Archirodon Construction (Overseas) Company Limited v. General Company for Ports of Iraq

District Court, District of Columbia·Decided January 30, 2024·No. Civil Action No. 2022-1571·Published

Opinion

UNITED STATES DISTRICT COURT FOR THE DISTRICT OF COLUMBIA

ARCHIRODON CONSTRUCTION (OVERSEAS) COMPANY LIMITED,

Petitioner, v. Civil Action No. 22-1571 (JEB)

GENERAL COMPANY FOR PORTS OF IRAQ, et al.,

Respondents.

MEMORANDUM OPINION

Petitioner Archirodon Construction (Overseas) Company Limited filed this action to recognize and enforce an arbitration award against Respondents General Company for Ports of Iraq (GCPI), the Ministry of Transport of the Republic of Iraq, and the Republic of Iraq itself. The case arises from a contractual dispute regarding the design and construction of a staging pier and breakwater for the Al Faw Grand Port in Iraq. On November 25, 2019, a tribunal of the International Court of Arbitration of the International Chamber of Commerce in Geneva, Switzerland, issued an award in favor of Petitioner. Archirodon now moves to enforce the award under Chapter 2 of the Federal Arbitration Act, 9 U.S.C. § 201, et seq., which codifies the 1958 Convention on the Recognition and Enforcement of Foreign Arbitral Awards (New York Convention). Although Respondents received a summons, the Petition, and notice of suit in October 2023, they have never appeared. As confirmation of the award is appropriate, the Court will grant the Petition.

I. Background The underlying dispute arose out of a November 22, 2012, contract between Archirodon and GCPI — “a department of the [Iraqi] Ministry of Transport” — for the design and construction of a staging pier and breakwater for the Al Faw Grand Port in Iraq. See ECF No. 1 (Pet.), ¶¶ 6, 14; ECF No. 1-4 (Contract) at 4–5. GCPI agreed to pay Archirodon a lump sum of €204,166,506.38 for its work, and Archirodon agreed to complete the project within eighteen months from the commencement date. See Pet., ¶ 16. The contract also contained an arbitration clause, which stipulated the parties’ intention to submit any disputes to the International Chamber of Commerce in Switzerland for arbitration. Id., ¶ 19. The Iraq Minister of Transportation Hadi Al Ameri signed the contract on behalf of GCPI. Id., ¶ 20.

During construction, Archirodon experienced a number of delays related to the access road to the construction site, the soil-settlement rate at the site, and foreign-workforce recruitment. Id., ¶¶ 21–24. As a result, it did not complete construction of the staging pier and breakwater by the deadline. Id., ¶ 25. As these complications arose, the parties could not agree on whether Archirodon was entitled to extensions of time and reimbursement of additional costs or whether GCPI was instead entitled to impose contractual delay damages. See ECF No. 1-2 (Final Award), ¶¶ 88–111.

To resolve these differences, the parties commenced arbitration proceedings on March 24, 2016, in the International Court of Arbitration of the International Chamber of Commerce sitting in Geneva. See Pet., ¶ 26. The arbitration tribunal, consisting of three arbitrators, unanimously rendered a foreign arbitral award of €82,944,276.76, in addition to $7,490,565.74 in costs and expenses, in favor of Petitioner on November 25, 2019. Id., ¶¶ 37–39. The tribunal also held that Archirodon was not entitled to pre-award interest since such claim had been raised

too late in the proceedings. See Final Award, ¶ 22.5. GCPI has refused to pay the award to Archirodon. See Pet., ¶ 4.

Archirodon then filed this action pursuant to Section 207 of the FAA on June 3, 2022, to confirm the arbitral award against GCPI and also impose liability on two additional parties, the Ministry of Transport and the Republic of Iraq. See Pet., ¶¶ 1, 54, 67. Petitioner effected service on Respondents in October 2023. See ECF Nos. 12 (First Certificate of Service), 13 (Second Certificate of Service), 14-2 (GCPI First Return Receipt); 15-2 (Ministry of Transport First Return Receipt); 16-2 (Iraq Return Receipt). Although no Respondent has filed an answer to the Petition, the Court nonetheless proceeds with a full analysis. II. Legal Standard Judicial review of arbitral awards is “extremely limited.” Kurke v. Oscar Gruss & Son, Inc., 454 F.3d 350, 354 (D.C. Cir. 2006). “Courts . . . do not sit to hear claims of factual or legal error by an arbitrator as an appellate court does in reviewing decisions of lower courts.” United Paperworkers Int’l Union v. Misco, Inc., 484 U.S. 29, 38 (1987). A court is thus not “authorized to reconsider the merits of an award even though the parties may allege that the award rests on errors of fact or on misinterpretation of the contract.” Id. at 36; see Steelworkers v. Enter. Wheel & Car Corp., 363 U.S. 593, 599 (1960) (holding award should not be rejected simply because court’s “interpretation of the contract is different from arbitrator’s”).

A federal court must instead confirm an award even if it “is convinced [the arbitrator]

committed serious error.” Major League Baseball Players Ass’n v. Garvey, 532 U.S. 504, 509 (2001) (quoting Eastern Associated Coal Corp. v. Mine Workers, 531 U.S. 57, 62 (2000)). An award, in other words, is legitimate so long as the “arbitrator is even arguably construing or applying the contract and acting within the scope of his authority.” Id. “It is only when the

arbitrator strays from interpretation and application of the agreement and effectively dispense[s] his own brand of industrial justice that his decision may be unenforceable.” Id. (quoting Enter. Wheel, 363 U.S. at 597) (quotation marks omitted). III. Analysis The Court first considers its jurisdiction to entertain the Petition. It next addresses grounds for non-enforcement, joint and several liability, and the proper calculation of the Award.

A. Jurisdiction 1. Subject-Matter Jurisdiction There are two prerequisites for this Court’s subject-matter jurisdiction here. “First, there must be a basis upon which a court in the United States may enforce a foreign arbitral award; and second, [Respondents] must not enjoy sovereign immunity from such an enforcement action.” Diag Human, S.E. v. Czech Republic-Ministry of Health, 824 F.3d 131, 134 (D.C. Cir. 2016) (quoting Creighton Ltd. v. Gov’t of the State of Qatar, 181 F.3d 118, 121 (D.C. Cir. 1999)).

As to the first, the Federal Arbitration Act codifies the New York Convention into U.S.

law. See 9 U.S.C. §§ 201–08. It provides that “[a]n action or proceeding falling under the Convention shall be deemed to arise under the laws and treaties of the United States. The district courts . . . shall have original jurisdiction over such an action or proceeding, regardless of the amount in controversy.” Id. § 203. An arbitral award between non-U.S. parties, like the one at issue here, “falls under the Convention” as long as it “arise[s] out of a legal relationship, whether contractual or not, which is considered as commercial.” Id. § 202.

There is no doubt that the Award arises out of such a relationship and thus falls under the Convention. The fact that Iraq was not a signatory to the New York Convention at the time of the final award is immaterial. “If the place of the award is in the territory of a party to the

Convention, all other Convention states are required to recognize and enforce the award, regardless of the citizenship or domicile of the parties to the arbitration.” BCB Holdings Ltd. v. Gov. of Belize, 110 F. Supp. 3d 233, 243 (D.D.C. 2015) (cleaned up). The arbitral tribunal issued the Award in Switzerland, and Petitioner seeks enforcement in the United States. As both countries are parties to the New York Convention, that Convention applies. See, e.g., id. (reaching same conclusion based on similar facts).

Free access — add to your briefcase to read the full text and ask questions with AI

Archirodon Construction (Overseas) Company Limited v. General Company for Ports of Iraq, (D.D.C. 2024).

Archirodon Construction (Overseas) Company Limited v. General Company for Ports of Iraq (Archirodon Construction (Overseas) Company Limited v. General Company for Ports of Iraq) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

United Steelworkers v. Enterprise Wheel & Car Corp.
363 U.S. 593 (Supreme Court, 1960)
Creighton Ltd. v. Government of Qatar
181 F.3d 118 (D.C. Circuit, 1999)
Roeder v. Islamic Republic of Iran
333 F.3d 228 (D.C. Circuit, 2003)
TMR Energy Ltd. v. State Property Fund of Ukraine
411 F.3d 296 (D.C. Circuit, 2005)
Kurke, David S. v. Oscar Gruss & Son
454 F.3d 350 (D.C. Circuit, 2006)
Practical Concepts, Inc. v. Republic of Bolivia
811 F.2d 1543 (D.C. Circuit, 1987)
Transaero, Inc. v. La Fuerza Aerea Boliviana
30 F.3d 148 (D.C. Circuit, 1994)
Oldham v. Korean Air Lines Co., Ltd.
127 F.3d 43 (D.C. Circuit, 1997)
Global Distressed Alpha Fund I LP v. Red Sea Flour Mills Co.
725 F. Supp. 2d 198 (District of Columbia, 2010)
Major League Baseball Players Assn. v. Garvey
532 U.S. 504 (Supreme Court, 2001)
Drc, Inc. v. Republic of Honduras
71 F. Supp. 3d 201 (District of Columbia, 2014)
Bcb Holdings Limited v. Government of Belize
110 F. Supp. 3d 233 (District of Columbia, 2015)