Armando Benavides v. Anselmo Benavides, Antonio Benavides and A.T. Trucking, L.L.P.

CourtCourt of Appeals of Texas
DecidedNovember 9, 2011
Docket04-11-00252-CV
StatusPublished

This text of Armando Benavides v. Anselmo Benavides, Antonio Benavides and A.T. Trucking, L.L.P. (Armando Benavides v. Anselmo Benavides, Antonio Benavides and A.T. Trucking, L.L.P.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Armando Benavides v. Anselmo Benavides, Antonio Benavides and A.T. Trucking, L.L.P., (Tex. Ct. App. 2011).

Opinion

MEMORANDUM OPINION No. 04-11-00252-CV

Armando BENAVIDES, Appellant

v.

Anselmo BENAVIDES, Antonio Benavides and A.T. Trucking, L.L.P., Appellees

From the 79th Judicial District Court, Jim Wells County, Texas Trial Court No. 06-03-44411 Honorable Richard C. Terrell, Judge Presiding

Opinion by: Catherine Stone, Chief Justice

Sitting: Catherine Stone, Chief Justice Karen Angelini, Justice Rebecca Simmons, Justice

Delivered and Filed: November 9, 2011

REVERSED AND REMANDED

The underlying cause, which has a tortured and protracted procedural history, involves a

dispute among three brothers over a business partnership. Ultimately, the three brothers entered

into a Settlement Agreement to resolve their dispute. This appeal arises from a judgment entered

by the trial court when one brother, Armando, sued the other two brothers, Anselmo and

Antonio, asserting a breach of the Settlement Agreement, requesting a rescission of the

agreement, and requesting damages equal to the redemption price he should have received for his 04-11-00252-CV

partnership interest. After a bench trial, the trial court signed a judgment concluding Anselmo

and Antonio did not breach the Settlement Agreement and that Armando had received sufficient

payment for the redemption value of his partnership interest. On appeal, Armando asserts the

trial court erred in: (1) determining that Anselmo and Antonio did not breach the Settlement

Agreement; and (2) applying the wrong measure of damages to the recovery which Armando

was entitled to receive.

STANDARD OF REVIEW

When the facts surrounding performance of an unambiguous contract are undisputed, the

determination of whether a party has breached the contract is a question of law for the court and

not a question of fact for the jury. United Water Services, L.L.C. v. Zaffirini, No. 04-08-00211-

CV, 2009 WL 136925, at *3 (Tex. App.—San Antonio Jan. 21, 2009, pet. denied) (mem op.);

Meek v. Bishop Peterson & Sharp, P.C., 919 S.W.2d 805, 808 (Tex. App.—Houston [14th Dist.]

1996, writ denied). Stated differently, while the factual determination of what actions were

taken is for the fact finder, whether those actions constitute a breach of contract is a question of

law for the court. In re Cano Petroleum, Inc., 277 S.W.3d 470, 473 (Tex. App.—Amarillo 2009,

orig. proceeding); BACM 2001–1 San Felipe Rd. Ltd. P’ship v. Trafalgar Holdings I, Ltd., 218

S.W.3d 137, 146 (Tex. App.—Houston [14th Dist.] 2007, pet. denied). “We review questions of

law de novo, without affording any particular deference to the legal conclusions of the trial

court.” BACM 2001–1 San Felipe Rd. Ltd. P’ship, 218 S.W.3d at 146; see also Tawes v. Barnes,

340 S.W.3d 419, 425 (Tex. 2011).

ANALYSIS A. Breach

Paragraph four of the Settlement Agreement provided that Anselmo and Antonio “agree

to transfer ownership and possession of all real property and equipment owned by the

-2- 04-11-00252-CV

Partnership (other than as designated below) to Armando Benavides within two weeks from the

date of this agreement.” The agreement was signed on May 27, 2009. The property required to

be transferred under paragraph four included the Partnership’s work trucks. The evidence is

undisputed that Anselmo and Antonio did not transfer possession of the work trucks within the

requisite two-week period. The attorney representing Anselmo and Antonio testified that he sent

a letter on June 19, 2009, after the two-week period for transfer had ended, stating that Anselmo

and Antonio would only give Armando access to the trucks instead of possession of the trucks as

required by the agreement. Moreover, Alfredo Benavides, an employee associated with

Anselmo and Antonio, admitted that he refused to give Armando’s son the keys to the trucks.

Because the evidence conclusively established that Anselmo and Antonio breached the

agreement by refusing to transfer possession of the work trucks within the requisite two-week

period, the trial court erred in concluding that Anselmo and Antonio did not breach the

agreement. 1

B. Remedy

Having determined that the trial court erred in concluding that Anselmo and Antonio did

not breach the agreement, the next question that arises concerns the remedy to which Armando

was entitled. “It is a fundamental principle of contract law that when one party to a contract

commits a material breach of that contract, the other party is discharged or excused from further

performance.” Mustang Pipeline Co. v. Driver Pipeline Co., 134 S.W.3d 195, 196 (Tex. 2004).

However, when a breach is immaterial, the non-breaching party is not excused from future

performance and may sue only for the damages caused by the breach. Harris County Utility

Dist. No. 16 v. Harris County Mun. Dist. No. 36, No. 01-10-00042-CV, 2011 WL 3359698, at *9

1 Although Anselmo and Antonio contend that Armando waived his breach of contract claim by failing to request additional findings of fact and conclusions of law, the trial court initially sent the parties a letter containing its findings and rulings which included a determination “that the Defendants did not breach the MSA.”

-3- 04-11-00252-CV

(Tex. App.—Houston [1st Dist.] Aug. 4, 2011, no pet.) (mem. op.). Whether a party’s breach of

contract is so material as to render the contract unenforceable is a question of fact to be

determined by the trier of fact based on the evaluation of several factors, including: (1) the extent

to which the non-breaching party will be deprived of the benefit that it could have reasonably

anticipated from full performance; (2) the extent to which the injured party can be adequately

compensated for the part of that benefit of which he will be deprived; (3) the extent to which the

party failing to perform or to offer to perform will suffer forfeiture; (4) the likelihood that the

party failing to perform or to offer to perform will cure his failure, taking account of all the

circumstances including any reasonable assurances; and (5) the extent to which the behavior of

the party failing to perform or to offer to perform comports with standards of good faith and fair

dealing. See Hernandez v. Gulf Group Lloyds, 875 S.W.2d 691, 693 & n.2 (Tex. 1994); Hudson

v. Wakefield, 645 S.W.2d 427, 430 (Tex. 1993); Henry v. Masson, 333 S.W.3d 825, 835 (Tex.

App.—Houston [1st Dist.] 2010, no pet.).

In this case, since the trial court determined that Anselmo and Antonio did not breach the

agreement, the trial court, as the trier of fact, did not consider or rule on whether the breach was

material or what remedy was available to Armando for the breach. See Kaspar-Wells v. Mowdy,

No. 03-06-00026-CV, 2007 WL 778135, at *4 (Tex. App.—Austin Mar. 16, 2007, no pet.)

(mem. op.) (holding remand necessary where trial court did not find breach so did not consider

materiality of breach or appropriate remedy).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Mustang Pipeline Co. v. Driver Pipeline Co.
134 S.W.3d 195 (Texas Supreme Court, 2004)
Tawes v. Barnes
340 S.W.3d 419 (Texas Supreme Court, 2011)
In Re Cano Petroleum, Inc.
277 S.W.3d 470 (Court of Appeals of Texas, 2009)
Browning Oil Co., Inc. v. Luecke
38 S.W.3d 625 (Court of Appeals of Texas, 2000)
Henry v. Masson
333 S.W.3d 825 (Court of Appeals of Texas, 2010)
American Bankers Insurance Co. of Florida v. Caruth
786 S.W.2d 427 (Court of Appeals of Texas, 1990)
Hernandez v. Gulf Group Lloyds
875 S.W.2d 691 (Texas Supreme Court, 1994)
Hudson v. Wakefield
645 S.W.2d 427 (Texas Supreme Court, 1983)
Meek v. Bishop Peterson & Sharp, P.C.
919 S.W.2d 805 (Court of Appeals of Texas, 1996)

Cite This Page — Counsel Stack

Bluebook (online)
Armando Benavides v. Anselmo Benavides, Antonio Benavides and A.T. Trucking, L.L.P., Counsel Stack Legal Research, https://law.counselstack.com/opinion/armando-benavides-v-anselmo-benavides-antonio-bena-texapp-2011.