Atlanta Gas Light Co. v. Federal Energy Regulatory Commission

756 F.2d 191, 244 U.S. App. D.C. 170
CourtCourt of Appeals for the D.C. Circuit
DecidedMarch 15, 1985
DocketNo. 82-2231
StatusPublished
Cited by1 cases

This text of 756 F.2d 191 (Atlanta Gas Light Co. v. Federal Energy Regulatory Commission) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Atlanta Gas Light Co. v. Federal Energy Regulatory Commission, 756 F.2d 191, 244 U.S. App. D.C. 170 (D.C. Cir. 1985).

Opinion

Opinion for the Court filed by Circuit Judge SCALIA.

SCALIA, Circuit Judge.

Atlanta Gas Light Company petitions under 15 U.S.C. § 3416(a)(4) for review of a Federal Energy Regulatory Commission order approving the curtailment plan of Southern Natural Gas Company — that is, its plan for distributing gas among its customers in times when it is unable to acquire sufficient supplies to cover all their orders. The. principal issue on appeal is whether the portion of the plan limiting the preferential claim of statutorily prescribed priority users to the volume of gas which they had contracted for an absolute right to receive (“contract demand" gas) is consistent with Title IV of the Natural Gas Policy Act of 1978 (“NGPA”), 15 U.S.C. §§ 3391-3394 (1982), and with Commission regulations.

I

In 1973, Southern Natural Gas Company (“Southern”) submitted to the Commission 1 a curtailment plan for its interstate pipeline system. The Commission approved an interim, modified version of the plan in its Opinion No. 747, Southern Natural Gas Co., Docket Nos. RP74-6 and RP72-74, Opinion and Order Prescribing Interim Curtailment Plan, 54 F.P.C. 2298 (1975). This version included a provision— encompassed in § 9.7(1) of Southern’s tariff — that limited the noncurtailable requirements of certain of Southern’s priority customers to contract demand. Contract demand (“CD”) is that quantity of gas which a customer has an unqualified contractual right (generally accompanied by a minimum contractual obligation) to purchase. It generally comes at a higher cost per unit volume than its opposite, authorized overrun (“AO”) gas, which a customer may elect to purchase and the pipeline is contractually bound to deliver only if and when available.

While court review of Opinion No. 747 (and of an opinion granting in part and denying in part rehearing, Opinion No. 747-B, Southern Natural Gas Co., Docket Nos., RP74-6 and RP72-74, Opinion and Order Granting Rehearing in Part and Denying Rehearing in Part, 55 F.P.C. 2358 (1976)) was pending, the parties, including all parties to the present action, reached a settlement adopting a permanent curtailment plan. The settlement restricted the application of the contract demand limitation to days when the forecast mean temperature fell to 48° F or below.2 The Commission approved the settlement. Opinion No. 5, Southern Natural Gas Co., Docket Nos. RP74-6 and RP72-74, Opinion and Order Approving Settlement Prescribing Permanent Curtailment Plan, 1 F.E.R.C. (CCH) ¶ 61,144 (1977).

One year later, Congress adopted the NGPA, Pub.L. No. 95-621, 92 Stat. 3351 (codified as amended at 15 U.S.C. §§ 3301-3432 (1982)). Section 401 of the Act provides for an “end-use” priority distribution [173]*173scheme under which several categories of users — primarily residential, small commercial, and essential agricultural users — receive preferential treatment in the event of gas shortages.3 In Orders Nos. 29 and 29-C, the Commission adopted regulations implementing this section of the NGPA. Order No. 29, FERC Statutes and Regulations (CCH) ¶ 30,053 (1979) (Final Regulation for the Implementation of Section 401 of the NGPA); Order No. 29-C, FERC Statutes and Regulations (CCH) ¶ 30,092 (1979) (Final Amending Regulation for the Implementation of Section 401 of the NGPA). The regulation at issue here provides that “[a]ll deliveries to all customers of the interstate pipeline for all volumes of natural gas not included in priorities 1 and 2 shall be fully curtailed by the interstate pipeline before priorities 1 and 2 entitlements are curtailed.” 18 C.F.R. § 281.-205(b) (1984).4 The Commission also directed interstate pipelines to file tariff sheets bringing their curtailment plans into conformity with the Commission’s rules. 18 C.F.R. § 281.204(a).

On October 2, 1979, Southern responded by filing proposed tariffs in Commission Docket No. TC80-26. The proposed tariffs modified Southern’s index of requirements to correspond to the new NGPA categories, but made no change in § 9.7(1). Atlanta Gas Light Company (“Atlanta”) protested Southern’s filing, arguing that it violated § 401 of the NGPA and Commission Orders No. 29 and No. 29-C. On October 31, 1979, the Commission accepted Southern’s tariff sheets for filing, suspended them for five months, and ordered an expedited hearing. At the same time, the Commission noted that Southern had the option of seeking special relief pursuant to § 502(c) of the NGPA, 15 U.S.C. § 3412(c), which allows adjustment “as may be necessary to prevent special hardship, inequity, or an unfair distribution of burdens.”

While not conceding that its filing was inconsistent with the Order No. 29 series, Southern thereafter withdrew the proposed tariffs and filed an adjustment application for special relief with the Director of the Office of Pipeline and Producer Regulation (“OPPR”), requesting that the same tariff [174]*174sheets be permitted to become effective. In May 1980, the Director of OPPR issued an order granting Southern special relief on the ground that while § 9.7(1) could result in gas deliveries to certain lower priority users in preference to higher priority users in violation of Order No. 29, any modification of the section would be unfair and reopen the years of litigation that resulted in the Opinion No. 5 settlement. Southern Natural Gas Co., Docket No. SA80-59, Order of the Director, Office of Pipeline and Producer Regulation, Granting Adjustment, 11 F.E.R.C. (CCH) II 62,124 (1980).

Atlanta and two other parties took an administrative appeal from the Director’s order. In the meantime, the Commission permitted Southern’s proposed tariff sheets to become effective. On September 23, 1981, after a two-day evidentiary hearing, the presiding officer found that the Director's order granting special relief was based on the erroneous assumption that § 9.7(1) was inconsistent with Order No. 29- Southern Natural Gas Co., Docket No. SA80-59, Proposed Order of Presiding Officer, 16 F.E.R.C. (CCH) ¶ 62,615 (1981) (“Proposed Order”). The presiding officer concluded instead that the priority entitlements designated by the Commission were protected only within a distributor’s contract demand.

Following the filing of comments by interested parties, the Commission, on July 16, 1982, affirmed and adopted the proposed order of the presiding officer. Southern Natural Gas Co., Docket No. SA80-59, Order Affirming and Adopting Proposed Order of Presiding Officer, 20 F.E.R.C. (CCH) 1161,056 (1982) (“Commission Order”). The Commission specifically affirmed the presiding officer’s finding that Order No. 29 simply required a pipeline to service high priority and essential agricultural requirements up to contract limitations. It also held that changes in Southern’s index of requirements did not require modification or elimination of § 9.7(1).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
756 F.2d 191, 244 U.S. App. D.C. 170, Counsel Stack Legal Research, https://law.counselstack.com/opinion/atlanta-gas-light-co-v-federal-energy-regulatory-commission-cadc-1985.