Hallett, J.

In the month of April, 1890, a freight train was wrecked at or near Salt river, in Macon county, Mo., on a line of railroad owned and operated by the plaintiff in error. In the evening of the same day a large force of men was assembled at the wreck for the purpose of clearing the track and repairing it as speedily as possible. These men were employes of the company, of various occupations, collected from the line of the road. It was not the practice of the company to keep men for the business of removing wrecks, but in such an emergency men were called from all branches of the service as occasion might demand. For the most part they were section-men, and with them came the division superintendent of the road, William E. Costello, the road-master, Charles A. Lehman, and the train-master, William B. Scott. It is not clear whether any of these officers had general supervision of the entire force and of all the work to be done at that time and place; and, in the view w'o take of the case, it is not important to determine that question. It is enough to note the fact, clearly established by the evidence, that in repairing the track, or reconstructing it in a manner to be presently noticed, the work was under the supervision of the road-master, Charles A. Lehman, who was present and attending to that duty. Circumstances were not favorable to the work in hand. Rain had been falling for several days, and was still falling, and the ground was very wet, soft, and muddy. The work could not be-completed in daylight, and it was necessary to carry it on through the night, with the aid of lanterns and bonfires, as might be possible under a wet sky. The place of the wreck was a high embankment or fill, 20 feet or more above the level of the adjacent land, and the borrow-pits below held more or less water. The width of the embankment was not much greater than the track, so that there was not much room for building a temporary track around the wreckage, or removing the old track to accomplish the same thing. The general course [59]*59of the road at that place is east and west, and about 180 feel of track west of the bridge over Salt river was displaced and torn up. Upon looking over the ground, and considering the work to be done, Lehman decided to move the track two feet south of its original position on the embankment. In doing this, part of the wreckage would lie avoided, and the remainder would have to bo removed as the work-progressed. To tins work Lehman appointed Eaton, foreman of section 14, and gave bis personal attention to other matters; but be says he returned twice or three times during the night “to see how the track was being repaired, and if everything was safe.” The work of relaying the track in this manner was carried on through the greater part of the night, until at length some trucks from a freight-car were found lying across the north rail of the original track, which it was necessary to remove. After several unsuccessful efforts to remove them, Costello, division superintendent, came upon the ground and suggested to McCormick the use of the derrick or wrecking-car. McCormick had been trying to remove the trucks by means of a cabio attached to a locomotive, and with men using crow-bars and possibly other appliances. He described himself as “car-repairer and wrecker-inspector,” and he had been for some time in charge of the derrick or wrecking-car used on this occasion. .More than any other person on the grouud ho seems to have had some special duties, in connection with his car, in the removal of wrecks; but lie had not, so far as shown in this record, more than one man in his charge, and up to that time, on this occasion, be had worked with his own hands in common with other employes of the company. He was superior to the others only' in his knowledge of the use of the wrecking-car, and in having charge of it when it was in action. McCormick assented to the use of the wrecking-car, and it was brought up for the purpose of removing the trucks. It then stood on the last rails of the now track laid by Eaton, which at this point wore about 12 or 15 inches south of the rails of the old track. The trucks which were to be removed were partly on the northerly side of the new and old tracks, but in front of the wrecking-car. The plan was to raise them sufliciontly so that they could be moved south of both tracks when suspended on the swinging boom of the derrick. For that purpose several men were called to assist McCormick in pushing the trucks to the south, when they should be lifted above the tracks with the aid of the derrick. Other men mounted the ear, by Costello’s command, for the purpose of working the derrick, and in due time the trucks were elevated above the tracks, as was proposed. But, contrary to all expectation, McCormick and the men who had hold of the trucks were unable to control them, and the trucks went north rather than south; the wrecking-car was overturned; and James W. Wilson, one of the men employed in working the derrick, fell under the trucks of that car and was killed. Wilson was a sectionmau from section 14, and his foreman was Asbury Eaton. Tisis action was brought by his widow7, upon a statute of the state of Missouri, (Rev. St. § 4425 et seq.,) to recover damages resulting to her from his death, and she had judgment in the circuit court.

[60]*60Referring, now, to the acts of negligence charged in the complaint, and the evidence at the trial on that subject, the prominent question of fact in the case is the condition of the new track on which the wrecking-car stood at the time of the casualty, and whether it was well built. Several witnesses testify that immediately after the car was overturned the north rail was observed to be two to four inches lower than the south rail, and those who deny the statement seem not to have given much attention to the matter. If such was the fact, it may have been due to carelessness in construction in placing the rails in that position, or to the sinking of the north rail under the weight of the wrecking-car.' In the latter case, the result would indicate that the rails were not adequately supported by ties. One witness testifies that only three ties were laid under each rail; others say four to six were laid; and still others give varying numbers, up to ten or twelve.

Whether the north rail was first laid lower than the other, or sunk in the mud under the wrecking-car, if in fact it was lower than the other immediately after the casualty, it was obviously a fault in construction. The track was straight at that point, and therefore there was no reason for placing one rail higher than the other, as is usual on curves. It is to be observed, also, that the new track was not intended for temporary use in removing the wreckage only, but was for the general traffic of the road during the following day, and j>erhaps longer. Under all the circumstances prevailing at the time, the duty of the company to restore the track as speedily as possible, and for that purpose to go on with the work at night, through rain and mud, no one will contend that the company should be held to the same care in building its track as would be demanded under more favorable conditions. Nevertheless, some care was necessary to make a track adequate to the support and safe passage of trains, not alone in the interest of the public, who were using the road extensively, but also in the interest of the employes of the company who should be sent over the road. With certain well-understood qualifications, which it is not necessary to define in this connection, a servant is as fully entitled to a safe track as any traveler over the road.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Blunt v. Chicago, R.I. P. Ry. Co.
1918 OK 362 (Supreme Court of Oklahoma, 1918)
Bennett v. Southern Railway
79 S.E. 710 (Supreme Court of South Carolina, 1913)
Northern Pac. R. v. Poirier
67 F. 881 (Ninth Circuit, 1895)

Cite This Page — Counsel Stack

Bluebook (online)
48 F. 57, Counsel Stack Legal Research, https://law.counselstack.com/opinion/atchison-t-s-f-r-v-wilson-ca8-1891.