Ashcraft v. Makwa Builders

CourtNew Mexico Court of Appeals
DecidedMay 16, 2019
DocketA-1-CA-35872
StatusUnpublished

This text of Ashcraft v. Makwa Builders (Ashcraft v. Makwa Builders) is published on Counsel Stack Legal Research, covering New Mexico Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ashcraft v. Makwa Builders, (N.M. Ct. App. 2019).

Opinion

ASHCRAFT V. MAKWA BUILDERS

This decision of the New Mexico Court of Appeals was not selected for publication in the New Mexico Appellate Reports. Refer to Rule 12-405 NMRA for restrictions on the citation of unpublished decisions. Electronic decisions may contain computer- generated errors or other deviations from the official version filed by the Court of Appeals.

STATE OF NEW MEXICO for the use and benefit of ASHCRAFT MECHANICAL INC., a New Mexico corporation, Plaintiff/Counterdefendant-Appellee, v. MAKWA BUILDERS, LLC, Defendant/Counterclaimant-Appellant, and STATE OF NEW MEXICO for the use and benefit of ASHCRAFT MECHANICAL, INC., a New Mexico corporation, Plaintiff-Appellee, v. GREAT AMERICAN INSURANCE COMPANY, Defendant-Appellant, and MAKWA BUILDERS, LLC, Third-Party Plaintiff, v. OHIO CASUALTY INSURANCE COMPANY, Third-Party Defendant.

Docket No. A-1-CA-35872 COURT OF APPEALS OF NEW MEXICO May 16, 2019

APPEAL FROM THE DISTRICT COURT OF BERNALILLO COUNTY, Carl J. Butkus, District Judge

COUNSEL

Calvert Menicucci, P.C., Sean R. Calvert, Albuquerque, NM for Appellee

Philip Dabney, P. Reid Griffith, Los Alamos, NM, SMTD LAW LLP, Robert J. Berens, Phoenix, AZ for Appellant.

JUDGES MEGAN P. DUFFY, Judge. WE CONCUR: M. MONICA ZAMORA, Chief Judge, KRISTINA BOGARDUS, Judge

AUTHOR: MEGAN P. DUFFY

MEMORANDUM OPINION

DUFFY, Judge.

{1} This appeal arises from a dispute between a subcontractor, Ashcraft Mechanical, Inc., and a general contractor, Makwa Builders, LLC, over payment and offsets, respectively. Following a bench trial, the district court issued forty-seven findings of fact and fifteen conclusions of law, and granted judgment in favor of Ashcraft on all matters. Makwa appeals. We affirm the district court’s judgment.

BACKGROUND

{2} Makwa was the general contractor on a construction project to build a new student union building for New Mexico Highlands University (NMHU) in the summer of 2010. Makwa hired Ashcraft as a subcontractor. Ashcraft in turn subcontracted parts of its contract and a portion of the work eventually fell to Hays Plumbing & Heating.

{3} Ashcraft submitted a payment application in the amount of $59,336 for work performed through the end of December 2011. About two months later, Makwa informed Ashcraft that its December payment application had been adjusted down to $21,558.08 but was otherwise approved. Ashcraft revised the application to reflect the adjusted amount and resubmitted it to Makwa. Makwa stipulated at trial that it was paid $21,558.08 by NMHU for Ashcraft’s December invoice, but that it did not pay Ashcraft. In this same period, Hays submitted a claim to Makwa’s surety, Great American Insurance Company, alleging it too had not been paid for work performed.

{4} NMHU terminated Makwa’s contract for convenience before construction was complete, and Makwa then terminated its subcontract with Ashcraft. Having not received payment from Makwa for the December payment application, Ashcraft sued Makwa and Great American for breach of contract, violations of the Prompt Payment Act (PPA), NMSA 1978, Sections 57-28-1 to -11 (2001, as amended through 2007), and the Little Miller Act, NMSA 1978, Sections 13-4-18 to -20 (1923, as amended through 2015). Makwa filed an answer and a counterclaim for breach of contract, seeking declaratory relief and an order requiring Ashcraft to indemnify and defend it from Hays’s claim. The district court issued judgment in favor of Ashcraft on all matters.

DISCUSSION

{5} All of the issues presented in this appeal involve mixed questions of law and fact. “[We] review a district court’s interpretation of an unambiguous contract de novo” and effectuate the intent of the parties by adopting a “reasonable construction of the usual and customary meaning of the contract language.” Smith & Marrs, Inc. v. Osborn, 2008- NMCA-043, ¶ 10, 143 N.M. 684, 180 P.3d 1183 (internal quotation marks and citation omitted). “The facts are reviewed to see if they are supported by substantial evidence, but the legal conclusions flowing from those facts are reviewed de novo.” Bank of Santa Fe v. Marcy Plaza Assocs., 2002-NMCA-014, ¶ 12, 131 N.M. 537, 40 P.3d 442; see also Sims v. Sims, 1996-NMSC-078, ¶ 65, 122 N.M. 618, 930 P.2d 153 (“Findings of fact made by the district court will not be disturbed if they are supported by substantial evidence.”). “We review the evidence in the light most favorable to support the trial court’s findings, resolving all conflicts and indulging all permissible inferences in favor of the decision below.” Jones v. Schoellkopf, 2005-NMCA-124, ¶ 8, 138 N.M. 477, 122 P.3d 844.

I. Waivers Were Not a Condition Precedent to Makwa’s Obligation to Offer Payment

{6} Makwa argues that Ashcraft was not entitled to payment because Ashcraft failed to submit lien waivers from its subcontractors, which Makwa claims is a contractual condition precedent to payment. “Generally, a condition precedent is an event occurring subsequently to the formation of a valid contract, an event that must occur before there is a right to an immediate performance, before there is breach of a contractual duty, and before the usual judicial remedies are available.” W. Commerce Bank v. Gillespie, 1989- NMSC-046, ¶ 4, 108 N.M. 535, 775 P.2d 737 (citing 3A A. Corbin, Corbin on Contracts § 628, at 16 (1960)).

{7} The parties’ contract identifies two types of waivers—conditional and unconditional waivers. The conditional waiver states that it becomes effective and that the subcontractor waives its right to assert a lien when the subcontractor has been paid for its work. Rider D to the parties’ contract states that the conditional waiver must be included with Ashcraft’s applications for payment and refers to a form provided within the contract for Ashcraft to use.

{8} Separately, the contract identified unconditional waivers as a “condition precedent” to payment. The unconditional waiver form was different from the conditional waiver form, stating that the subcontractor had already been paid and, therefore, unconditionally waived its right to assert a lien against the project. Rider D states clearly that Ashcraft was required to submit the unconditional waivers “when the check is picked[]up.” Rider D also states:

After the first draw, and prior to the release of [next] payment, [Ashcraft] shall submit unconditional lien waivers from all major suppliers who have submitted Preliminary Lien Notices to Makwa Builders, LLC, or furnished materials and/or labor on this project. . . . This procedure shall take place each month when the subcontractor is to pick[]up his monthly draw check. (Emphasis added.) {9} At trial, Dawn Gurule, Ashcraft’s contract administrator and project coordinator, testified that the parties followed a procedure consistent with Rider D, stating that “I would submit a pay application. And normally I—a lien release would follow with Ashcraft mechanical. Lien releases were then provided from our subcontractors and suppliers to Makwa once we were notified that payment was available.” (Emphasis added.)

{10} The plain, unambiguous language in the contract states that the unconditional lien waivers were a condition precedent to payment, but that these waivers were not due until Ashcraft was to pick up the monthly check; as such, Makwa necessarily had a duty to offer payment to Ashcraft before Ashcraft’s duty to produce the unconditional waivers arose. We conclude that Ashcraft’s duty to submit unconditional lien waivers was a condition precedent to Makwa’s duty to release the payment to Ashcraft, and not a condition precedent to Makwa’s duty to offer the payment in the first place.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

City of Albuquerque v. BPLW Architects & Engineers, Inc.
2009 NMCA 081 (New Mexico Court of Appeals, 2009)
Western Commerce Bank v. Gillespie
775 P.2d 737 (New Mexico Supreme Court, 1989)
Sims v. Sims
930 P.2d 153 (New Mexico Supreme Court, 1996)
Public Service Co. v. Diamond D Construction Co.
2001 NMCA 082 (New Mexico Court of Appeals, 2001)
Jones v. Schoellkopf
2005 NMCA 124 (New Mexico Court of Appeals, 2005)
Seipert v. Johnson
2003 NMCA 119 (New Mexico Court of Appeals, 2003)
Bank of Santa Fe v. Marcy Plaza Associates
2002 NMCA 014 (New Mexico Court of Appeals, 2001)
Smith & Marrs, Inc. v. Osborn
2008 NMCA 043 (New Mexico Court of Appeals, 2008)
Curry v. Great Nw. Ins. Co.
2014 NMCA 31 (New Mexico Court of Appeals, 2013)
Ballou v. Walker
2017 MT 197 (Montana Supreme Court, 2017)
Unified Contractor, Inc. v. Albuquerque Housing Auth.
2017 NMCA 60 (New Mexico Court of Appeals, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
Ashcraft v. Makwa Builders, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ashcraft-v-makwa-builders-nmctapp-2019.