Associated Builders & Contractors of Rhode Island, Inc. v. Department of Administration

787 A.2d 1179, 2002 R.I. LEXIS 1, 170 L.R.R.M. (BNA) 2054, 2002 WL 21815
CourtSupreme Court of Rhode Island
DecidedJanuary 4, 2002
Docket2001-40-Appeal, 2000-514-M.P.
StatusPublished
Cited by23 cases

This text of 787 A.2d 1179 (Associated Builders & Contractors of Rhode Island, Inc. v. Department of Administration) is published on Counsel Stack Legal Research, covering Supreme Court of Rhode Island primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Associated Builders & Contractors of Rhode Island, Inc. v. Department of Administration, 787 A.2d 1179, 2002 R.I. LEXIS 1, 170 L.R.R.M. (BNA) 2054, 2002 WL 21815 (R.I. 2002).

Opinion

OPINION

LEDERBERG, J.

The contest over whether Rhode Island’s competitive bidding statute barred project labor agreements (PLAs) in public construction contracts was engaged well before the convocation center and ice facility opened to official events at the University of Rhode Island. Generally speaking, a PLA is a prehire collective bargaining agreement between an owner and labor unions involving a specific construction project. As a condition for accepting work on the project, contractors are required to execute the agreement and abide by its terms.

In our opinion, the State Purchases Chapter, G.L.1956 chapter 2 of title 37 (state purchases act or statute) does not specifically permit, nor does it prohibit PLAs. Under the state purchases act, decisions made by the awarding authority are entitled to a presumption of correctness and, accordingly, are given great deference by this Court. But given the presumptively anticompetitive nature of such agreements, the state, before adopting a PLA in a contract, must demonstrate that (1) the size and complexity of the project are such that a PLA supports the objectives of the state purchases act, and (2) the chief purchasing officer or purchasing agency has performed an objective, reasoned evaluation demonstrating that the adoption of a PLA furthers statutory goals. This requirement, however, does not affect the existing authority of the purchasing officer to make bidding process decisions otherwise held and authorized pursuant to the state purchases act. The case reached this Court following the consolidation of the state’s petition for certiorari and its appeal of a Superior Court judgment granting declaratory and injunctive relief, thereby halting the state’s use of a PLA.

Facts and Procedural History

This litigation arose in the course of construction of a 200,000-square-foot convocation center and a 65,877-square-foot ice facility (collectively, the project) on the Kingston campus of the University of Rhode Island (URI). The total cost of the project was estimated at $73,000,000, including $53,000,000 in construction costs, to be funded from revenue bonds, state appropriations, fundraising, and donations. The project is one of several currently underway or in the planning stages at URI, totaling approximately $80,000,000. Because the new facilities will become part of the URI campus, title to the project is held by the State of Rhode Island Board of Governors for Higher Education, thereby bringing the project under the purview of the state purchases act.

The state engaged a private company, Gilbane Building Company (Gilbane), to act as program manager for the project. Following Gilbane’s recommendation, the state adopted a multiple bid package approach for the project, instead of using one or two general contracting packages. Although Gilbane conducted a study, entitled “The Benefits of a Multiple Bid Package Approach for the University of Rhode Island Convocation Center and Ice Arena,” the study made no mention of PLAs. The trial justice found that the state’s purposes in adopting multiple bid packages were:

*1182 “1) Saving the State a significant amount of money.
“2) Expediting the schedule completion date.
“3) Maximizing the State’s opportunity to control costs.
“4) Maximizing the opportunity for local participation.
“And, finally:
“5) Providing the State better control over the selections of the most qualified subcontractors.”

The project was divided into thirty-four bid packages, six of which were awarded before the round of bid solicitations at issue here. 1 These first six bid packages contained no PLA requirement.

In the spring of 1999, Lawrence Bacher, project manager for Gilbane, first suggested to Paul DePace, the associate director of capital projects at URI, that a PLA might be appropriate for the project. At that time, DePace did not pursue the idea further, in part because there were no state purchasing regulations on the subject. Robert Carl, Ph.D., Director of the Rhode Island Department of Administration (state or defendant), who serves as chief purchasing officer for the State of Rhode Island, testified that he presumed from his first knowledge of the project that it “would be appropriate for a PLA.” By the fall of 1999, the state was considering amending the state purchasing regulations to include provisions for the use of PLAs in public contracts, an amendment that apparently was not made.

In his decision, the trial justice found that the initiative to use a PLA on the convocation center project was “on-again and off-again” until, “following a flurry of meetings” in the fall of 2000, a PLA for the project (URI PLA) was negotiated and signed. The trial justice further found that from the summer of 2000 onward, the Department of Administration, URI, and Gilbane all endorsed the concept of a PLA, their only hesitation stemming from a fear of legal challenges and possible consequent delays and from the fact that work was already underway without a PLA in place. The trial justice noted that “a number of the collective bargaining agreements involved in connection with various crafts that will be working on this project by their terms expire during the anticipated construction schedule for the Project.”

The dispute underlying the instant litigation arose in connection with a round of bid solicitations issued in November 2000, involving fourteen individual bid packages, each issued with the URI PLA attached. 2 Each bid solicitation stated:

“Bidders are advised that execution of this Project Labor Agreement, that is completion and signature by an authorized agent of the successful bidder, shall be a pre-requisite to contract award. Note carefully that the attached [PLA] is an integral part of the bid specifications and that the fully executed [PLA] should be included in the bid submission.” (Bold in original.)

The solicitations also required that bidders submit “Bid security in the form of a Bid *? Bond * * * in the amount of a sum no less than 5 percent of the Bid Price” and required that sealed bids be submitted by December 12, 2000, the opening date. The solicitations warned that a successful bidder that failed to commence work or provide the required bonds would forfeit the security up to the amount of the difference between its bid and the bid upon which a contract was eventually signed.

The URI PLA itself was a product of negotiations among the state, Gilbane, and the Rhode Island Building and Construction Trades Council (building trades) “on behalf of its affiliated Local unions” (unions). 3 Article I, section 2, of the URI PLA, setting forth the purpose of the agreement, provided in part:

“The timely and successful completion of the Project is of vital importance to the State. Therefore, it is essential that the construction work be done in an efficient and economical manner in order to secure optimum productivity and eliminate any delays in the work.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Horsfield Materials, Inc. v. City of Dyersville
834 N.W.2d 444 (Supreme Court of Iowa, 2013)
Harodite Industries, Inc. v. Warren Electric Corp.
24 A.3d 514 (Supreme Court of Rhode Island, 2011)
RBS Citizens Bank, N.A. v. Issler
21 A.3d 293 (Supreme Court of Rhode Island, 2011)
Watson v. Murphy
Superior Court of Rhode Island, 2009
A.F. Lusi, Inc. v. R.I. Dept. of Admin.
Superior Court of Rhode Island, 2008
Greensleeves, Inc. v. Smiley
942 A.2d 284 (Supreme Court of Rhode Island, 2007)
Heritage Healthcare Serv. v. Marques, Pb
Superior Court of Rhode Island, 2007
A.F. Lusi Constr. v. Rhode Island Dept.
Superior Court of Rhode Island, 2007
Duffy v. Milder
896 A.2d 27 (Supreme Court of Rhode Island, 2006)
Andrade v. Perry
863 A.2d 1272 (Supreme Court of Rhode Island, 2004)
Lajayi v. Fafiyebi
860 A.2d 680 (Supreme Court of Rhode Island, 2004)
D'Amico v. Morris, 04-123 (2004)
Superior Court of Rhode Island, 2004
Richards v. Halder
853 A.2d 1206 (Supreme Court of Rhode Island, 2004)
Anjoorian v. Kilberg
836 A.2d 1092 (Supreme Court of Rhode Island, 2003)
Direct Action for Rights & Equality v. Gannon
819 A.2d 651 (Supreme Court of Rhode Island, 2003)
Feeney v. Napolitano
825 A.2d 1 (Supreme Court of Rhode Island, 2003)
Master Builders of Iowa, Inc. v. Polk County
653 N.W.2d 382 (Supreme Court of Iowa, 2002)
DeBourgknecht v. Rossi
798 A.2d 934 (Supreme Court of Rhode Island, 2002)
Perry v. Garey
799 A.2d 1018 (Supreme Court of Rhode Island, 2002)

Cite This Page — Counsel Stack

Bluebook (online)
787 A.2d 1179, 2002 R.I. LEXIS 1, 170 L.R.R.M. (BNA) 2054, 2002 WL 21815, Counsel Stack Legal Research, https://law.counselstack.com/opinion/associated-builders-contractors-of-rhode-island-inc-v-department-of-ri-2002.