Atlantic & Pacific Railroad v. Mingus

165 U.S. 413, 17 S. Ct. 348, 41 L. Ed. 770, 1897 U.S. LEXIS 1985
CourtSupreme Court of the United States
DecidedFebruary 15, 1897
Docket100
StatusPublished
Cited by40 cases

This text of 165 U.S. 413 (Atlantic & Pacific Railroad v. Mingus) is published on Counsel Stack Legal Research, covering Supreme Court of the United States primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Atlantic & Pacific Railroad v. Mingus, 165 U.S. 413, 17 S. Ct. 348, 41 L. Ed. 770, 1897 U.S. LEXIS 1985 (1897).

Opinion

Mr. Justice Brown,

after stating the case, delivered the opinion of the court.

While the value of the land involved in this case is small, the question at issue between the parties affects the validity of the entire land grant of the company adjacent to and coterminous with all that part of the main line of the road not completed. on July 6, 1886. - The case turns wholly upon the validity of the act of that date, forfeiting that portion of the land grant.

Plaintiff claims in this connection that the act was invalid, inasmuch as the United States had failed to perform their own .obligations in two particulars: First, that they not only failed to extinguish the Indian title to lands along the prescribed route of the road, but had since further encumbered the grant by the creation of additional Indian reservations, carved out of the granted lands. , Second, that they also largely "failed to survey the lands as required by the sixth section, although repéatedly urged and requested to do só by the railroad' company.

1. The reservéd rights of the United States with respect to this land grant are contained in the eighth, ninth and twentieth sections of the original act, and are as.follows: By § 8 the grant was made subject to the condition that the company ■ should commence work within two years from the approval of the act, and should complete not less than fifty-miles a year after the second year,, and should complete the main line of' *427 the whole road by July 4, 1878. By § 9, a “ further condition ” was imposed: that if the company made any breach of the conditions of the act, and allowed the same to continue for upwards of one year, the United States might do anything which-might be needful and necessary to secure the speedy completion of the road. And by § 20 the general power was reserved to Congress to alter, amend or repeal the act, subject only to á due regard for.the rights of the company.

The position of the plaintiff is .that the rights of the United States were fixed and limited by § 9; that Congress did not intend that the grant should ever be forfeited, but that, upon a breach of any of the conditions, the United States could only take steps itself to insure the speedy completion of the road.

What steps the government could take in that direction, and what the effects of its action upon the land grant might be, it is difficult to decide. It would seem highly inequitable, however, that if the government.were compelled to go on and complete the road at its own expense the company should yet be able to retain the land grant, the condition of which was the completion of the road at its expense. The act makes no provision- whatever for the disposition of the land grant in this'.contingency. What remedy the government would have had in case it had elected itself to go on and complete the road is left entirely to conjecture. Some further action on the part of Congress would seem to have been necessary.

Aside from this difficulty, however, we are clearly of opinion that Congress intended to impose this simply as a “further condition,” consequent upon a breach by the railroad company of its stipulations, and to reserve to the United States the. option of forfeiting the grant entirely, or of taking measures to insure the speedy completion of the road. This further condition was obviously intended for the benefit of the government, and with no. purpose of merging other con- . ditions,' or-of superseding.other remedies to which it might be entitled. While, by the act of July 27, 1866, like other similar acts passed about the same time, it - was doubtless -intended that .the grant should operate m prcesenti% it certainly never could have? befen contemplated, that, in case the *428 company took no steps toward the completion of the road, the government, could not forfeit'the grant,, and, could resort to no other remedy than building the road itself.', It certainly would be highly inequitable as well ns impolitic that the company should retain the land grant and do nothing, toward the construction of the road, or that the lands granted should be permanently avithdrawn from the public domain. A more reasonable interpretation would be to say that Congress contemplated a possibility that the company might proceed in'good faith with the construction of the road, and might so nearly approach its completion that it would be for the best, interests of the government to go on itself and complete it rather than to insist upon an- entire forfeiture of the grant. Even.if § 9 were intended as a limitation upon the. power of Congress, which might otherwise be inferred from § 8,- the power reserved by § 20 to alter, amend or repeal the act,' except so far as its exercise might interfere with the just rights of the company, being the latest- expression of the legislative will, may properly be construed to dominate the others.

But little light is to be gained in the consideration of this question by referring to the conditions for forfeiture or reinvestment of title under other railway land grant acts. There is no such uniformity in the terms of their conditions subsequent as to lead us to give'any different construction to the three sections in question than such as their language plainly requires. It cannot be. supposed'that Congress intended to vest a title in the railway company to this enormous grant of lands without contemplating that the Government might in some way reacquire it in case of a failure of the company to comply with the conditions of the grant. No express provision for a forfeiture was required to fix the rights of the Government. If an estate be granted upon a condition subsequent, no express words of forfeiture or reinvestiture of title are necessary to authorize the grantor to reenter in case of a breach of such conditions. Stanley v. Colt, 5 Wall. 119 ; Mead v. Ballard, 7 Wall. 290; Ruch v. Rock Island, 97 U. S. 693; Hayden v. Stoughton, 5 Pick. 528 ; Jackson v. Allen, 3 Cowen, 220; Gray v. Blanchard, 8 Pick. 283. And the fact that *429 Congress imposed as a further condition the right to complete the road itself, did not deprive it of the power of resorting to other remedies to which the breach of such conditions entitled it.

2. As to the proper construction of the act of April 20,1871. This act, in general terms, authorized the railroad company to make and issue its bonds in such sums as it pleased, and to mortgage its road, etc., to secure them, with a proviso that if the Company should thereafter

Free access — add to your briefcase to read the full text and ask questions with AI

Related

McGirt v. Oklahoma
591 U. S. 894 (Supreme Court, 2020)
Carlson v. Village of Union City, Mich.
601 F. Supp. 801 (W.D. Michigan, 1985)
Collin v. Smith
578 F.2d 1197 (Seventh Circuit, 1978)
Choctaw Nation v. Oklahoma
397 U.S. 620 (Supreme Court, 1970)
Screws v. United States
325 U.S. 91 (Supreme Court, 1945)
People Ex Rel. Kunstman v. Nagano
59 N.E.2d 96 (Illinois Supreme Court, 1945)
Creek Nation v. United States
318 U.S. 629 (Supreme Court, 1943)
United States v. Santa Fe Pacific Railroad
314 U.S. 339 (Supreme Court, 1942)
Bryan County, Okl. v. United States
123 F.2d 782 (Tenth Circuit, 1941)
Horse Creek Conservation District v. Lincoln Land Co.
92 P.2d 572 (Wyoming Supreme Court, 1939)
Public Serv. Comm'n of PR v. Havemeyer
296 U.S. 506 (Supreme Court, 1936)
Oslin v. State
132 S.E. 542 (Supreme Court of Georgia, 1926)
United States v. Oregon & CR Co.
8 F.2d 645 (D. Oregon, 1925)
Webb v. O'BRIEN
263 U.S. 313 (Supreme Court, 1923)
Kern River Co. v. United States
257 U.S. 147 (Supreme Court, 1921)
First Construction Co. v. State
194 A.D. 608 (Appellate Division of the Supreme Court of New York, 1921)
First Construction Co. v. State
110 Misc. 164 (New York State Court of Claims, 1920)
Santa Fe Pacific Railroad v. Lane
244 U.S. 492 (Supreme Court, 1917)

Cite This Page — Counsel Stack

Bluebook (online)
165 U.S. 413, 17 S. Ct. 348, 41 L. Ed. 770, 1897 U.S. LEXIS 1985, Counsel Stack Legal Research, https://law.counselstack.com/opinion/atlantic-pacific-railroad-v-mingus-scotus-1897.