TAMM, Circuit Judge:
We are asked to review the Federal Power Commission’s [Commission] denial of an application for a certificate of public convenience and necessity filed by El Paso Natural Gas Company [El Paso]. For reasons set forth below, we remand for further consideration of environmental issues.
I
For present purposes, the facts may be summarized briefly. El Paso is a natural gas company within the scope of the Natural Gas Act.
It is engaged in the business of producing, purchasing, transporting and selling natural gas for resale and direct consumption, and currently operates the only interstate gas pipeline serving the state of Arizona. Petitioner, Arizona Public Service Company [APS], is a combination gas and electric public utility serving various areas of the state of Arizona. APS purchases the entire supply of gas used in its distribution activities from El Paso in addition to large volumes of gas used directly for its electrical generating plants.
In anticipation of a predicted increase of nearly 75% in electrical load between 1970 and 1976, APS launched what may be described simply as a two-fold plan to enlarge its capacity. On the one hand it currently participates in and intends to participate in several large scale coal-fired plant projects, including those at Four Corners and Page, Arizona. On the other hand, on a smaller scale, in order to provide' for incremental increases in capacity, system reliability (particularly during times of peak demand), and to permanently supplement • the larger coal-fired units, APS plans to install ten gas turbine units with a capacity totaling approximately 450 Mw.
These units would be designed to burn oil as well as natural gas, and here lies the heart of the controversy.
At roughly the same time that APS was formulating plans to meet the predicted increase in demand for its services, El Paso was facing a shortage of natural gas available for the interstate market. Accordingly, it advised all customers in its Southern Division System, including APS, that it could not provide significant gas supplies over and above current contract commitments: Similarly, in the recent past, even supplies purchased by those customers under direct sales contracts had occasionally been curtailed. It was with this problem in mind that APS designed its gas turbine units to burn oil as an alternative fuel.
Not yet ready to throw in the towel, however, APS initiated a search for natural gas in Texas, independent of El Paso. The search was fruitful, culminating in an eight year contract with Forest Oil Corporation [Forest] for 50,000,000 Mcf. of natural gas from the Delaware Basin at a rate substantially above that set by the Commission for sales for resale. Since the gas was purchased by APS for direct use in its generators, the transaction was not subject to Commission jurisdiction.
Unable to
move the gas from Texas to facilities in Arizona, APS then contracted with El Paso to construct additional facilities and transport the gas, a proposal which required approval by the Commission.
Accordingly, on March 29, 1971, El Paso filed an application for 'a certificate of public convenience and necessity under Section 7 of the Natural Gas Act
which would authorize it to transport up to 32,000 Mcf. of natural gas per day for APS from the Delaware Basin of West Texas to Arizona and to construct associated facilities, including more than 17 miles of additional pipeline. Several months later a hearing was held and on September 7, 1971, the presiding examiner issued his initial decision denying El Paso’s application.
On March 22, 1972, the Commission affirmed.
II
Many of the issues typically critical to similar applications were not involved in the present controversy. The parties stipulated:
That the proposal set forth in El Paso’s said application does not raise issues respecting the reserves to be transported for APS; the ability of the proposed facilities to transport such reserves in the manner proposed; the cost of the facilities; the ability of El Paso to finance the proposed facilities; economic feasibility; or the ability of APS to utilize such reserves.
The presiding examiner properly went on to consider several other factors involving the public interest,
see
FPC v. Transcontinental Gas Pipe Line Corp., 365 U.S. 1, 81 S.Ct. 435, 5 L.Ed.2d 377 (1961), namely the effect of the purchase on available supply, the end use to which the gas would be put, the preemption of pipeline space that would be involved, the availability of alternative fuel to APS, and the adverse environmental effects that would result from using an alternative fuel such as oil.
The first and dominant factor injected into the balancing process was the price to be paid for the Texas gas, substantially above the field rates set by the
Commission,
and the effect that it might have upon supply. The Commission
reasoned that “approval of the application would result in an incentive for producers to hold their gas off the interstate market [where the lower rates fixed by the Commission prevail] with the objective of packaging it for sale at higher prices.”
The result would be adverse both in terms of the price and the amount of gas available for the interstate market. More specifically, .large users with substantial financial resources such as APS would presumably be able to “tie up ever-dwindling gas reserves in the field”
to the detriment of small consumers and regulated pipelines. On the other hand, if the Commission refused this and similar applications and presumably dealt with the problem comprehensively, it would successfully induce into ■ the interstate market much of the natural gas now devoted to the non-jurisdictional intrastate market.
The Commission next examined the closely related issues of pre-emption and end use. Admittedly utilization of natural gas as boiler fuel is an “inferior” end use. A frequent corollary is that pipeline facilities tied up for such purposes are thereby pre-empted from being used to transport gas for “superior” uses. The Commission concluded that the failure of any opponent to compare APS’s asserted need for gas to be used for electrical generation with the local need for “superior” uses by residential, commercial and industrial customers meant that “we are left only with the general proposition” and therefore the demerit against APS on this score “cannot be said to be more than slight.”
Notably, however, it was still a demerit.
Free access — add to your briefcase to read the full text and ask questions with AI
TAMM, Circuit Judge:
We are asked to review the Federal Power Commission’s [Commission] denial of an application for a certificate of public convenience and necessity filed by El Paso Natural Gas Company [El Paso]. For reasons set forth below, we remand for further consideration of environmental issues.
I
For present purposes, the facts may be summarized briefly. El Paso is a natural gas company within the scope of the Natural Gas Act.
It is engaged in the business of producing, purchasing, transporting and selling natural gas for resale and direct consumption, and currently operates the only interstate gas pipeline serving the state of Arizona. Petitioner, Arizona Public Service Company [APS], is a combination gas and electric public utility serving various areas of the state of Arizona. APS purchases the entire supply of gas used in its distribution activities from El Paso in addition to large volumes of gas used directly for its electrical generating plants.
In anticipation of a predicted increase of nearly 75% in electrical load between 1970 and 1976, APS launched what may be described simply as a two-fold plan to enlarge its capacity. On the one hand it currently participates in and intends to participate in several large scale coal-fired plant projects, including those at Four Corners and Page, Arizona. On the other hand, on a smaller scale, in order to provide' for incremental increases in capacity, system reliability (particularly during times of peak demand), and to permanently supplement • the larger coal-fired units, APS plans to install ten gas turbine units with a capacity totaling approximately 450 Mw.
These units would be designed to burn oil as well as natural gas, and here lies the heart of the controversy.
At roughly the same time that APS was formulating plans to meet the predicted increase in demand for its services, El Paso was facing a shortage of natural gas available for the interstate market. Accordingly, it advised all customers in its Southern Division System, including APS, that it could not provide significant gas supplies over and above current contract commitments: Similarly, in the recent past, even supplies purchased by those customers under direct sales contracts had occasionally been curtailed. It was with this problem in mind that APS designed its gas turbine units to burn oil as an alternative fuel.
Not yet ready to throw in the towel, however, APS initiated a search for natural gas in Texas, independent of El Paso. The search was fruitful, culminating in an eight year contract with Forest Oil Corporation [Forest] for 50,000,000 Mcf. of natural gas from the Delaware Basin at a rate substantially above that set by the Commission for sales for resale. Since the gas was purchased by APS for direct use in its generators, the transaction was not subject to Commission jurisdiction.
Unable to
move the gas from Texas to facilities in Arizona, APS then contracted with El Paso to construct additional facilities and transport the gas, a proposal which required approval by the Commission.
Accordingly, on March 29, 1971, El Paso filed an application for 'a certificate of public convenience and necessity under Section 7 of the Natural Gas Act
which would authorize it to transport up to 32,000 Mcf. of natural gas per day for APS from the Delaware Basin of West Texas to Arizona and to construct associated facilities, including more than 17 miles of additional pipeline. Several months later a hearing was held and on September 7, 1971, the presiding examiner issued his initial decision denying El Paso’s application.
On March 22, 1972, the Commission affirmed.
II
Many of the issues typically critical to similar applications were not involved in the present controversy. The parties stipulated:
That the proposal set forth in El Paso’s said application does not raise issues respecting the reserves to be transported for APS; the ability of the proposed facilities to transport such reserves in the manner proposed; the cost of the facilities; the ability of El Paso to finance the proposed facilities; economic feasibility; or the ability of APS to utilize such reserves.
The presiding examiner properly went on to consider several other factors involving the public interest,
see
FPC v. Transcontinental Gas Pipe Line Corp., 365 U.S. 1, 81 S.Ct. 435, 5 L.Ed.2d 377 (1961), namely the effect of the purchase on available supply, the end use to which the gas would be put, the preemption of pipeline space that would be involved, the availability of alternative fuel to APS, and the adverse environmental effects that would result from using an alternative fuel such as oil.
The first and dominant factor injected into the balancing process was the price to be paid for the Texas gas, substantially above the field rates set by the
Commission,
and the effect that it might have upon supply. The Commission
reasoned that “approval of the application would result in an incentive for producers to hold their gas off the interstate market [where the lower rates fixed by the Commission prevail] with the objective of packaging it for sale at higher prices.”
The result would be adverse both in terms of the price and the amount of gas available for the interstate market. More specifically, .large users with substantial financial resources such as APS would presumably be able to “tie up ever-dwindling gas reserves in the field”
to the detriment of small consumers and regulated pipelines. On the other hand, if the Commission refused this and similar applications and presumably dealt with the problem comprehensively, it would successfully induce into ■ the interstate market much of the natural gas now devoted to the non-jurisdictional intrastate market.
The Commission next examined the closely related issues of pre-emption and end use. Admittedly utilization of natural gas as boiler fuel is an “inferior” end use. A frequent corollary is that pipeline facilities tied up for such purposes are thereby pre-empted from being used to transport gas for “superior” uses. The Commission concluded that the failure of any opponent to compare APS’s asserted need for gas to be used for electrical generation with the local need for “superior” uses by residential, commercial and industrial customers meant that “we are left only with the general proposition” and therefore the demerit against APS on this score “cannot be said to be more than slight.”
Notably, however, it was still a demerit.
Finally, after carefully considering the argument by APS" that it had no
readily available oil reserves and therefore, being landlocked, was subject to the uncertainties inherent in shipment of oil by rail or truck, the Commission found that APS had never in the past been plagued by untimely delivery of oil for use in its boilers. Indeed, it further found that APS had effectively conceded that sufficient supplies of oil could be contracted for, albeit oil with high sulphur content. “[A] fair reading of the record compels a finding that fuel oil is available to APS as an alternative fuel. [N]o plus mark can be said to accrue to the proposal by virtue of the unavailability of an alternative fuel.”
At this juncture, fully aware of the limited scope of our review,
we find no fault with either the conclusions of the Commission or the process applied to juxtapose them. It is the final consideration, the environmental consequences of the proposed agency action, which compels a remand. „
III
The essence of the Commission’s evaluation of environmental consequences is neatly summarized in the following statement by the presiding examiner :
[I]n terms of El Paso’s required showing under the National Environmental Policy Act of 1969, it is clear that no adverse environmental impact would be occasioned by any phase of the proposal. Actually, it is the other side of the coin — the consequences of
not
granting the proposal — which is of the greater import here. In brief, the proposal is entitled to a plus mark on this aspect of the proceeding — but one no greater than would be awarded
any
proposal involving the substitution of gas for oil as boiler fuel.
The examiner went on to reason that if APS were permitted to utilize 50,000,000 Mcf. of natural gas over the eight year period in lieu of the purported 6,000,000 barrels of high sulphur content oil (more than triple APS’s total predicted consumption of oil were the application to be granted), "at some point in time some other community (with ‘rights’, it must be said, equal to those of the Phoenix community) will be required to burn the same quantity of oil with whatever harmful effects flow therefrom.”
Without questioning these conclusions, we are at a loss to test their validity. We can find no indication that an environmental impact statement within the meaning of § 102(2) (C) of the National Environmental Policy Act of 1969 [NEPA]
was filed. Indeed, every indication is that one was not filed.
On
the other hand, no reason was given as to why the statement was not required nor is one apparent.
Even were we to concede the accuracy of the unsupported one sentence conclusion of the examiner, that no adverse environmental impact would result from the construction of 17 miles of additional pipeline and associated facilities, clearly he was correct in observing that the matter of great import was the
failure
to grant the application and the resulting consumption of millions of barrels of oil. In short, with one stroke of the pen the Commission arrived at the very conclusions which concerned those enacting NEPA. Without either meeting the procedural requisites of NEPA or providing us with record evidence of the substance from which conclusions were intended to be drawn, the Commission asks us to hold that it has not abused its discretion.
APS argued -vociferously in its brief that the Commission had failed to properly consider environmental factors: .
The National Environmental Policy Act (NEPA) was intended to require a more sensitive reaction from the Commission than it has evidenced in this case. . . . An agency of the Federal Government must comply with the directives set out in Section 102(2) of NEPA . . .
Section 102(2) of NEPA requires,
inter alia,
that:
all agencies of the Federal Government shall—
(C) include in every recommendation or report on proposals for legislation
and other major Federal actions significantly affecting the quality of the human environment,
a detailed statement by the responsible official on—
(i) the environmental impact of the proposed action,
(ii) any adverse environmental effects which cannot be avoided should the proposal be implemented,
(iii) alternatives to the proposed action,
(iv) the relationship between local short-term uses of man’s environment and the maintenance and enhancement of long-term productivity, and
(v) any irreversible and irretrievable commitments of resources which would be involved in the pro
posed action should it be implemented.
Even were we to accept respondent’s argument that “ [petitioner does not deny that the Commission did consider the appropriate environmental factors, nor does it question the procedures used in making the consideration,” an unlikely conclusion in light of petitioner’s argument as set forth above, it would be to no avail. NEPA makes environmental protection part of the mandate of every federal agency, and each is “not only permitted, but compelled, to take environmental values into account.” Calvert Cliffs’ Coordinating Committee, Inc. v. AEC, 146 U.S.App.D.C. 33, 449 F.2d 1109, 1112 (1971).
The agency may not be permitted to skirt this responsibility, particularly where it may be in the interests of the parties for purposes of expedition or otherwise to overlook these considerations.
The minimum requirement for compliance with the “action — forcing” provisions of NEPA is for the agency to supply a statement of reasons why it believes that an impact statement is unnecessary.
See
Scientists’ Institute for Public Information, Inc. v. AEC, 481 F.2d 1079, 1094-1095 (D.C.Cir. 1973), and Hanly v. Kleindienst, 471 F.2d 823 (2d Cir. 1972), cert. denied, 412 U.S. 908, 93 S.Ct. 2290, 36 L.Ed.2d 974 (1973).
A statement of reasons will serve two functions. It will ensure that the agency has given adequate consideration to the problem and that it understood the statutory standard. In addition, it will provide a focal point for judicial review of the agency’s decision, giving the court the benefit of the agency’s expertise.
Scientists’ Institute for Public Information, Inc. v. AEC,
supra,
481 F.2d at 1095.
Our position today and the remedy we adopt are not without recent precedent. In City of New York v. United States, 337 F.Supp. 150 (E.D.N.
Y.1972), Judge Friendly wrote for a unanimous three judge district court in resolving a similar problem. An action was brought to annul an order of the Interstate Commerce Commission [ICC] which authorized abandonment of a railroad line, consisting of approximately 15 miles of track and used predominantly to service New York harbor, on the ground that the ICC had failed to comply with NEPA. Despite the fact that the issue of applicability of an impact statement was not raised before the hearing examiner, and despite the railroad’s convincing argument that it could not economically continue to run the line in question, the court agreed with plaintiff, first noting that the tardiness of the parties cannot excuse an agency from complying with its responsibilities under NEPA, then stating:
To permit an agency to ignore its duties under NEPA with impunity because we have serious doubts that its ultimate decision will be affected by compliance would subvert the very purpose of the Act and encourage further administrative laxity in this area.
Id.
at 160. The agency “action” involved was negative, like the present case, in the sense that it resulted not in the construction of new facilities but in the exact opposite.
Moreover, the potentially adverse environmental impact related not to the immediate physical features of the
project
— i.
e.
the absence of locomotives and personnel from the area or the physical removal of tracks— but to damage “once removed” yet directly attributable to the
action
— i.
e.
pollution caused by heavy truck traffic which would replace the railroad. The court remanded to the agency for further consideration of the environmental issue within the framework of NEPA. The agency’s initial order was not vacated and the court retained jurisdiction. We opt for the same remedy, and give the Commission ninety days to conduct whatever further proceedings it deems necessary either for the preparation and circulation of an impact statement or for preparation of a statement of reasons as to why an impact statement is unnecessary. The parties shall serve and file any further briefs within twenty days thereafter.
So ordered.