ASCOLESE v. SHOEMAKER CONSTRUCTION CO.

CourtDistrict Court, E.D. Pennsylvania
DecidedApril 19, 2021
Docket2:18-cv-01864
StatusUnknown

This text of ASCOLESE v. SHOEMAKER CONSTRUCTION CO. (ASCOLESE v. SHOEMAKER CONSTRUCTION CO.) is published on Counsel Stack Legal Research, covering District Court, E.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
ASCOLESE v. SHOEMAKER CONSTRUCTION CO., (E.D. Pa. 2021).

Opinion

IN THE UNITED STATES DISTRICT COURT FOR THE EASTERN DISTRICT OF PENNSYLVANIA

: DON ASCOLESE, : CIVIL ACTION : : Plaintiff, : : v. : No. 18-1864 : SHOEMAKER CONSTRUCTION CO., : et al., : : Defendants. : :

Goldberg, J. April 19, 2021

MEMORANDUM OPINION

This is a qui tam action brought on behalf of the United States of America under the False Claims Act (“FCA”) by Plaintiff-Relator Don Ascolese (“Relator”). Relator alleges that Defendants Shoemaker Construction Co. (“Shoemaker”), Shoemaker Synterra, a JV1 (“SSAJV”),2 and McDonough Bolyard Peck (“MBP”) engaged in a scheme to defraud the government by submitting false claims for payment to the Philadelphia Housing Authority (“PHA”) for deficient construction work performed by Defendants in connection with a public housing project funded by the United States Department of Housing and Urban Development (“HUD”). Defendants have each moved to dismiss all claims pursuant to Federal Rules of Civil Procedure 12(b)(6) and 9(b), contending that the Amended Complaint fails to meet threshold

1 SSAJV is a joint venture between Shoemaker, “a major East Coast builder,” and a developer, Synterra LTD. (Am. Compl. ¶ 7.)

2 Defendant SSAJV is incorrectly named as “Shoemaker Synterra JV” in the Amended Complaint. pleading requirements. For the reasons stated below, I will grant in part and deny in part the motions. I. FACTUAL AND PROCEDURAL BACKGROUND At this stage of the litigation, I am required to take the facts directly from the Amended Complaint.3

A. The Alleged Scheme In July 2014, HUD awarded PHA a $30 million grant to build mixed-income homes in North Philadelphia (the “Project”). This project involved the construction of 89 new rental units that were “a mix of two and three-story townhomes, including several disability accessible units . . . near the Temple University campus.” (Am. Compl. ¶ 12.) PHA designated Defendant SSAJV as the construction manager for the Project. Defendant MBP was hired in 2017 as “an independent Quality Assurance/Quality Control Manager.” (Id. at ¶ 8.) Relator was employed by MBP as a Quality Assurance/Quality Control Manager and was hired for the Project on May 31, 2017.

MBP was hired to perform the following services: (1) “constructability review services for several building disciplines, including architectural, structural, civil-site, mechanical, electrical, plumbing, fire protection/life safety”; (2) “a comprehensive review of the Project’s construction documents, including verifying that the design documents adhered to the Project’s Program of Requirements”; (3) “coordination of the various disciplines being performed by the design professional”; (4) “assess the site logistics planning for site access, utility and adjacent facilities

3 When deciding a motion to dismiss for failure to state a claim pursuant to Federal Rule of Civil Procedure 12(b)(6), a district court must assume the veracity of all well-pleaded facts found in the complaint. Ashcroft v. Iqbal, 556 U.S. 662, 679 (2009). Thus, I will assume that all the facts found in the Amended Complaint are true for purposes of Defendants’ Rule 12(b)(6) and 9(b) arguments. coordination”; and (5) “develop a Quality Assurance/Quality Control [] plan that included, among other things, review of various project drawings, performance management, inspecting and verifying construction activities, noting any construction deficiencies, and various document and record keeping functions.” (Id. at ¶¶ 13–15.)

As part of MBP’s contract, Relator, as the Project’s Quality Assurance/Quality Control Manager, was required to maintain a Project Deficiency List. Relator alleges that over the course of his six months on the Project, he observed a number of deficiencies in “concrete work,” which he noted in his deficiency log and reported to his supervisors at MBP and “the contractors.” (Id. at ¶¶ 34, 47.) Relator attributes these deficiencies to the Project’s running behind schedule: “it soon became apparent that the original time frame for placing the concrete foundation during warmer Fall weather was passing, and the Project went into a ‘hurry-up’ mode where the sole emphasis was on completing the work, even if it meant cutting corners, so as not to incur significant penalties from PHA and HUD for late completion of work.” (Id. at ¶ 27.) Relator alleges that “[t]his cutting of corners took an ominous turn when defendants began to ignore

fundamental safety issues.” (Id. at ¶ 28.) One of the deficiencies in concrete work identified by Relator was SSAJV’s alleged “backfilling” over frozen ground in violation of “Division 31, Earthwork Sec. 31.” (Id. at ¶ 30.) Relator claims that during the installation of pilings, “the Project encountered buried obstructions and the soil was frozen, which meant that it could not be used safely as backfill under the structural concrete slab in Building K of the Project.” (Id. at ¶ 28.) Relator asserts that in his December 26, 2017 deficiency log, he made a notation regarding the frozen soil: “backfilling inside ‘K’ Building on top of frozen ground.” (Id. at ¶ 30.) Relator states that when he noted this deficiency and complained, he was told that “another contractor, Ambric Technology Corp., had provided . . . a report claiming that the frost had been removed from that area.” (Id. at ¶ 31.) Relator subsequently spoke to “an elderly man” who claimed that he worked for this other contractor and had witnessed the removal of the frozen soil. (Id. at ¶ 32.) Based on Relator’s conversation with this person, he asserts that the report on the removal of frozen soil must have been fraudulently created by SSAJV

and the frozen soil never removed because “[g]iven the depth of the freeze line and the large area containing frozen soil, it would have required equipment and manpower to accomplish such a task and the conditions at the site simply would not have permitted equipment to access this area.” (Id. at ¶¶ 32, 49.) Relator also alleges that SSAJV failed to allow concrete used in foundational walls and slabs to fully cure before the forms were removed and that steel, horizontal rebar was not used in the concrete foundational walls as required by the standards of the American Concrete Institute (“ACI”), the Philadelphia Building Code, and the contract with PHA.4 (See id. at ¶¶ 16–24, 33– 43, 47.) For example, Relator claims that: • On October 21, 2017, Relator raised a concern with “Superintendent Tice” that the “1st floor slab that was placed yesterday at 1925 N. 9th Street” was not cured properly. (Id. at ¶¶ 36, 39.)

• On October 31, 2017, the Project Structural Engineer, Megan Holloway, “issued a report noting the concrete wall forms had been removed and noting that such an occurrence was allowed so long as the temperature remained above 50 degrees,” and “[s]he recommended that the contractor provide adequate thermal protection, but this was never done.” (Id. at ¶ 40.)

• The next day, after the report from the Project Structural Engineer, two project and construction engineers from PHA exchanged emails, copying Relator, and “noted the removal of the [concrete] forms and backfilling and said: ‘[t]his does not seem to be in accordance with ACI standards.’” (Id. at ¶ 41.)

4 Although not the focus of his claims under the FCA, Relator also asserts that “the grade beam for 1943-45-47-39 East side (rear) of the properties was not centered over the top of the piling and while some variance was permitted, not in the 8 to 16-inch variance noted at the site.” (Am. Compl.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States Ex Rel. Grubbs v. Kanneganti
565 F.3d 180 (Fifth Circuit, 2009)
Bell Atlantic Corp. v. Twombly
550 U.S. 544 (Supreme Court, 2007)
Ashcroft v. Iqbal
556 U.S. 662 (Supreme Court, 2009)
Burtch v. Milberg Factors, Inc.
662 F.3d 212 (Third Circuit, 2011)
In Re: Rockefeller Center Properties, Inc. Securities Litigation, Charal Investment Company Inc., a New Jersey Corporation C.W. Sommer & Co., a Texas Partnership, on Behalf of Themselves and All Others Similarly Situated Alan Freed Jerry Crance Helen Scozzanich Sheldon P. Langendorf Rita Walfield Robert Flashman Renee B. Fisher Foundation Inc. Frank Debora Wilson White Stanley Lloyd Kaufman, Jr. Joseph Gross v. David Rockefeller Goldman Sachs Mortgage Co. Goldman Sachs Group Lp Goldman Sachs & Co. Whitehall Street Real Estate Limited Partnership v. Wh Advisors Inc. v. Wh Advisors Lp v. Daniel M. Neidich Peter D. Linneman Richard M. Scarlata Frank Debora Wilson White Stanley Lloyd Kaufman, Jr. Joseph Gross, Charal Investment Company Inc., a New Jersey Corporation C.W. Sommer & Co., a Texas Partnership, on Behalf of Themselves and All Others Similarly Situated Alan Freed Jerry Crance Helen Scozzanich Sheldon P. Langendorf Rita Walfield Robert Flashman Renee B. Fisher Foundation Inc. Frank Debora Wilson White Stanley Lloyd Kaufman, Jr. Joseph Gross v. David Rockefeller Goldman Sachs Mortgage Co. Goldman Sachs Group Lp Goldman Sachs & Co. Whitehall Street Real Estate Limited Partnership v. Wh Advisors Inc. v. Wh Advisors Lp v. Daniel M. Neidich Peter D. Linneman Richard M. Scarlata Charal Investment Company Inc. C.W. Sommer & Co. Renee B. Fisher Foundation Helen Scozzanich Jerry Crance Alan Freed Sheldon P. Langendorf Rita Walfield Robert Flashman
311 F.3d 198 (Third Circuit, 2002)
Thomas Foglia v. Renal Ventures Management
754 F.3d 153 (Third Circuit, 2014)
Lincoln Benefit Life Co. v. AEI Life, LLC
800 F.3d 99 (Third Circuit, 2015)
Hutchins v. Wilentz, Goldman & Spitzer
253 F.3d 176 (Third Circuit, 2001)
United States Ex Rel. Schmidt v. Zimmer, Inc.
386 F.3d 235 (Third Circuit, 2004)
Brown v. Daniels
128 F. App'x 910 (Third Circuit, 2005)
United States Ex Rel. Petras v. Simparel, Inc.
857 F.3d 497 (Third Circuit, 2017)
United States Ex Rel. Spay v. CVS Caremark Corp.
875 F.3d 746 (Third Circuit, 2017)
William O'Hara v. NIKA Technologies, Inc.
878 F.3d 470 (Fourth Circuit, 2017)
USA, ex rel. v. UPMC
946 F.3d 162 (Third Circuit, 2019)
Smith v. Carolina Medical Center
274 F. Supp. 3d 300 (E.D. Pennsylvania, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
ASCOLESE v. SHOEMAKER CONSTRUCTION CO., Counsel Stack Legal Research, https://law.counselstack.com/opinion/ascolese-v-shoemaker-construction-co-paed-2021.