Atlantic Coast Brewing Co. v. Donnelly

35 A. 647, 59 N.J.L. 48, 30 Vroom 48, 1896 N.J. Sup. Ct. LEXIS 76
CourtSupreme Court of New Jersey
DecidedJune 15, 1896
StatusPublished
Cited by3 cases

This text of 35 A. 647 (Atlantic Coast Brewing Co. v. Donnelly) is published on Counsel Stack Legal Research, covering Supreme Court of New Jersey primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Atlantic Coast Brewing Co. v. Donnelly, 35 A. 647, 59 N.J.L. 48, 30 Vroom 48, 1896 N.J. Sup. Ct. LEXIS 76 (N.J. 1896).

Opinion

The opinion of the court was delivered by

Garrison, J.

These four cases arose out of the same transaction and may be considered together, although each case has some feature not common to all. Of the several assignments of error there is one that runs through the entire group and raises this question, viz., whether, under our Mechanics’ Lieu law, where the building is erected under a contract with the owner of the land not on file, a materialman must, in order to have a lien under section 1, show a written consent of the owner, under section 4.

lu the transaction before us the contract was between the Atlantic Coast Brewing Company, owner, and Frank Math, builder. The sixth section was in these words: The owner shall notin any manner be answerable or accountable * * * for any of the materials or other things used and employed in finishing and completing (said building).”

’When this contract was offered in behalf of the plaintiff, who, in each ease, claimed for materials furnished, it w;as objected to upon the ground that "it is so inconsistent with the offer to show that it is a consent to the builder in writing, that it clearly shows that it is not.”

The major premiss in this proposition is that a building erected under a contract with the owner of the land, is a building erected by a person other than the owner of the land. If this be not so, the objection is without force. We think that it is without force. The construction uniformly given to this fourth section of the Lien law, from 1855, when Babbitt v. Condon, 3 Dutcher 154, was decided by this court, down to [50]*501893, when Earl v. Willets, 27 Vroom 334, was decided in the Court of Errors, has been, in the language of the later opinion, that “ it is obvious that a contract, when the building is so erected, must be signed by a person other than the owner of the land. Such a contract must be made by a person other than the owner, else it would be the contract of the owner.”

The matter seems to be entirely at rest.

In the case of the Atlantic Lumber Company, plaintiff, the court was requested to instruct the jury that a certain bond to secure the builder’s contract, from which the plaintiff’s name had been erased, imputed to the plaintiff notice of such contract, and that as the contract provided against liens, the plaintiff was debarred from asserting its lien. The testimony did not establish all of the facts recited in this request so that it could have been charged as a whole. It was therefore not error to deny it. If the substantial question be severed the refusal was still correct. The facts touching the plaintiff’s knowledge of the bond and the time it was acquired, whether before or after the materials were furnished, must in any event be for the jury. So that the plaintiff was not injured unless the bare existence of the waiver of liens in an unfiled contract protects a building from liens. This obviously is not so. The right of lien given by the first section is fixed when materials are furnished, unless it is taken away by section 2. The fact that the builder who made the contract has waived his right does not affect the rights of others. In each case the right is personal and is vested unless personally waived.

There is nothing substantial in the assignment.

In the case of the Phoenix Iron Company, plaintiff, there are two assignments of error based upon a request to charge, and an exception to the charge of the court as delivered. These exceptions tend to raise the question whether a materialman, who has made an entire contract with the builder, may, upon the failure of the builder to make the payments called for by each contract, refuse to complete it and lien the building for the material actually delivered as on a quantum [51]*51valebat. The assignment, however, does not call for decision of this question.

The jury were correctly instructed by the trial court, that the right of the plaintiff to a lien for materials furnished the building under an entire contract, depended upon whether the contract had been lawfully rescinded by the parties thereto. This was left to the jury, although the testimony upon this .point was practically undisputed. There was no occasion for charging an abstract proposition of law, unsupported by .adequate proof.

The case of Joseph C. Clement, plaintiff, presents a somewhat novel question. Math, the builder, had given a bond to the owner for the faithful performance of his contract. Clement was one of the sureties on this bond. The condition of the bond was that Math should “ indemnify and save harmless the owner from all claims, demands, suits and' actions, * * * and should keep the said building and lot free from encumbrance and lien of any and all debts, and furnish -complete release of liens.” Clement- furnished materials for the building, for which he filed a lien. The contention of ■the owner is that Clement, by executing the bond as surety, barred his own right to lien the building.

The bond was put in evidence incidentally—almost accidentally—since the fact of its mechanical attachment to the contract seems to have been its only relevancy to the plaintiff’s case at- the time it was impliedly offered. Its introduction was opposed by the defendant below, who now seeks to make •the case turn upon its controlling import. After the issue raised by the pleadings had been tried, the defendant asked “that a binding instruction be given the jury to find that the debt is not a lien, for the reason that the plaintiff has undertaken, in a bond, that there shall be no lien as per' the terms •of the bond itself offered in evidence.” The refusal of this request is the point upon which a reversal of the judgment is now sought.

It will be seen that the proposition is presented in a mode .ill-adapted to its proper consideration. If true, it constituted [52]*52a complete defence, yet it was not pleaded. It falls to the-ground if there was any material alteration in the contract without the assent of the surety, yet no opportunity for a replication was afforded. A demurrer to such a plea, or a joinder to such a reply, would have presented an issue capable of definite disposition. As the case stands, the question upon which it turns does not appear upon the record, and its adjudication will not be within any issue the parties set out to try or that in point of fact they did try. The defence is clearly not estoppel, for the issue concerned a transaction in which the obligee took no part; it is not a waiver, because the plaintiff’s agreement was of a secondary character, resting upon no direct consideration. At bottom, the defence is that it would be circuitous, and hence oppressive, to permit the surety on the contractor’s bond to proceed with a lien after the enforcement of which the obligee would be compelled to-sue on the bond in order to get back the money recovered on the lien.

The “ vigilance and jealousy ” with which the law “ favors-a surety and protects him ” (De Colyar, p. 277), would be a very empty phrase if his legal liability may be enlarged upon the ground that it is inequitable to limit it by the express-terms of his undertaking.

Avoidance of circuity of action is at best a doctrine of convenience, a secondary equity, so to speak, and not to be resorted to in the face of either legal rule or substantial right.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

General Electric Co. v. E. Fred Sulzer and Co.
207 A.2d 346 (New Jersey Superior Court App Division, 1965)
Stewart Contracting Co. v. Trenton & New Brunswick Railroad
60 A. 405 (Supreme Court of New Jersey, 1905)
Bates Machine Co. v. Trenton & New Brunswick Railroad
58 A. 935 (Supreme Court of New Jersey, 1904)

Cite This Page — Counsel Stack

Bluebook (online)
35 A. 647, 59 N.J.L. 48, 30 Vroom 48, 1896 N.J. Sup. Ct. LEXIS 76, Counsel Stack Legal Research, https://law.counselstack.com/opinion/atlantic-coast-brewing-co-v-donnelly-nj-1896.