Arundel Corp. v. United States

121 Ct. Cl. 741, 1952 U.S. Ct. Cl. LEXIS 172, 1952 WL 5928
CourtUnited States Court of Claims
DecidedMarch 4, 1952
DocketNo. 46210
StatusPublished
Cited by1 cases

This text of 121 Ct. Cl. 741 (Arundel Corp. v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Arundel Corp. v. United States, 121 Ct. Cl. 741, 1952 U.S. Ct. Cl. LEXIS 172, 1952 WL 5928 (cc 1952).

Opinion

JoNes, Chief Judge,

delivered the opinion of the court:

Plaintiff claims damages for alleged excess costs, extra work, and delays under a contract in connection with a flood control project authorized as a public work under the National Industrial Recovery Act.. The entire project covered areas in three counties in the Muskingum river valley in Ohio. It involved the construction of a number of dams, reservoirs, and levees, as well as the relocation of parts of nine different railroad lines and several utility lines.

Contracts for different phases of the extensive project were made with various companies. The relocation of the railroad lines required the construction of 11 bridges, the contract for which was awarded to the Mt. Vernon Bridge Company. The contract in suit was for the relocation of 14.6 miles of the Wheeling and Lake Erie Railway line. This 14.6 miles included 719.66 feet of track to be laid on the three bridges to be constructed by the Mt. Vernon Bridge Company on the new Wheeling and Lake Erie line.

The progress of the various companies on the project naturally affected to some extent the work of plaintiff, and the Corps of Engineers undertook to coordinate the timing of the work of the various contractors, and especially that of the Mt. Vernon Bridge Company, with the several railroad relocation contractors. The Government’s contracting officer for the contracts of both the plaintiff and the Mt. Vernon Bridge Company was the district engineer at Zanesville, Ohio.

Under the contract, pertinent provisions of which are set forth in findings 67 through 117, plaintiff was required to relocate 139,870 feet of main and side track. Plaintiff was to do all the necessary clearing, grubbing, and grading for [813]*813the roadbed, to lay the ties and tracks, to build underpasses, trestles, culverts, and drainage facilities, and to remove the ties, tracks and bridges from the abandoned portion of the old line. Plaintiff’s bid covered unit prices for 80 separate items. Plaintiff was to furnish all labor and materials and do all work necessary for relocation in accordance with the specifications. Findings 5 and 6 further detail the work required of plaintiff.

Different periods were allotted for different parts of the work, and the entire contract was to be completed within 500 days after notice to proceed. That notice was given on October 26, 1935. During the progress of the work 30 change orders were issued. In 22 of the change orders there were upward adjustments in price. The time for completion was finally extended to September 12,1938, on which date the work was completed and accepted. No liquidated damages were assessed.

Final settlement was made in January 1939, and the following release was signed by plaintiff, specifying certain exceptions:

Pursuant to Article 16 (d) of Contract W968 eng-115 dated July 13, 1935, for relocation of the Wheeling and Lake Erie Eailroad in the Dover Eeservoir, Ohio, we, The Arundel Corporation, of Baltimore, Md., do hereby release the TJ. S. Government of all claims against the Government arising under and by virtue of this contract unless specifically excepted in stated amounts set forth herein.
Additional Cost of Resloping Cuts in 1937 (see claim our letter February 2,1938)-$3,487.22
Additional Cost on Account of Delays to contract by the Government (details to be submitted as soon as cost can be determined) approximately- 85,000. 00
Payment for Excavation for Cast Iron Water Lines (details to be submitted) approximately- 6,000.00
Total_ 94,487.22

It is on these excepted claims that plaintiff is here suing.

DELAYS

There were a number of delays in the performance of the contract, and completion date was ultimately extended to September 12, 1938, a total of 1,049 days for what had [814]*814originally been a 500-day contract. Claim for costs incident to delays was first asserted in January 1939, when plaintiff acknowledged receipt of the proposed release and final voucher. The claim was excepted from the release but no further mention of it was made until plaintiff’s comprehensive claim letter of May 23,1944, to the district engineer who had succeeded the contracting officer.

There were four basic causes for the extension of the time required for completion. First, there were delays in obtaining the necessary rights-of-way. In March 1934, the Muskingum Watershed Conservancy District, a political subdivision of the State of Ohio, had obligated itself to defendant to secure the land for the entire project, by title or easement. The Conservancy District did not complete this until some months after plaintiff received its notice to proceed.

Second, there was much bad weather and wet ground which naturally hampered operations. Third, extra work took up additional time. And finally, completion was delayed by the failure of the Wheeling and Lake Erie Bail-way Company to release its old line after the new one had been completed.

It is not established that any of the delays were caused by any act of omission or commission on the part of defendant or any of its representatives, except in the instance of the extra work. All of the extra work, however, was covered by change orders. Eight of the thirty change orders provided for an extension of time, and the others specifically provided that no additional time would be allowed. Plaintiff accepted all of the change orders without protest, and no appeal was taken from any of them. The work was completed and accepted within the extended time, and no liquidated damages were assessed.

The contract, Article 9, provided that commensurate extensions of time would be granted where there were such delays, but contained nothing as to any further consequences of those delays. None of the delays was shown to be the fault of the defendant and there can be no recovery for damages which might have been caused by those delays. United States v. Foley, 329 U. S. 64; Eisenberg & Sons v. United States, 110 C. Cls. 388, 429.

[815]*815EESLOPING AND BENCHING OP CUTS

Plaintiff’s claim under this heading is for extra costs incurred in the resloping and benching of cuts between stations 7765 and 7851, and between stations 8145 and 8193, performed as a part of extensive corrective work found necessary as a result of severe weather, slides, and erosion. Plaintiff has been paid for this work at the regular rate for unclassified excavation, and is here seeking the excess of its actual costs for that work over the amount paid at the regular contract rate.

The corrective work between stations 7765 and 7851 had been completed by plaintiff on May 22, 1937. Plaintiff protested on May 24, 1937, that the corrective work had been more expensive than the work originally contemplated, and requested that it be permitted to proceed on a force account basis. This would entail the keeping of separate records by the contractor as to the costs incurred in this particular work, and an independent settlement. The defendant denied this request on June 7, 1937, and plaintiff did not appeal that ruling.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
121 Ct. Cl. 741, 1952 U.S. Ct. Cl. LEXIS 172, 1952 WL 5928, Counsel Stack Legal Research, https://law.counselstack.com/opinion/arundel-corp-v-united-states-cc-1952.