Assicurazioni Generali S.P.A. v. Black & Veatch Corp.

362 F.3d 1108, 2004 A.M.C. 773, 2004 U.S. App. LEXIS 5681, 2004 WL 594113
CourtCourt of Appeals for the Eighth Circuit
DecidedMarch 26, 2004
Docket03-1431
StatusPublished
Cited by6 cases

This text of 362 F.3d 1108 (Assicurazioni Generali S.P.A. v. Black & Veatch Corp.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Assicurazioni Generali S.P.A. v. Black & Veatch Corp., 362 F.3d 1108, 2004 A.M.C. 773, 2004 U.S. App. LEXIS 5681, 2004 WL 594113 (8th Cir. 2004).

Opinion

COLLOTON, Circuit Judge.

Appellants, members of a syndicate of underwriters, appeal the district court’s 1 entry of summary judgment in favor of appellees on claims for coverage under a maritime insurance policy. We affirm.

*1110 I.

Appellee MEP Pleasant Hill, LLC (“MEP”) contracted with appellee Black & Veatch Corporation (“Black & Veatch”) (jointly, “Appellees”) to design, procure equipment for, and build a combined-cycle electricity generating facility near Pleasant Hill, Missouri. This construction effort was referred to as the Aries Project.

Black & Veatch contracted with Toshiba to manufacture Heat Recovery Steam Generators (“HRSGs”) for the Aries Project. HRSGs are boilers that convert waste heat from gas turbines into processed steam for combined-cycle electrical generation. The components comprising the HRSGs were to be shipped by Toshiba from its facilities in Japan to the United States.

Appellants are members of a syndicate of underwriters at Lloyd’s of London (collectively, “Underwriters”). Black & Veatch, through a broker, procured a policy for marine cargo insurance from the Underwriters. The policy offered two types of coverage. Section I provided, among other things, physical loss coverage for the transport of “equipment, machinery, supplies and materials.” Section II included coverage for delay-in-start-up losses and for expenditures incurred to avoid or diminish such losses.

The parties agree that the policy established a “facility” or framework for insurance coverage, and that the facility did not, by itself, provide coverage for specific projects. Instead, the risk for a project was added to the facility by way of declaration (or endorsement). Consequential loss coverage under Section II was available only in conjunction with projects selected for physical loss coverage under Section I, and only if the Underwriters specifically agreed to accept the risk on a project-by-project basis.

As an apparent means of managing the risk of consequential loss, Section II provided that certain “critical items” (presumably cargo) must be surveyed. The facility does not define “critical item.” Section II provides: “Warranted critical items to be surveyed by LSA [London Salvage Association] or their appointees, or surveyors to be approved by Underwriters — as per warranty wording attached.”

The attached “Survey Warranty Wording” states (with emphasis added):

Warranted the Salvage Association or its appointee, at the Assured’s expense, shall in respect of the items listed below:-
1. Approve vessel(s), tug(s), barge(s), towing arrangements, all other carrying conveyances and all lifting equipment including cranes required or loadinghmloading operations.
2. Approve all packing, loading, stowage, securing and unloading arrangements.
3. Attend and approve all stages of handling during the transportation.
4. Approve all transport operations including transport to vessel, voyage arrangements and transport from vessel to site.
5. Approve prevailing weather conditions or stipulate acceptable weather criteria for handling and transit operations.
And all recommendations complied with.
List of items: (If necessary to be listed on a separate schedule).
The Salvage Association to be, advised of shipping schedules and any amendments and given all reasonable notice of required attendances in order that the above warranties can be complied with.
Underwriters shall be entitled to receive any advices, reports or recommendations from The Salvage Association and/or its appointed surveyor.

*1111 No items were “listed below” in the Survey Warranty Wording, and no other document appended to the policy was denominated specifically a “separate schedule” of critical items.

Endorsement 5 added the Aries Project to the facility “in respect of marine cargo and consequential loss insurance cover.” Endorsement 6 amended certain wording of the policy relating to the Aries Project. Both Endorsement 5 and Endorsement 6 include an effective date of April 18, 2000.

On July 20, 2000, a ship carrying certain HRSG components departed Japan for the United States. No survey had been conducted. On July 24, 2000, the ship was caught in a typhoon, which caused severe damage to most of the HRSG components on board.

Toshiba replaced the damaged HRSG components at no cost to Appellees. However, the replacements did not arrive at the Aries Project site until approximately six months after the originally scheduled delivery date. In anticipation of this delay, Black & Veatch changed the construction sequencing and employed additional labor and management in an effort to avoid delay in the start-up of the plant. As a result of these efforts, the deadline for completing the plant was met. Black & Veatch states that these efforts resulted in additional costs of $38 million for Appel-lees.

Black & Veatch and MEP submitted claims to the Underwriters for consequential damages and the expenses incurred to avoid the delay in start-up. The Underwriters denied the claims on the basis that no survey had been conducted.

The Underwriters filed a complaint in the district court seeking a declaration that the policy provided no coverage because of Appellees’ failure to comply with the survey requirement. Appellees each filed counterclaims requesting a declaratory judgment that their losses were covered under the policy. The parties filed cross-motions for summary judgment on the question whether the Underwriters were liable under the policy. The district court ruled that no survey was required, and that the claims were covered under Section II of'the policy. "This interlocutory appeal followed pursuant to 28 U.S.C. § 1292(a)(3).

II.

This court reviews a district court’s grant of summary judgment de novo. We also review de novo a district court’s interpretation of an insurance policy, which is a question of law for the court. E.g., United Fire & Cas. Co. v. Gravette, 182 F.3d 649, 654 (8th Cir.1999). Disputes arising under marine insurance contracts are governed by state law, unless an established federal admiralty rule addresses the issue raised. Wilburn Boat Co. v. Fireman’s Fund Ins. Co., 348 U.S. 310, 316-21, 75 S.Ct. 368, 99 L.Ed. 337 (1955); Yu v. Albany Ins. Co., 281 F.3d 803, 806 (9th Cir.2002).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Joseph v. Inter-Ocean Insurance Agency, Inc.
59 V.I. 820 (Supreme Court of The Virgin Islands, 2013)
Church & Dwight Co., Inc. v. United States
362 F. Supp. 2d 1360 (Court of International Trade, 2005)
Die-Cutting Diversified, Inc. v. United Nat. Ins. Co.
353 F. Supp. 2d 1053 (E.D. Missouri, 2004)

Cite This Page — Counsel Stack

Bluebook (online)
362 F.3d 1108, 2004 A.M.C. 773, 2004 U.S. App. LEXIS 5681, 2004 WL 594113, Counsel Stack Legal Research, https://law.counselstack.com/opinion/assicurazioni-generali-spa-v-black-veatch-corp-ca8-2004.