. In EnerVenue’s account, ATS and its affiliates failed to provide:

the initial project schedule on time; the System’s assembly process flow; key testing-related documents; component quantity requirements for testing protocols; and clear installation instructions for helium and nitrogen tanks. (Id. ¶ 11). ATS and its affiliates also supposedly failed to: coordinate with subcontractors, ensure delivery of the System’s first module, meet testing deadlines; obtain vendor support; determine System engineering tolerances; ensure ATS personnel performed adequately; ensure ATS personnel completed all hardware and software tasks; and avoid creating design flaws in the System. (Id.). Thus, on February 15, 2024, EnerVenue brought its own breach of contract claim, alleging that ATS failed to deliver the contractually-required, completed System of a sufficient quality in a timely manner, causing EnerVenue to sustain millions of dollars in damages. (Id. ¶¶ 10, 12–17). The parties subsequently engaged in discovery regarding their competing breach of contract claims, which was ultimately scheduled to last until May 5, 2025. (See ECF No. 31).

During this discovery, ATS inquired about the System’s condition in April 2024. (ECF No. 33 at 5; see ECF No. 35 at 2). On or around May 10, 2024, EnerVenue provided responses and objections to, among other things, ATS’s Interrogatory No. 5, in which ATS queried “how many 100 MWh batteries EnerVenue is currently able to manufacture each month using the System, even in its current state of completion.” (ECF No. 33-2 at 8) (emphasis added). EnerVenue replied that it “is able to operate the line at a maximum capacity of approximately 20 MWh annually, or 20% of nameplate capacity,” due to a missing automated stacking module from ATS’s subcontractor, whose absence necessitated manual stacking, (Id.), and formed part of the basis for EnerVenue’s breach of contract Counterclaim.

Also during discovery, at some time in the summer of 2024, EnerVenue videotaped the System in operation, and produced these videos to ATS. (ECF No. 35 at 3). On August 8, 2024, counsel for ATS and EnerVenue emailed back and forth about these videos, with counsel for ATS asking whether they “reflect the current state of the 100MWh System as it is currently operating,” and EnerVenue’s counsel—not really answering the question that ATS had asked—replying that “[t]he videos were taken of the assembly line this summer.” (ECF No. 33-3) (emphasis added). On November 6, 2024,1 ATS’s counsel sent EnerVenue a Request to Inspect the System. (ECF No. 33-1; ECF No. 33 at 2). The next day, EnerVenue’s counsel replied, asking, “[ATS] want[s] to come inspect the current assembly line in operation (as it exists today), correct?” (ECF No. 33-1). ATS’s counsel confirmed that was correct. Days later, on November 12, 2024, EnerVenue’s counsel informed ATS that “In

approximately the summer of 2024,” EnerVenue decided to “stop[] manufacturing the 100Mwh batteries” “for business reasons,” and “[a]s a result of this decision, Enervenue disassembled the 100Mwh manufacturing assembly line. Accordingly, the company cannot comply with [ATS’s] request to inspect an assembly line that no longer exists.” (ECF No. 33-1) (emphasis added). This was the first time EnerVenue notified ATS that the System—central to EnerVenue’s counterclaims and the litigation broadly—no longer existed, and had not existed for months. On November 22, 2024, ATS served additional discovery requests on EnerVenue, naturally seeking a better understanding of why EnerVenue had destroyed the System. (ECF No. 33 at 6). On January 7, 2025, EnerVenue provided responses and objections to, among other things, ATS’s

Interrogatories Nos. 1 and 2, in which ATS asked when the System had been decommissioned, and where the System’s parts were. (ECF No. 33-5 at 1). EnerVenue replied that the System had been decommissioned and disassembled at some point during the week of July 7, 2024, and that the parts of the System “were nearly completely disassembled into individual components” in various locations. (Id. at 1–2). Although EnerVenue did not give a very clear accounting,

1 ATS suggests that it issued its Request for Inspection to EnerVenue on November 8, 2024, while Exhibits 1 and 4 appear to show that the Request for Inspection was issued to EnerVenue’s counsel on November 6, 2024. (Compare ECF Nos. 33-1, 33-4 with ECF No. 33 at 2). This Court will presume that Exhibits 1 and 4, which show an email and the Request for Inspection with a Certificate of Service each dated November 6, 2024, are correct. Ultimately, this minor difference is immaterial. apparently some parts of the System were still on-site in EnerVenue’s California facility, some were destined for an EnerVenue facility in China (although it was unclear if they had already been shipped or had arrived), and still others were to be sold (although it was unclear whether any of these parts had actually been sold yet). (Id.). On February 20, 2025, ATS filed this Motion for Sanctions against EnerVenue, accusing

EnerVenue of not only destroying the System during the summer of 2024, but of hiding the System’s destruction from ATS until November 12, 2024.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Beaven v. United States Department of Justice
622 F.3d 540 (Sixth Circuit, 2010)
Flagg Ex Rel. J.B. v. City of Detroit
715 F.3d 165 (Sixth Circuit, 2013)
Adkins v. Wolever
554 F.3d 650 (Sixth Circuit, 2009)
Joostberns v. United Parcel Services
166 F. App'x 783 (Sixth Circuit, 2006)
Sam Byrd v. Alpha Alliance Insurance Corp.
518 F. App'x 380 (Sixth Circuit, 2013)
Nancy McCarty v. Covol Fuels No. 2, LLC
644 F. App'x 372 (Sixth Circuit, 2016)
Lorie Applebaum v. Target Corporation
831 F.3d 740 (Sixth Circuit, 2016)
Crown Battery Manufacturing Co. v. Club Car, Inc.
185 F. Supp. 3d 987 (N.D. Ohio, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
ATS Ohio, Inc. v. EnerVenue, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/ats-ohio-inc-v-enervenue-inc-ohsd-2025.