Associated Electric & Gas Insurance Services v. BendTec, Inc.

822 F.3d 420, 2016 WL 2772595
CourtCourt of Appeals for the Eighth Circuit
DecidedMay 13, 2016
Docket15-2596, 15-2598
StatusPublished
Cited by5 cases

This text of 822 F.3d 420 (Associated Electric & Gas Insurance Services v. BendTec, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Associated Electric & Gas Insurance Services v. BendTec, Inc., 822 F.3d 420, 2016 WL 2772595 (8th Cir. 2016).

Opinion

MURPHY, Circuit Judge.

The Public Service Company of New Hampshire hired Siemens to replace a turbine in one of its power plants. BendTec, Inc. manufactured steam pipes for the new turbine as a subcontractor for Siemens. After the turbine was turned on, it became damaged by fine grit. The utility and its insurers sued BendTec for negligence, alleging that its pipes were the source of the grit and had been improperly cleaned. The district court 1 granted summary judgment to BendTec, concluding that the negligence claim was barred under the two year limitations period in Minn.Stat. § 541.051 since the installation of the turbine was an improvement to real property. The utility and insurance companies appeal, and we now affirm.

I.

Public Service Company of New Hampshire (PSCNH) operates a coal power plant in Bow, New Hampshire. The “Merrimack Station” power plant has two generating units each consisting of a coal fired boiler and a turbine generator. Unit 2 was built in 1968, and PSCNH decided to upgrade it in 2006 by purchasing a new 340 megawatt turbine from Siemens Power Generation. Siemens was to be the supplier of the new generator rotor and turbine, and it also agreed to procure the manufacture, supply, and installation of all necessary components. Siemens warranted that all equipment, materials, and supplies furnished by or through it would be free from defects. The new turbine was installed by Siemens in the spring of 2008.

“Turbine piping” carries high pressure steam from the boiler to the turbine. Siemens had selected BendTec as the subcontractor to fabricate to its specifications the turbine piping for the new PSCNH turbine. The piping consists of twenty one sections of large pipe which are transported by flatbed truck and moved using cranes. BendTec cleaned the interior of the piping using abrasive grit blasting, a process which involves spraying steel grit at the piping under high pressure. It then conducted a visual inspection of the pipes, capped them, and shipped them to the Merrimack Station. The piping was delivered on April 8, 2008 and installed by Siemens. After shipping the pipes, Bend-Tec had no further involvement with the project.

On May 22, 2008 PSCNH started the turbine for the first time. Power output was lower than expected, and eventually the turbine was shut down and an inspection revealed steel grit blast material *423 throughout the turbine. PSCNH’s experts determined that the grit had been blown into the turbine by high pressure steam and opined that the foreign material was left over from BendTee’s cleaning process. The turbine was cleaned and turned back on. Eventually PSCNH replaced the turbine blades and other components which had been damaged.

On May 21, 2014 PSCNH’s agent Northeast Utilities Service Company, along with Associated Electric and Gas Insurance Services, Zurich American Insurance Company, and Energy Insurance Mutual Limited, the insurers and subro-gees of Northeast Utilities Service Company (collectively, “plaintiffs”), sued BendTec for negligence. The district court granted, summary judgment to BendTec, concluding that the plaintiffs’ claim was barred under the applicable statute of limitations. The plaintiffs appeal.

II.

We review a grant of summary judgment de novo. Woods v. DaimlerChrysler Corp., 409 F.3d 984, 990 (8th Cir.2005). Summary judgment is appropriate if there are no genuine issues of material fact when the record is viewed in the light most favorable to the nonmoving party, and the moving party is entitled to judgment as a matter of law. Id.; see Fed.R.Civ.P. 56. We apply Minnesota law in this diversity case. In doing so we are bound by the decisions of the Minnesota Supreme Court. Badrawi v. Wells Fargo Home Mortg., Inc., 718 F.3d 756, 758 (8th Cir.2013). If that court has not ruled on a particular issue, we consider what rule it would likely apply. Id. Decisions of the Minnesota Court of Appeals are not binding on us but may be instructive. Doe v. Baxter Healthcare Corp., 380 F.3d 399, 407 (8th Cir.2004); Aerotronics, Inc. v. Pneumo Abex Corp., 62 F.3d 1053, 1068 (8th Cir.1995).

Minnesota has a two year statute of limitations for contract and tort claims “arising out of the defective and unsafe condition of an improvement to real property” and “brought against any person performing or furnishing the design, planning, supervision, materials, or observation of construction or construction of the improvement to real property.” Minn.Stat. § 541.051, subd. 1(a). The statute contains an exception however for “the manufacturer or supplier of any equipment or machinery installed upon real property.” Id. subd. 1(e). If the exception applies, negligence claims against a manufacturer or supplier are subject to 'a six year statute of limitations. See Minn.Stat. § 541.05, subd. 1(5).

The questions presented here are whether the turbine piping installed on the new turbine at the Merrimack Station was an “improvement to real property,” and if so, whether BendTec fits the subdivision 1(e) exception for a manufacturer or supplier of equipment or machinery.

A.

The Minnesota Supreme Court has said that courts should use a “common-sense interpretation” of the phrase “improvement to real property” under section 541.051, defining such an improvement as

[A] permanent addition to or betterment of real property that enhances its capital value and that involves the expenditure of labor or money and is designed to make the property more useful or valuable as distinguished from ordinary repairs.

Lietz v. N. States Power Co., 718 N.W.2d 865, 869 (Minn.2006); see also Kloster-Madsen, Inc. v. Tafi’s, Inc., 303 Minn. 59, 226 N.W.2d 603, 607 (1975) (same) (quoting *424 Webster’s Third New International Dictionary 1138 (1971)).

The installation of the new turbine at Merrimack Station, at a total cost of over $12 million, meets each qf the three main factors used by Minnesota courts to ascertain whether something is an improvement to real property. See Siewert v. N. States Power Co., 793 N.W.2d 272, 287 (Minn.2011). The turbine is a “permanent addition” to the power plant. See id. The installation of the turbine involved large expenditures of labor and money. See id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
822 F.3d 420, 2016 WL 2772595, Counsel Stack Legal Research, https://law.counselstack.com/opinion/associated-electric-gas-insurance-services-v-bendtec-inc-ca8-2016.