Arizona Public Service Company v. Federal Power Commission, the People of the State of California, Intervenors

483 F.2d 1275, 157 U.S. App. D.C. 272, 5 ERC 1619
CourtCourt of Appeals for the D.C. Circuit
DecidedJuly 30, 1973
Docket72-1636
StatusPublished
Cited by34 cases

This text of 483 F.2d 1275 (Arizona Public Service Company v. Federal Power Commission, the People of the State of California, Intervenors) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Arizona Public Service Company v. Federal Power Commission, the People of the State of California, Intervenors, 483 F.2d 1275, 157 U.S. App. D.C. 272, 5 ERC 1619 (D.C. Cir. 1973).

Opinion

TAMM, Circuit Judge:

We are asked to review the Federal Power Commission’s [Commission] denial of an application for a certificate of public convenience and necessity filed by El Paso Natural Gas Company [El Paso]. For reasons set forth below, we remand for further consideration of environmental issues.

I

For present purposes, the facts may be summarized briefly. El Paso is a natural gas company within the scope of the Natural Gas Act. 1 It is engaged in the business of producing, purchasing, transporting and selling natural gas for resale and direct consumption, and currently operates the only interstate gas pipeline serving the state of Arizona. Petitioner, Arizona Public Service Company [APS], is a combination gas and electric public utility serving various areas of the state of Arizona. APS purchases the entire supply of gas used in its distribution activities from El Paso in addition to large volumes of gas used directly for its electrical generating plants.

In anticipation of a predicted increase of nearly 75% in electrical load between 1970 and 1976, APS launched what may be described simply as a two-fold plan to enlarge its capacity. On the one hand it currently participates in and intends to participate in several large scale coal-fired plant projects, including those at Four Corners and Page, Arizona. On the other hand, on a smaller scale, in order to provide' for incremental increases in capacity, system reliability (particularly during times of peak demand), and to permanently supplement • the larger coal-fired units, APS plans to install ten gas turbine units with a capacity totaling approximately 450 Mw. 2 These units would be designed to burn oil as well as natural gas, and here lies the heart of the controversy.

At roughly the same time that APS was formulating plans to meet the predicted increase in demand for its services, El Paso was facing a shortage of natural gas available for the interstate market. Accordingly, it advised all customers in its Southern Division System, including APS, that it could not provide significant gas supplies over and above current contract commitments: Similarly, in the recent past, even supplies purchased by those customers under direct sales contracts had occasionally been curtailed. It was with this problem in mind that APS designed its gas turbine units to burn oil as an alternative fuel.

Not yet ready to throw in the towel, however, APS initiated a search for natural gas in Texas, independent of El Paso. The search was fruitful, culminating in an eight year contract with Forest Oil Corporation [Forest] for 50,000,000 Mcf. of natural gas from the Delaware Basin at a rate substantially above that set by the Commission for sales for resale. Since the gas was purchased by APS for direct use in its generators, the transaction was not subject to Commission jurisdiction. 3 Unable to *1278 move the gas from Texas to facilities in Arizona, APS then contracted with El Paso to construct additional facilities and transport the gas, a proposal which required approval by the Commission. 4 Accordingly, on March 29, 1971, El Paso filed an application for 'a certificate of public convenience and necessity under Section 7 of the Natural Gas Act 5 which would authorize it to transport up to 32,000 Mcf. of natural gas per day for APS from the Delaware Basin of West Texas to Arizona and to construct associated facilities, including more than 17 miles of additional pipeline. Several months later a hearing was held and on September 7, 1971, the presiding examiner issued his initial decision denying El Paso’s application. 6 On March 22, 1972, the Commission affirmed. 7

II

Many of the issues typically critical to similar applications were not involved in the present controversy. The parties stipulated:

That the proposal set forth in El Paso’s said application does not raise issues respecting the reserves to be transported for APS; the ability of the proposed facilities to transport such reserves in the manner proposed; the cost of the facilities; the ability of El Paso to finance the proposed facilities; economic feasibility; or the ability of APS to utilize such reserves. 8

The presiding examiner properly went on to consider several other factors involving the public interest, see FPC v. Transcontinental Gas Pipe Line Corp., 365 U.S. 1, 81 S.Ct. 435, 5 L.Ed.2d 377 (1961), namely the effect of the purchase on available supply, the end use to which the gas would be put, the preemption of pipeline space that would be involved, the availability of alternative fuel to APS, and the adverse environmental effects that would result from using an alternative fuel such as oil.

The first and dominant factor injected into the balancing process was the price to be paid for the Texas gas, substantially above the field rates set by the *1279 Commission, 9 and the effect that it might have upon supply. The Commission 10 reasoned that “approval of the application would result in an incentive for producers to hold their gas off the interstate market [where the lower rates fixed by the Commission prevail] with the objective of packaging it for sale at higher prices.” 11 The result would be adverse both in terms of the price and the amount of gas available for the interstate market. More specifically, .large users with substantial financial resources such as APS would presumably be able to “tie up ever-dwindling gas reserves in the field” 12 to the detriment of small consumers and regulated pipelines. On the other hand, if the Commission refused this and similar applications and presumably dealt with the problem comprehensively, it would successfully induce into ■ the interstate market much of the natural gas now devoted to the non-jurisdictional intrastate market.

The Commission next examined the closely related issues of pre-emption and end use. Admittedly utilization of natural gas as boiler fuel is an “inferior” end use. A frequent corollary is that pipeline facilities tied up for such purposes are thereby pre-empted from being used to transport gas for “superior” uses. The Commission concluded that the failure of any opponent to compare APS’s asserted need for gas to be used for electrical generation with the local need for “superior” uses by residential, commercial and industrial customers meant that “we are left only with the general proposition” and therefore the demerit against APS on this score “cannot be said to be more than slight.” 13 Notably, however, it was still a demerit.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pacific Legal Foundation v. Cecil B. Andrus
657 F.2d 829 (Sixth Circuit, 1981)
Peshlakai v. Duncan
476 F. Supp. 1247 (District of Columbia, 1979)
Barcelo v. Brown
478 F. Supp. 646 (D. Puerto Rico, 1979)
Committee for Auto Responsibility v. Solomon
603 F.2d 992 (D.C. Circuit, 1979)
Joseph v. Adams
467 F. Supp. 141 (E.D. Michigan, 1978)
Norway Hill Preservation & Protection Ass'n v. King County Council
552 P.2d 674 (Washington Supreme Court, 1976)
Morgan v. United States Postal Service
405 F. Supp. 413 (W.D. Missouri, 1975)
No Oil, Inc. v. Occidental Petroleum Corp.
50 Cal. App. 3d 8 (California Court of Appeal, 1975)
McDowell v. Schlesinger
404 F. Supp. 221 (W.D. Missouri, 1975)

Cite This Page — Counsel Stack

Bluebook (online)
483 F.2d 1275, 157 U.S. App. D.C. 272, 5 ERC 1619, Counsel Stack Legal Research, https://law.counselstack.com/opinion/arizona-public-service-company-v-federal-power-commission-the-people-of-cadc-1973.