Atlas Concrete Pipe, Inc. v. Roger J. Au & Son, Inc.

467 F. Supp. 830, 26 U.C.C. Rep. Serv. (West) 395, 1979 U.S. Dist. LEXIS 13985
CourtDistrict Court, E.D. Michigan
DecidedMarch 6, 1979
DocketCiv. A. 77-40159
StatusPublished
Cited by11 cases

This text of 467 F. Supp. 830 (Atlas Concrete Pipe, Inc. v. Roger J. Au & Son, Inc.) is published on Counsel Stack Legal Research, covering District Court, E.D. Michigan primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Atlas Concrete Pipe, Inc. v. Roger J. Au & Son, Inc., 467 F. Supp. 830, 26 U.C.C. Rep. Serv. (West) 395, 1979 U.S. Dist. LEXIS 13985 (E.D. Mich. 1979).

Opinion

MEMORANDUM OPINION AND ORDER

JAMES HARVEY, District Judge.

On October 6, 1970, plaintiff Atlas Concrete filed a complaint seeking damages for the alleged breach by the defendant Au of a contract for the sale of concrete pipe, as follows: (1) The alleged failure of Au to pay for pipe manufactured and delivered by Atlas to Au, and (2) the alleged failure by Au to install the pipe at the contract rate. Au later counterclaimed seeking damages for the alleged failure by Atlas to deliver the pipe at the contract rate, to remove excess pipe from the job site, and to deliver certain manhole “T’s”, as well as for the alleged sale by Atlas of defective pipe. Subsequently, Au filed a third party complaint against defendant Michigan Testing Engineers seeking damages for the alleged failure by Michigan Testing to properly inspect the pipe in question. The third party complaint aspect was subsequently severed for separate trial and is not involved in this appeal.

Prior to the trial of this ease in 1973, Atlas filed three motions for partial summary judgment seeking to dismiss the counterclaims against it by Au. These motions, which were decided by Judge Roth, were granted, and the counterclaims, as well as certain related defenses of Au, were dismissed. A motion for reconsideration of the foregoing decision was denied on the eve of trial. The case went to trial before Judge Roth in November of 1973. Judge Roth died before rendering a decision.

On March 15,1974, Atlas filed for reorganization pursuant to Chapter X of the Bankruptcy Act. As a related matter, the contract action involved herein was referred by this Court to the Bankruptcy Court for retrial. Pursuant to stipulation of the parties, the Bankruptcy Court made its findings on the basis of the transcript of the proceedings before Judge Roth and limited documentary supplementation of the record.

Before making its findings, the Bankruptcy Court rendered, in substance, two decisions which were later the subject of an interlocutory appeal to this Court. First, the Bankruptcy Court denied Au’s motion to set aside partial summary judgment granted Atlas by Judge Roth. Second, the Bankruptcy Court denied Au’s motion to transfer the action to District Court for lack of subject matter jurisdiction in the Bankruptcy Court. On March 17, 1977, these rulings were affirmed on appeal by this Court.

*833 Subsequently, on June 8, June 22, and October 18 of 1977, the Bankruptcy Court made the Findings of Fact which form the subject of this appeal. On October 18, 1977, judgment was rendered in favor of Atlas in the amount of $525,789.31.

FACTUAL BACKGROUND

In early 1968, the Oakland County Department of Public Works submitted four specific contracts for sewer jobs in Oakland County for bids. Au was the successful bidder on one of these contracts. Atlas, a concrete pipe supplier, prior to the contract bid date, sent certain price information to the various contractors who had obtained copies of the plans, which prices, as it turned out, were 25% higher than those arrived at in the written agreement between the parties. Later, on July 2, 1968, after Au had been awarded the contract, Atlas sent Au a revised price list for the purpose of inviting Au to enter into negotiations to culminate in a contract for the sale of pipe. Significantly, the prices submitted in this list were the prices ultimately agreed upon by the parties in their written contract.

Between July 2 and July 15 of 1968, a meeting took place between representatives of Au and Atlas to discuss the terms of the prospective contract. At this meeting, Au sought and received from Atlas assurance that Atlas could deliver to the job site 600' of pipe per day. On the other hand, Atlas informed Au that, because Atlas was financing its operation primarily on borrowed capital, it would require payment for the pipe by Au within two days after Au had received payment for such by the County.

These considerations, as well as the price list of July 2, 1968, were incorporated into the written contract between the parties entered into on July 15, 1968. That contract had two key provisions which lie at the heart of this appeal:

(1) Atlas was required to supply 600' of pipe per day to the project; and
(2) Au was to pay for the product received within two days after it had been paid by the County.

As it later developed, neither of these provisions were complied with. As both parties concede, had Atlas delivered 600' of pipe per day to the project, Atlas would have completed its supply obligations by January of 1969. The last shipment of pipe, however, was not made until August, 1970. Further, by Au’s own admission, assuming its defenses and counterclaims are without merit as determined by Judge Roth, Au owes Atlas $119,477.47 for pipe delivered by Atlas.

Atlas bases recovery of damages on three basic theories of contractual liability:

(1) Failure of Au to pay Atlas the outstanding open account indebtedness, that is, for all of the pipe delivered, accepted, and installed by Au;
(2) Breach of Au’s implied promise to “call for” or install, the pipe at the rate of 600' per day; and
(3) Consequential damages in the form of interest Atlas had to pay its lenders for working capital needed because of Au’s failure to pay the outstanding open account indebtedness.

The Bankruptcy Court found for Atlas on all of the foregoing theories of liability; as follows:

Open Account Indebtedness $193,148.63
Breach of Implied Promise to install pipe át rate of 600' per day 43,710.95
Consequential Damages - Interest 124.565.69
Subtotal $ 361,485.27

After adding certain items which are not seriously disputed and statutory interest, the Bankruptcy Court rendered judgment for Atlas in the amount of $525,789.31.

ISSUES ON APPEAL

After carefully reading the briefs of the parties, the Court believes the real issues involved herein are as follows:

(1) What is the appropriate standard of review the Court should use to review the findings of the Bankruptcy Court;
(2) Should the findings of the Bankruptcy Court be reversed:
(a) Did the Bankruptcy Court properly compute the outstanding open account indebtedness;
*834 (b) Did the Bankruptcy Court properly find that Au breached an implied promise to install pipe at the rate of 600' per day; if so, did the Bankruptcy Court properly compute damages based upon this breach;
(c) Did the Bankruptcy Court properly allow as consequential damages interest paid by Atlas for working capital required because of Au’s failure to pay the outstanding open account indebtedness;
(3) Should the granting of partial summary judgment to Atlas by Judge Roth be set aside;
(4) Did the Bankruptcy Court have jurisdiction to hear the case; and

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Stokes v. Roberts
711 S.W.2d 757 (Supreme Court of Arkansas, 1986)
MH & H IMPLEMENT, INC. v. Massey-Ferguson, Inc.
702 P.2d 917 (Idaho Court of Appeals, 1985)
Mohammed v. Union Carbide Corp.
606 F. Supp. 252 (E.D. Michigan, 1985)
Ernst Steel Corp. v. Horn Construction Division
104 A.D.2d 55 (Appellate Division of the Supreme Court of New York, 1984)
Thomas v. Turner (In Re Turner)
12 B.R. 497 (N.D. Georgia, 1981)
Cement National Bank v. Colasante (In Re Colasante)
12 B.R. 635 (E.D. Pennsylvania, 1981)
Hollowell v. Career Decisions, Inc
298 N.W.2d 915 (Michigan Court of Appeals, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
467 F. Supp. 830, 26 U.C.C. Rep. Serv. (West) 395, 1979 U.S. Dist. LEXIS 13985, Counsel Stack Legal Research, https://law.counselstack.com/opinion/atlas-concrete-pipe-inc-v-roger-j-au-son-inc-mied-1979.