Arizona Public Service Company v. Ferc

Court of Appeals for the Ninth Circuit·Decided June 14, 2019·No. 17-73244·Unpublished

Opinion

NOT FOR PUBLICATION

UNITED STATES COURT OF APPEALS FILED FOR THE NINTH CIRCUIT JUN 14 2019 MOLLY C. DWYER, CLERK U.S. COURT OF APPEALS ARIZONA PUBLIC SERVICE No. 17-73244 COMPANY, FERC No. ER16-1342-001 Petitioner,

v. MEMORANDUM*

FEDERAL ENERGY REGULATORY COMMISSION,

Respondent.

On Petition for Review of an Order of the Federal Energy Regulatory Commission

Argued and Submitted May 15, 2019 San Francisco, California

Before: WALLACE, IKUTA, and CHRISTEN, Circuit Judges.

Petitioner Arizona Public Service Company (APS) challenges two orders of

respondent Federal Energy Regulatory Commission (FERC or “Commission”)

with respect to the termination of the fifty-year-old Edison-Arizona Transmission

Agreement (“Transmission Agreement”) between APS and Southern California

* This disposition is not appropriate for publication and is not precedent except as provided by Ninth Circuit Rule 36-3. Edison Company (“Edison”).1 We have jurisdiction pursuant to 16 U.S.C.

§ 825l(b). We deny the petition in part and grant the petition in part, and remand

to FERC for further proceedings.

1. Reimbursement Payment. On April 1, 2016, APS submitted a notice

of cancellation of the Transmission Agreement, effective July 6, 2016. APS also

sought FERC authorization to pay Edison a $12,688,457 negotiated reimbursement

payment pursuant to section 25.4 of the Transmission Agreement, which APS

would then recover from its ratepayers through its transmission formula rates. On

July 1, 2016, FERC accepted APS’s notice of cancellation, but rejected APS’s

proposal to recover the reimbursement payment from its ratepayers. FERC

concluded that the reimbursement payment calculation constituted “a rate change

under section 205 of the FPA . . . . requir[ing] cost support and Commission

review.” Specifically, FERC explained that APS’s “$12,688,457 final payment to

SoCal Edison . . . supplants two components of the filed rate: the monthly charge

to SoCal Edison and the negotiation process set forth in section 25.4.”

Our review of a FERC decision is limited to whether the decision was arbitrary, capricious, an abuse of discretion, unsupported by substantial evidence, or not in accordance with the law. As long as the record reflects that the decision was based on a consideration of relevant factors

1 As the parties are familiar with the facts, we do not recount them here. 2 and there was no clear error of judgment the decision was not arbitrary or capricious. Cal. Dep’t of Water Res. v. FERC, 341 F.3d 906, 910 (9th Cir. 2003) (internal

citations omitted) (internal quotation marks omitted); see also 5 U.S.C.

§ 706(2)(A). FERC’s conclusion that the reimbursement payment altered the filed

rate in the Transmission Agreement was not arbitrary or capricious. Although

FERC accepted the Transmission Agreement in 1967, that acceptance did not

constitute approval of the yet-to-be-negotiated reimbursement payment because it

was not possible for FERC to say whether the future payment would be “just and

reasonable” without a proposed formula with sufficient specificity.

Rate changes require cost support and FERC review under section 205 of the

Federal Power Act to ensure that the rate is “just and reasonable.” 16 U.S.C.

§ 824d(a); see Mont. Consumer Counsel v. FERC, 659 F.3d 910, 914 (9th Cir.

2011). Courts afford “great deference to the Commission in its rate decisions[,]”

such as when determining whether a rate is “just and reasonable[.]” Morgan

Stanley Capital Grp. Inc. v. Pub. Util. Dist. No. 1, 554 U.S. 527, 532 (2008).

FERC’s order concluded that APS failed to satisfy its burden to provide cost

support for its proposed rate. FERC took issue with APS’s “beneficial use”

calculation because: (1) it rested on a service life estimate that APS failed to

provide or support; (2) “under the Commission’s straight-line, remaining life

3 depreciation method, utilities may implement changes in the estimated service life

prospectively only, over the remaining life of the assets”; and (3) it did not reflect

the under-recovery of any expenses, contrary to APS’s assertions. APS disputes

this rationale, but FERC’s conclusions were reasonable, particularly given the

limited information APS provided as to how it arrived at its “beneficial use”

amount. FERC’s conclusion that APS failed to provide adequate cost support for

its proposed reimbursement payment has not been shown to be arbitrary or

capricious.

2. Expiration Agreement. FERC determined that the 2015 Agreement

Concerning the Expiration of the Edison-Arizona Transmission Agreement (the

“Expiration Agreement”) was subject to FERC’s jurisdiction because it revised the

Transmission Agreement by setting a new termination date. FERC thus ruled that

APS should have filed the Expiration Agreement with FERC pursuant to section

205(c) of the FPA, and FERC referred the matter to its Office of Enforcement for

further examination. The Transmission Agreement does not specify any

termination date; rather it defines its “term” as lasting “during the term of the New

4 Lease, and any and all renewals or extensions thereof.”2 APS asserts that the

Transmission Agreement expired on its own terms on July 6, 2016 because the

relevant lease is the 1966 Four Corners Project Lease with Navajo Nation, which

became effective on July 6, 1966 for a period of 50 years. FERC contends that the

Amendment and Supplement No. 3 to the 1996 Lease (“Supplement No. 3”)

qualifies as an “extension” of the lease under the Transmission Agreement’s

“term” definition because Supplement No. 3 states that “[t]he 1960 Lease and the

1966 Lease . . . are extended to July 6, 2041[.]” But Edison was not a party to

Supplement No. 3, and APS argues that the parties intended for Supplement No. 3

to be a separate lease, not a renewal or extension of the New Lease, for purposes of

determining the Transmission Agreement’s expiration date.

The Commission has interpreted FERC’s Rule 217 to mean that summary

disposition is only appropriate where “there are no material facts in dispute or

because the facts presented by the proponent have been accepted in reaching the

decision.” Pac. Gas & Elec. Co. v. FERC, 746 F.2d 1383, 1386 (9th Cir. 1984);

see 18 C.F.R. § 385.217(b). In reviewing FERC’s decision that summary

2 The New Lease is defined as: “The provisions of the Supplemental Lease from the Navajo Tribe of Indians as lessors, which are applicable to the Four Corners Project, and under which the Participants, as lessees, shall acquire leasehold rights to construct, reconstruct, use, operate, maintain, relocate and remove the Four Corners Project.” 5 disposition is proper, “this court must be satisfied that FERC properly addressed all

the relevant factors in dispute and that a formal hearing was unnecessary for the

Commission to reach its conclusion.” Pac. Gas & Elec. Co, 746 F.2d at 1386. The

record before us is missing key documents, including the 1960 Lease and 1966

Lease. Moreover, there is a material issue of fact as to whether the parties intended

Supplement No.

Free access — add to your briefcase to read the full text and ask questions with AI

Arizona Public Service Company v. Ferc, (9th Cir. 2019).

Arizona Public Service Company v. Ferc (Arizona Public Service Company v. Ferc) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related