Arrow Machine Co. v. Array Connector Corp.

968 N.E.2d 515, 197 Ohio App. 3d 598
CourtOhio Court of Appeals
DecidedDecember 19, 2011
DocketNo. 2010-L-115
StatusPublished
Cited by2 cases

This text of 968 N.E.2d 515 (Arrow Machine Co. v. Array Connector Corp.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Arrow Machine Co. v. Array Connector Corp., 968 N.E.2d 515, 197 Ohio App. 3d 598 (Ohio Ct. App. 2011).

Opinion

Diane V. Grendell, Judge.

{¶ 1} Plaintiff-appellant and cross-appellee, Arrow Machine Co., Ltd., appeals the judgment entry of the Lake County Court of Common Pleas, denying its motion for judgment notwithstanding the verdict or, in the alternative, a motion for new trial. The issues before this court are as follows: (1) whether the jury’s verdicts ought to have been set aside as mutually inconsistent, (2) whether Arrow Machine was entitled to judgment as a matter of law, and (3) whether the trial [601]*601court erred by instructing the jury, in the course of its deliberations, that certain conduct did not constitute a breach of contract. For the reasons that follow, we answer these propositions in the negative and, thus, affirm the judgment of the court below.

{¶ 2} On July 31, 2008, Arrow Machine filed suit against defendant-appellee and cross-appellant, Array Connector Corp., for breach of contract. The complaint alleged that Arrow Machine is an Ohio limited-liability company with its principal place of business in Mentor, Ohio, and Array Connector is a Florida corporation, with its principal place of business in Miami, Florida. It was further alleged that in September 2007, Arrow Machine entered into a purehase-andsupply agreement with Array Connector, “in the city of Mentor, Ohio,” whereby “[Arrow Machine] was to manufacture and sell to [Array Connector] certain goods; and [Array Connector] agreed to purchase from [Arrow Machine] minimum quantities of such goods at specified prices during the three (3) year term of the Agreement.” Arrow Machine claimed that Array Connector breached the agreement by failing “to purchase the minimum quantities of goods” and by attempting “to unilaterally terminate the Agreement, without cause.”1

{¶ 3} On April 29, 2009, Array Connector filed its answer, affirmative defenses, and counterclaim. As the basis for its counterclaim, Array Connector alleged that Arrow Machine was in breach of contract “by failing to fulfill the delivery requirements set forth within * * * the Agreement and by producing parts that were defective and/or non-conforming with the purchase order requirements.”

{¶ 4} The case was tried before a jury.

{¶ 5} The following testimony and evidence was presented at trial.

{¶ 6} On September 14, 2007, John Habe IV, as president of Arrow Machine, and Robert Correa, as materials director for Array Connector, signed a purchase and supply agreement. The purpose of the agreement was to establish a “buy/sell business relationship” between the parties. The agreement began on September 12, 2007, and was to continue in effect until December 31, 2010. An attachment to the agreement provided the pricing for four sizes of machine parts in quantities of 500 to 12,000 and for a “production lead time” of 12 weeks. There was a specified “minimum quarterly quantity” of 500 pieces of each of the four sizes. The agreement contained the following relevant provisions:

[602]*602{¶ 7} “This agreement in no way guarantees the purchase of specific volumes of all or any item listed but does guarantee that the volume will be between the minimum and maximum listed on Attachment A.
* * %
{¶ 8} “Seller [Arrow Machine] agrees to an on time shipping performance of 98% defined as no more than 5 days early and 0 days late to the agreed schedule.
« * * *
{¶ 9} “Failure to meet the requirements of this agreement will subject the agreement to possible termination at the discretion of the buyer [Array Connector]. This contract may be terminated by the buyer without liability to the buyer for failure by the seller to fulfill any or all agreement requirements.”

{¶ 10} On December 3, 2007, Array Connector placed a purchase order for 12,000 pieces of each part. According to the terms of the agreement and the 12-week lead time set forth in the attachment, the parts were to be delivered between February 20, and 25, 2008. The purchase order specified that certain quantities of each part were needed “ASAP.”

{¶ 11} Periodic shipments of parts were made by Arrow Machine beginning in December 2007 and continuing through March 28, 2008. Arrow Machine’s president, Habe, testified that Arrow Machine shipped parts as requested by Array Connector, through a senior buyer, Alexis Rone. Habe testified that Rone would contact Arrow Machine with a request for a given number of parts, typically for immediate shipment. These requests were made periodically and at varying intervals, both before and after the period between February 20 and 25. Correa, testifying on behalf of Array Connector, admitted that it was “standard practice” for Rone to contact Arrow Machine and request parts, as needed, on a periodic basis.

{¶ 12} Between December 2007 and March 2008, there were several occasions when Array Connector returned parts to Arrow Machine as defective. Some of these parts were determined to be conforming and some of these parts were corrected by Arrow Machine and reshipped to Array Connector. Ultimately, all parts were accepted by Array Connector.

{¶ 13} Array Connector did not make a purchase order for the second quarter (April to June) of 2008. During this time, Habe advised Array Connector that pursuant to the agreement, a minimum quantity of parts had to be ordered each quarter. There was also some discussion between the parties about reducing the rate to be charged for orders of smaller quantities.

{¶ 14} On June 23, 2008, Correa sent Habe the following e-mail: “After a considerable amount of time and effort trying to figure out a solution to your [603]*603price increase; we have no choice but to terminate our agreement dated 9/14/0[7] due to Array and Arrow’s failure to agree on unit pricing.”

{¶ 15} Correa testified that his primary reason for terminating the agreement was Arrow Machine’s failure to deliver parts by February 25, 2008, as required by the agreement. In particular, there were two shipments of parts after February 25, 2008. In addition to late shipments, problems with quality were a significant issue. Correa testified that he attempted to negotiate for reduced pricing of small quantities as a way to continue with the agreement despite the quality and delivery issues. Correa admitted that he never advised Habe that he would terminate the agreement due to delivery or quality issues, although he did express his displeasure at the two late deliveries.

{¶ 16} Habe testified that he was under the impression, from speaking with Rone, that Array Connector was not ordering parts because it did not need them. Habe confirmed that he was not made aware of Array Connector’s claims regarding late deliveries and quality until about a year after filing suit.

{¶ 17} On June 9, 2010, the jury returned a verdict against both parties with respect to their breach-of-contract claims, i.e., neither party had proven the other party to be in breach.

{¶ 18} Following the delivery of the verdict, the trial court put the following on the record:

{¶ 19} “For the record, I wanted to put on the record that the jurors had a question during their deliberations. They initially sent one question back to the Court. I wasn’t clear what it was they were asking so I did send Mr. Roberts back in to ask them to clarify that question.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jacovetty v. Browning Ferris Indus.
2021 Ohio 1400 (Ohio Court of Appeals, 2021)
Roberts v. Mike's Trucking, Ltd.
2014 Ohio 766 (Ohio Court of Appeals, 2014)

Cite This Page — Counsel Stack

Bluebook (online)
968 N.E.2d 515, 197 Ohio App. 3d 598, Counsel Stack Legal Research, https://law.counselstack.com/opinion/arrow-machine-co-v-array-connector-corp-ohioctapp-2011.