Arcole Construction Co. v. State

11 Ill. Ct. Cl. 423, 1941 Ill. Ct. Cl. LEXIS 30
CourtCourt of Claims of Illinois
DecidedJanuary 14, 1941
DocketNo.2560
StatusPublished

This text of 11 Ill. Ct. Cl. 423 (Arcole Construction Co. v. State) is published on Counsel Stack Legal Research, covering Court of Claims of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Arcole Construction Co. v. State, 11 Ill. Ct. Cl. 423, 1941 Ill. Ct. Cl. LEXIS 30 (Ill. Super. Ct. 1941).

Opinion

Mr. Chief Justice Hollerich

delivered the opinion of the court:

On or about December 14, 1933, respondent, through its Department of Public Works and Buildings, Division of Highways, mailed to claimant and other contractors a certain “Notice to Contractors,” soliciting bids or proposals for the reconstruction of the pavement on Roosevelt Road in the City of Chicago, from Ashland Avenue to Canal Street, a distance of 1.3972 miles.

In and by such notice prospective bidders were advised that plans for said work prepared by the Department of Public Works and Buildings were available at the office of the District Engineer, and could be purchased, at the office of the Division of Highways at Springfield, Illinois.

Claimant purchased a copy of such plans; examined and studied the same, and inspected the site of the proposed improvement before submitting its bid for the doing of the work. In and* by its bid the claimant proposed to furnish all labor and materials necessary to complete said improvement according to said plans and specifications for the sum of $164,272.75, and at the unit prices therein specified.

Claimant was the low bidder on the project and was awarded the contract. On January 30, 1934 the respondent entered into a written agreement with claimant whereby the claimant agreed to do all the work, furnish all materials and all labor necessary to complete the work in accordance with the plans and specifications therein described, which plans and specifications were by said contract made essential documents and a part of said contract. Respondent agreed to pay the claimant for the work performed on a unit basis at the prices specified in claimant’s proposal or bid.

The plans showed, among other items, a cross section of the proposed 9-inch Portland cement concrete pavement and a “Typical Cross Section for Existing Granite Block pavement.”

The description of the improvement, as shown by the special provisions of the plans and specifications is as follows:

“This improvement consists of constructing a P. C. C. pavement between the existing curbs exclusive of the portion occupied by the Chicago Surface Lines, in accordance with the typical cross section as shown in the plans.”

The aforementioned ‘ ‘ Typical Cross Section for Existing Granite Block Pavement” (the pavement then in place) shows, among other things, a granité block pavement with an 8-inch Portland cement concrete base course. The evidence also shows that there was a two-inch sand cushion between said granite block pavement and said base course. The proposed improvement contemplated the removal óf the existing pavement and base course to at least three inches below the sub-grade of the proposed pavement and the construction of a new pavement in accordance with the plans and specifications.

Claimant commenced work under its contract about March 30, 1934, and started operations with a steam shovel on the north side of the street in order to remove the granite block pavement, and followed shortly thereafter with other steam shovels to remove the 8-inch Portland cement concrete base course. Claimant then discovered that on the north side of the street extending through the entire length of the proposed improvement, there was an abandoned street car track foundation of very tough Portland cement concrete, which had imbedded in it the wooden ties formerly part of the street car track construction. This street car track foundation was approximately eighteen (18) feet in width and had a thickness of from sixteen to twenty inches and was bonded to the eight-inch concrete described in the “typical cross section” above referred to. The requirement of the specifications for excavation to at least three inches below the sub-grade of the proposed pavement necessitated the removal of the top three inches of the old street car track foundation. Such foundation was of very tough material and could not be removed in the same manner as the eight-inch Portland cement concrete base, to wit, by steam shovels, but had to be cut and chipped off by compressed air' methods.

Upon the discovery of the old street car track foundation claimant notified the officials of the Highway Department and a meeting with such officials was held on the site of the work. Claimant demonstrated'to the representatives of respondent that said street car track foundation, or so much of it as was required to be removed, could not be removed by the usual and ordinary means employed. In an effort to solve the problem it was suggested that the grade of the proposed pavement be raised to such an extent that it would be unnecessary to interfere with the street car track foundation, but on account of drainage plans on the job, such suggestion was found to be impracticable. Several other suggestions were made, but on account of the refusal of the Federal Bureau of Highways to consent to a base of less than nine inches in thickness on the proposed improvement, it was impossible to change the plans, and the claimant proceeded with the work in accordance with the plans and specifications. Thereafter claimant completed the work required to be done under the contract, and the same was accepted and approved by the proper authorities of the respondent.

On December 26, 1934, claimant filed its complaint herein “for damages accruing to it in the sum of $24,944.85 for the cost of equipment, wages and other expenditures caused by being compelled to cut out and break loose the old concrete paving base on said project from the old street car track foundation and chipping and cutting the old street car track foundation to the sub-grade of the new pavement,” and based its claim upon the following contentions, to wit:

A) That the plans and specifications for the improvement prepared by the respondent did not truly, accurately and correctly set forth the nature, character and amount of work to be performed by the claimant in.the construction of the improvement.

B) That thereby the claimant was deceived and misled in making its proposal, and in entering into said contract.

C) That as a result thereof claimant was put to an expense of $24,944.85, which it would not have been required to expend had the conditions as to the sub-grade been as represented by the respondent in the plans and specifications.

Final payment estimate under the contract was scheduled for payment on January 14, 1935, and supplemental final payment estimate was scheduled for payment on June 28, 1935, and actual payments were made shortly after said respective dates.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hollerbach v. United States
233 U.S. 165 (Supreme Court, 1914)
Christie v. United States
237 U.S. 234 (Supreme Court, 1915)
United States v. Spearin
248 U.S. 132 (Supreme Court, 1918)
United States v. Atlantic Dredging Co.
253 U.S. 1 (Supreme Court, 1920)
Hunt v. Chicago Horse & Dummy Railway Co.
13 N.E. 176 (Illinois Supreme Court, 1887)
People ex rel. Stead v. Spring Lake Drainage & Levee District
97 N.E. 1042 (Illinois Supreme Court, 1912)
Keithley v. County of Clark
206 Ill. App. 500 (Appellate Court of Illinois, 1917)

Cite This Page — Counsel Stack

Bluebook (online)
11 Ill. Ct. Cl. 423, 1941 Ill. Ct. Cl. LEXIS 30, Counsel Stack Legal Research, https://law.counselstack.com/opinion/arcole-construction-co-v-state-ilclaimsct-1941.